R25-134 RESOLUTION NO. R25-134 2 3 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOYNTON 4 BEACH, FLORIDA, AWARDING INVITATION TO BID NO. PWE25-026B 5 FOR THE BOYNTON BEACH OYER PARK FIRE BOAT UFT PROJECT, 6 ALSO KNOWN AS BOATING SAFETY PROGRAM PH II, TO SEASIDE 7 MARINE CONTRACTORS, AND APPROVING AN AGREEMENT WITH 8 SEASIDE MARINE CONTRACTORS IN THE AMOUNT OF $178,017.50, 9 PLUS A 10% CONTINGENCY OF $17,801.75 FOR A TOTAL NOT TO 10 EXCEED $195,819.25; AND FOR ALL OTHER PURPOSES. 11 12 WHEREAS, the Boynton Beach Boating Safety Project is supported by a grant from the 13 Florida Inland Navigation District ("FIND"), which provides $109,150, representing 50% of the total 14 project cost. This initiative builds upon Phase One, planning, funded by FIND, and supports Phase 15 Two, implementation; and I6 WHEREAS, the project scope includes the installation of new boat lifts at the existing dock, 17 along with associated demolition, structural enhancements, electrical work, and other related 18 tasks. The City's Fire Department has recently secured funding to purchase a 28-foot Marine 19 Rescue Boat, which requires a permanent mooring location. Similarly, the Police Department 20 operates a comparable vessel, with mooring costs covered by the City. Installing these lifts will 21 reduce long-term mooring expenses and significantly improve emergency response times for 22 both public safety departments; and 23 WHEREAS, on March 3, 2025, the City published an Invitation to Bid ("ITB") No. PWE25- 24 026B for the Boynton Beach Oyer Park Fire Boat Lift Project, also known as Boating Safety Program 25 PH II. As a result, the City received two bid submissions when the ITB closed on April 24, 2025. 26 After review by the Procurement Division and the Public Works Department, Seaside Marine 27 Contractors ("Contractor") was deemed the lowest responsive and responsible bid submission; 28 and 29 WHEREAS, the City Commission, upon the recommendation of staff, has deemed it in the 30 best interests of the City's citizens and residents to award ITB No. PWE25-026B for the Boynton 31 Beach Oyer Park Fire Boat Lift Project, also known as Boating Safety Program PH II, to Seaside 32 Marine Contractors, and approve an Agreement with Seaside Marine Contractors in the amount 33 of $178,017.50, plus a 10% contingency of $17,801.75 for a total not to exceed $195,819.25 34 NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF BOYNTON 35 BEACH, FLORIDA, THAT: 36 SECTION 1. The foregoing "Whereas" clauses are hereby ratified and confirmed as 37 being true and correct and are hereby made a specific part of this Resolution upon adoption. 38 SECTION 2. The City Commission of the City of Boynton Beach, Florida, does hereby 39 award ITB No. PWE25-026B for the Boynton Beach Oyer Park Fire Boat Lift Project, also known as 40 Boating Safety Program PH II, to Seaside Marine Contractors. 41 SECTION 3. The City Commission of the City of Boynton Beach, Florida, does hereby 42 approve an Agreement between Seaside Marine Contractors and the City for ITB No. PWE25-026B 43 for the Boynton Beach Oyer Park Fire Boat Lift Project, also known as Boating Safety Program PH 44 II in the amount of $178,017.50, plus a 10% contingency of $17,801.75 for a total not to exceed 45 $195,819.25 (the "Agreement"), in form and substance similar to that attached as Exhibit A. 46 SECTION 4. The City Commission of the City of Boynton Beach, Florida, hereby 47 authorizes the Mayor to execute the Agreement. The Mayor is further authorized to execute any 48 ancillary documents required under the Agreement or necessary to accomplish the purposes of 49 the Agreement and this Resolution, including any term extensions as provided in the Agreement, 50 provided such documents do not modify the financial terms or material terms. 51 SECTION 5. The City Clerk shall retain the fully executed Agreement as a public record 52 of the City. A copy of the fully executed Agreement shall be provided to Rhonda Kaplan to forward 53 to the Contractor. 54 SECTION 6. This Resolution shall take effect in accordance with the law. 55 56 57 [SIGNATURES ON THE FOLLOWING PAGE] 58 %14 rati59 PASSED AND ADOPTED this �0day of 2025. 60 CITY OF BOYNTON BEACH, FLORIDA 61 YES NO 62 Mayor- Rebecca Shelton 63 f� 64 Vice Mayor-Woodrow L. Hay 65 66 Commissioner-Angela Cruz 67 f 68 Commissioner-Thomas Turkin 69 V 70 Commissioner-Aimee Kelley 71 72 OTE 0 175 73 A 74 / Ilk- . .1 1 . 76 Mayle: D• esus, MPA, , C Rebecca Shelton 77 City Cle, Mayor 78 _ .�...... �,<�pY.NT.. ,,6 I. APPROVED AS TO FORM: 79 80 (Corporate Seal) gt.. ° 4,.. ••C9�'� 81 SEAL '; AGREEMENT BETWEEN THE CITY OF BOYNTON BEACH AND SEASIDE MARINE CONSTRUCTION, LLC. FOR OYER PARK FIRE BOAT LIFT INSTALLATION PROJECT This Construction Contract (the "Agreement") is entered into by and between the City of Boynton Beach, a municipal corporation organized and existing under the laws of Florida, with a business address of 100 East Ocean Ave., Boynton Beach, FL 33435, hereinafter referred to as "City," and Seaside Marine Construction, LLC., a Florida Limited Liability Company authorized to do business in the State of Florida, with a business address of 555 W. Ocean Avenue, Boynton Beach, Florida 33426 hereinafter referred to as the "Contractor," (each a "Party" and collectively the "Parties"). WHEREAS, the City of Boynton Beach's Public Works Engineering Department identified a significant need for the installation of a new Fire Department Boat Lift at Oyer Park; and WHEREAS, on March 4, 2025, the Purchasing Division issued an Invitation to Bid PWE25- 026B —Oyer Park— Fire Boat Lifts Installation Project (the "ITB") for the Fire Boat Lift Installation Project (the "Project"); and WHEREAS, Contractor responded to the ITB by submitting its Bid dated April 22, 2025 (the "Bid"); and WHEREAS, the City has selected the Contractor to perform construction services related to the Project; and, WHEREAS, at its meeting of m4,4 , , by Resolution No. Rs-13y , the City Commission approved this award to the Contractor and authorized the proper City officials to execute this Agreement. NOW, THEREFORE, City and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as follows: Article 1. ZCOPE OF WORK. The Contractor shall furnish all construction services necessary for the complete and proper construction of the Project, if not expressly indicated or called for in the Contract Documents (as defined in Article 10 below), and includes all labor, equipment, machinery, tools, materials, manufactured articles, supplies, documents, permits, traffic control, transportation, security, and other services and incidentals, including fuel, power, light, water, sanitary facilities, temporary facilities, and essential communications, and the costs of bonds, insurance, permitting, taxes warranties, general conditions, overhead and miscellaneous costs or expenses, necessary to construct the Project as described in the ITB and shown in the Contract Drawings and described in the technical specifications for the Project, and to fulfill Contractor's obligations under this Agreement as described in the Scope of Work detailed in the ITB (collectively the "Project" or the "Work"). Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 1 Article 2. CONSULTANT. Shall mean the City of Boynton Beach, who has designed the Project and will assume all duties and responsibilities and will have the rights and authority assigned to the Consultant in connection with the completion of the Work in accordance with the Contract Documents. Article 3. CONTRACT TIME, TERMINATION, LIQUIDATED DAMAGES. 3.1 Contract Time. Time is of the essence for this Agreement. The Contractor shall proceed with the Work and conform to the Project Schedule attached as Exhibit A. Work shall commence on the date Notice to Proceed is issued by the City and be fully completed in accordance with the General Conditions, with such extensions of time as are provided in the General Conditions (the "Contract Time"). The Work will be substantially completed within Ninety (90) calendar days from the issuance of Notice to Proceed when the Contract Time commences to run as provided in Paragraph 2.3 of the General Conditions and completed and ready for final inspection and payment in accordance with Paragraph 14.9 of the General Conditions within One Hundred Twenty (120) calendar days from the date of Substantial Completion (the "Contract Time"). 3.2 Termination for Convenience. This Agreement may be terminated in whole or in part by City for convenience, without cause, upon providing seven (7) business days' written notice to Contractor for such termination in accordance with Paragraph 15.3 of the General Conditions. Upon such termination, the Contract Price earned to the date of termination shall be paid to the Contractor, but the Contractor waives any claim for damages, including loss of profits, arising out of or related to the early termination. Contractor may not recover overhead or profit for Work not performed. Those Agreement provisions that, by their nature, survive final payment shall remain in full force and effect. 3.3 Termination for Cause. In addition to all other remedies available to City, this Agreement shall be subject to cancellation by City for cause, should Contractor neglect or fail to perform or observe any of the terms, provisions, conditions, or requirements herein contained or as set forth in Paragraph 15.2 of the General Conditions, if such neglect or failure shall continue for thirty (30) days after receipt by Contractor of written notice of such neglect or failure. If Contractor abandons this Agreement or causes it to be terminated, Contractor shall indemnify City against loss pertaining to this termination. If the City terminates this Agreement for cause, the Contractor shall not be relieved from any of its obligations under the Contract Documents and shall not be entitled to receive any further payment until the City's costs to complete the Work are determined. In no event shall the Contractor receive any payment for Work finished by the City. The City shall determine its costs incurred in completing the Work, including fees and charges to contractors, fees of engineers/architects, attorney and other professional fees, court costs, and other damages incurred by the City. The City shall not be required to obtain the lowest price for the Work to be performed, but the costs paid by the City must be reasonable. If the Contract Price exceeds the City's costs to finish the Work, the City shall retain the excess. If the City's costs exceed the unpaid balance, the Contractor shall pay the difference to the City. This obligation for payment shall survive the termination of this Agreement and final payment. Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 2 If the Contractor's Surety is directed or agrees to complete the Work, all payments due after termination shall be made to the Surety until the Work is complete and/or the Contract price has been expended. The Surety shall then be responsible for all of the obligations and duties of the Contractor under the Contract Documents and shall be bound by the conditions of the Contract Documents, this Agreement, and the Bond to fulfill all obligations of the Contract Documents for the Contract Price in effect as of termination. The Surety may not assign those obligations without the City's written consent. The Surety shall be responsible for paying all costs relating to the Contractor's termination. Contractor and its Surety shall be jointly and severally liable for all costs over the Contract Price for completion of the Work and Liquidated Damages. If, upon termination for cause, it is determined that the Contractor was not in default, the rights and obligations of the Parties shall be as if the notice of termination had been issued for the City's convenience. 3.4 Contractor Obligations Upon Termination. Upon receipt of written notice from City of termination, Contractor shall: (i) cease operations as directed by City in the notice; (ii)take actions necessary, or that City may direct for the protection and preservation of the Work; (iii) except for Work directed to be performed before the effective date of termination stated in the notice, and if directed by City, terminate all existing subcontracts and purchase orders and enter into no further subcontracts and purchase orders; and (iv) turn over all marked up Construction Drawings and record set documents showing progress to date. The City may assume and become liable at its sole discretion for obligations, commitments, and unsettled contractual claims that the Contractor has previously undertaken or incurred in good faith in connection with said project. City shall reimburse Contractor for any unpaid and earned project cost as of the termination date, less damages or setoffs applicable under the Contract Documents. The Contractor shall, as a condition of receiving the payments referred to herein, execute and deliver all such papers and take all such steps, including the legal assignment of its contractual rights, as the City may require for fully vesting in it the rights and benefits of the Contractor under such obligations or commitments. 3.5 Liquidated Damages. The City and Contractor recognize and acknowledge that time is of the essence for the Contractor's performance of this Agreement and that the City will suffer financial loss if the Work is not completed within the times specified in Paragraph 3.1 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. The Contractor shall pay the City $500.00 Dollars ($500) per calendar day for each day or part of a day after scheduled substantial completion, as specified in Paragraph 3.1 that Substantial Completion is not achieved until the Work is substantially complete. After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Time or any proper extension thereof granted by the City, Contractor shall pay City Two Hundred Fifty Dollars ($250.00) per calendar day for each day or part of a day that final completion is not achieved after the time specified in Paragraph 3.1 for final completion and readiness for final payment (the "Liquidated Damages"). The Contractor further acknowledges that the City is entitled to deduct any Liquidated Damages to which the City is entitled from the final payment to the Contractor. If the Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 3 amount of Liquidated Damages due to the City exceeds the final payment amount, the Contractor shall pay the difference to the City. This obligation for payment shall survive the expiration or termination of this Agreement and final payment. The City does not waive any rights or other remedies under this Agreement by collecting Liquidated Damages. Liquidated Damages will continue to be charged in the event of the Contractor's default and continuation of the Work by City or Surety. The Parties agree that the amounts established in this section are not penalties but are Liquidated Damages to the City for its inability to obtain full beneficial occupancy and/or use of the Project. Liquidated Damages are hereby fixed and agreed upon between the Parties based on (1) mutual recognition of the impossibility of precisely ascertaining the amount of damages that the City will sustain as a consequence of the Contractor's failure to obtain Substantial Completion, Final Completion, or both timely; and (2) both Parties' desire to obviate any question or dispute concerning the amount of said damages and the cost and effect of the failure of Contractor to achieve Substantial Completion, Final Completion, or both, on time. These Liquidated Damages shall apply separately to each portion of the Project for which a deadline for Substantial Completion, Final Completion, or both is given. Liquidated Damages do not address costs incurred by the City or Consultant in having the Consultant administer the construction of the Project beyond the deadlines for Substantial Completion, Final Completion, or both. The Contractor is separately responsible to the City for the actual costs referenced above, pursuant to Article 13. Article 4. CONTRACT PRICE. The City agrees to pay the Contractor for the completion of all Work and the Project, and the Contractor will accept, as full compensation for the completion of the Work, a total sum as follows: Based on the Contract Price(s) shown in the Bid Form submitted to the City as may have been subsequently negotiated and as stated herein, a copy of such Bid Form attached hereto as Exhibit B, the aggregate amount of this Agreement (obtained from either the lump sum price, the application of unit prices to the quantities shown in the Bid Form or the combination of both) not to exceed: One Hundred Seventy Eight Thousand, Seventeen Dollars and Fifty Cents ($178,017.50) (the "Contract Price"), subject only to adjustment as provided in the General Conditions. Contingency Funds. All contingency sums are the City's contingency and remain the City's property until the expense is approved. The Contract Price shall not include any contingency amounts. If this Agreement or schedule of bid prices includes an agreed sum as a contingency, such amount is identified solely for budget purposes and remains the City's funds. The City may approve the use of contingency funds only to defray expenses due to unforeseen conditions, extra work, and circumstances relating to construction, unless otherwise agreed. Such contingency funds are not for use by the Contractor to cover shortfalls in the Contractor's bid amount, nor for use by the City to increase the scope of work. Contractor shall obtain prior written approval from the City before the expenditure of contingency funds, and Contractor will be required to furnish documentation evidencing expenditures charged to contingency and/or allowances before the release of such funds by the City. All uncommitted contingency funds remain the funds of the City. Oyer Park Fire Boat lits Installation Project AKA Boynton Beach Boating Safety Program Phase II 4 Contingency. City and Contractor agree that the Project budget shall include City's contingency, which shall be utilized as outlined above. The Contingency shall be 10% or$17,801.75 to account for any unforeseen conditions only approved by the City Manager. Article 5. PAYMENT PROCEDURES. The Contractor shall submit Applications for Payment in accordance with Article 14 of the General Conditions. The City will process Applications for Payment as provided in the General Conditions. 5.1 Progress Payments. A. The Contractor may submit an Application for Payment as recommended by the Consultant for Work completed at intervals of no more than once a month. All progress payments will be based on the progress of Work measured by the schedule of values established in Paragraph 2.9.1 of the General Conditions and, in the case of Unit Price Work, based on the number of units completed or, in the event there is no schedule of values, as provided in the General Requirements. The Schedule of Values must be reviewed and approved by the City before the first Application for Payment is submitted B. Before Substantial Completion, progress payments will be made in an amount equal to 95% of the Work completed, but, in each case, less the aggregate of payments previously made and less such amounts as the Consultant shall determine, or the City may withhold, in accordance with Paragraph 14.5 of the General Conditions. C. Contractor shall submit with each Application for Payment, an updated progress schedule acceptable to the City and a Warranty of Title/Release of Liens relative to the Work that is the subject of the Application. Each Application for Payment shall be submitted to the City for approval. The City shall pay the Contractor within thirty (30) calendar days after approval by the City of the Contractor's Application for Payment and submission of an acceptable updated progress schedule. 5.2 Withheld Payments. The City may withhold, in whole or in part, payment to such extent as may be necessary to protect itself from loss if: a. Defective Work or material is not remedied. b. Claims filed or reasonable evidence indicating probable filing of claims by other parties against Contractor. c. The Contractor fails to properly pay subcontractors for materials or labor or vendors and manufacturers for equipment, supplies, and materials. d. Damage to the City or another Contractor that remains unresolved. e. Reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Price. f. Reasonable evidence that the Work cannot be completed within the schedule. g. Repeated failures to carry out the Work in accordance with the Contract Documents. h. The Contractor is in default of any condition of this Agreement. i. The Contractor fails to submit information required by this Agreement. j. Lapse of Contractor's insurance coverage. k. Claims filed or reasonable evidence indicating public filing of claims by the City or third parties against the Contractor. Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 5 I. The City has the right to claim Liquidated Damages or costs incurred by the City for extended construction administration. m. Failure of Contractor to provide any document(s) required by the Contract Documents. When the above grounds are removed or resolved, or the Contractor provides a Performance Bond, Surety Bond, or consent of Surety satisfactory to the City, which will protect the City in the amount withheld, payment may be made in whole or in part. 5.3 Retainage. All retainage shall be withheld in accordance with Florida law, including but not limited to Sections 255.077 and 255.078, Fla. Stat. The City shall withhold retainage of five percent (5%) of all monies earned by the Contractor from each progress payment paid to the Contractor until Final Completion of the Work (defined as that point at which the Contractor has performed one hundred percent(100%) of the Work) has been reached and acceptance by City. Within 30 calendar days after reaching the earlier of substantial completion or beneficial occupancy, the City and the Contractor will inspect the Work and develop a punch list covering those items required to render complete, satisfactory, and acceptable Work. The punch list will include a schedule of values that provides the estimated cost to complete each item on the punch list. If the City and Contractor cannot agree on an item or value, the City has final discretion on whether to include an item and the amount for valuation of the cost to complete each item on the punch list. Within twenty (20) business days after the creation of the final punch list, the City shall pay the Contractor the remaining contract balance, including any retainage, less one hundred fifty percent(150%) of the amount listed in the final punch as the cost to complete the punch list items. Upon final acceptance for an item or all items, the 150 percent withheld for each item will be released with the final payment. For projects valued at $10 million or more, the 30 calendar days may be extended to 45 calendar days. If the City has grounds under Florida law to continue to retain all or a portion of the requested retainage, the City may continue to hold all retainage. If the Work is not on schedule when the request for payment of retainage is submitted, the City may continue to hold all retainage and charge the Contractor all applicable Liquidated Damages authorized by Article 3 above. 5.4 Final Payment. Upon completion of all requirements for substantial completion and final completion and acceptance of the Work in accordance with Paragraph 14.10 of the General Conditions, the City shall pay the remainder of the Contract Price and release any retainage, as recommended by the Consultant as provided in Paragraph 14.10. The Contractor acknowledges that final payment shall not be made until the City receives a consent of Surety. Additionally, before final payment, the Contractor shall submit a final waiver and release of lien, as well as final releases from all suppliers and subcontractors who worked on the Project. The making and acceptance of the final payment shall constitute a waiver and release of all claims by the Contractor, except those previously made in writing and still unsettled. If the Contractor fails to submit all documents required for final payment within one (1) year after final completion, any amounts owed as final payment shall be forfeited. The City shall provide written notice to the Contractor at least sixty (60) days before forfeiture. Forfeiture will not apply to documents that are the subject of existing claims or pending legal proceedings. Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 6 5.5 Local Government Prompt Payment Act. All payments shall be governed by the Local Government Prompt Payment Act, as outlined in Part VII, Chapter 218, Fla. Stat. 5.6 Payment Where Public Construction Bond Required. If this Agreement requires the Contractor to provide a Public Construction Bond of Performance and Payment Bonds, no payment shall be made by the City to the Contractor until the Contractor has provided the City with a certified copy of the Bond(s) evidencing that said Bond(s) have been recorded with the Clerk of the Courts in the Public Records of Palm Beach County, in accordance with Section 255.05, Fla. Stat. Article 6. BONDS. The Contractor shall provide bonds in accordance with Article 5 of the General Conditions. 6.1 Performance Bond. In accordance with the provisions of Section 255.05, Fla. Stat., and as required by the Contract Documents, the Contractor shall provide, on forms furnished by the City, a Public Construction Bond in an amount not less than the total Contract Price by a Surety Company acceptable to City. The Bond shall guarantee the Contractor's performance and payments to all claimants, as defined in Section 255.05(1), Fla. Stat., supplying the Contractor with labor, materials, or supplies used directly or indirectly in the Work provided for in this Agreement. The Bond shall incorporate by reference the terms of the Contract Documents in its entirety. Moreover, the Contractor agrees that the following language shall be expressly included within the language of its Bond: "The Surety expressly agrees to be bound by all terms and conditions related to Liquidated Damages, delay and time, or impact-related damages. The Surety shall be bound by the warranty or warranties contained in the Contract Documents and shall be responsible for any and all warranty obligations or damages resulting from latent defects or deficiencies in the Work performed under this Agreement. The Surety waives all rights against the City and its agents and employees for damages or other causes of loss by the Surety's performance of its obligations under this Bond, including claims by Surety against the City for costs it asserts were not warranted by the Contract Documents, excluding only such rights as the Surety shall have to proceeds of such insurance held by City as fiduciary." 6.2 Performance Bond and Payment Bond. Alternatively, the City may accept a Performance Bond and a Payment Bond, each in the amount not less than the total Contract Price, by a Surety acceptable to the City, on a form furnished by, or acceptable to, the City, instead of the Public Construction Bond. 6.3 Recording of Bond. Within ten days after receipt of the fully executed contract, the Contractor shall record its Bond(s) in the public records of Palm Beach County and provide a certified copy of the recorded Bond to the City in accordance with Section 255.05, Fla. Stat. 6.4 Surety.. To be acceptable to the City, a Surety Company shall comply with the following provisions: Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 7 (1) The Surety Company shall have a currently valid Certificate of Authority, issued by the State of Florida Department of Insurance, authorizing it to write surety bonds in the State of Florida. (2) The Surety Company shall have a valid Certificate of Authority issued by the United States Department of Treasury under Sections 9304 to 9308 of Title 31 of the United States Code. (3) The Surety Company shall be in full compliance with the provisions of the Florida Insurance Code. (4) The Surety Company shall have at least twice the minimum surplus and capital required by the Florida Insurance Code when the Contractor submits its Bid. (5) The Surety Company shall have at least the ratings of A-/Class V. (6) The Surety Company shall not expose itself to any loss on any one risk in an amount exceeding ten percent (10%) of its surplus to policyholders. Article 7. CONTRACTOR GUARANTEE. For one (1) year after the date of Final Completion of the complete Work (and not from final completion of component parts of the Work) or for such longer periods as may be set forth with respect to specific warranties contained in the specifications (the "Warranty Period"), Contractor warrants to City that the Work will conform to the requirements of the Contract Documents and will be free from defects and fit for the purpose for which they were intended. Work, materials, or equipment not conforming to these requirements may be considered defective. The Contractor's warranty excludes remedy for damage or defect caused by abuse, alterations to the Work not executed by or under the Contractor, improper or insufficient maintenance by the City, improper operation by the City, or normal wear and tear and regular usage. Warranty by Contractor shall not be construed as a waiver by City of any other contract or legal remedy. Article 8. CHANGE ORDER. Except as otherwise provided in the General Conditions, this Agreement shall only be modified by a written Change Order executed by the Contractor and City. Commencing Work without a written Change Order or Change Directive executed by the City before the commencement of Work waives any claim by the Contractor to an adjustment to the Contract Price and the Contract Time related to such Work. It is expressly and specifically agreed that any and all claims for changes to the Contract Time due to delay shall be waived if not submitted in strict accordance with the requirements of the General Conditions. The Contractor waives all of its rights, including, but not limited to, claims for Contract Time and Contract Price adjustments if the Contractor fails to strictly comply with the requirements of the General Conditions. Article 9. CONTRACTOR'S UNDERSTANDING. It is understood and agreed that the Contractor has, by careful examination, satisfied itself as to the nature and location of the Work, the conformation of the ground, the character, quality, and quantity of the materials to be encountered, the character of the equipment and facilities needed preliminary to and during the prosecution of the Work, and the general and local conditions. Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 8 Execution of this Agreement by the Contractor is a representation that the Contractor has visited the site, reviewed any design criteria furnished by the City, become generally familiar with local conditions under which the Work is to be performed, and correlated personal observations with requirements of the Contract Documents. The Contractor deems its inspection of the site and review of information furnished by the City to be an adequate investigation. The Contractor represents that the plans and specifications are consistent, practical, feasible, and constructible within the scheduled construction time. The Contractor affirmatively covenants that the Contractor has observed no defects or discrepancies in the plans, specifications, or site and that if, during construction, any discrepancies, defects, etc., are discovered by or made known to the Contractor, the Contractor shall immediately communicate the same to the City. Article 10. CONTRACT DOCUMENTS. The term "Contract Documents" shall include all the terms and conditions and Project requirements contained in this Agreement, the Invitation to Bid, and the following documents, all of which, taken together, are incorporated herein and form the Contract Documents. The Contract Documents constitute the entire agreement between the Contractor and City and supersedes all prior verbal and written agreements, understandings, negotiations, and discussions between the Parties. The terms and conditions of any Invitation to Bid issued regarding the Project and Work is incorporated herein and made a part of this Agreement. No verbal agreement or conversation with any City officer, agent, or employee before or after execution of this Agreement shall affect or modify any of the terms or obligations contained in any of the documents comprising this Agreement. For convenience, not all of the Contract Documents may be attached to this Agreement, but they make up the Contract Documents, regardless of whether they are attached. 10.1 Contract 10.2 Insurance Advisory 10.3 General Conditions of Construction 10.4 Invitation to Bid 10.5 Instructions to Proposers / Bidders 10.6 Contractor's Bid (including the Bid, Schedule(s), Submission Requirements of Proposer/ Bidder, and all required certificates, affidavits, and other documentation) 10.7 Special Terms and Conditions 10.8 City Construction Standards and Details (available online at: PW Engineering: https://www.boynton-beach.org/760/Engineering-Standards-Manual and Utilities Engineering: https://www.boynton-beach.org/691/Utilities-Engineering-Division) 10.9 Attachment "A" —Technical Specifications / Special Conditions 10.10 Contractor's Bid Bond, Performance, and Payment Bond The Contract Documents are complementary, and wherever possible, the provisions of the documents shall be construed to avoid conflicts between the provisions of the various documents. In the event of a conflict, the more specific or more recent document shall control, generally in the order provided above. Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase Il 9 Article 11. NOTICE. All notices required in this Agreement shall be sent by certified mail, return receipt requested, and if sent to the City, shall be mailed to: Daniel Dugger, City Manager City of Boynton Beach 100 East Ocean Ave Boynton Beach, FL 33435 Telephone No. (561) 742-6000 Copy: Shawna G. Lamb, City Attorney City of Boynton Beach P.O. Box 310 Boynton Beach, Florida 33425 Telephone: (561) 742-6010 / Facsimile: (561) 742-6090 If sent to the Contractor, it shall be mailed to: Peter Bilbo, CFO Seaside Marine Construction, LLC. 555 West Ocean Avenue Boynton Beach, FL 33426 Telephone: (561) 946-9249 Article 12. JNDEMNIFICATION. Contractor shall indemnify and hold harmless the City, its commissioners, officers, employees and agents ("Indemnified Parties"), from and against any and all claims, obligations, liability, expenses, losses, and causes of action, including attorneys' fees and costs, to the extent the same are caused by: (i) an act, negligence, recklessness or intentional wrongful misconduct of Contractor or its subcontractors, or the officers, employees or agents of either, while engaged in or about the performance of the Work; or while in or about the project site or premises; (ii) arising from accident or any injury to Contractor or its subcontractors while engaged in or about the performance of the Work, or while in or about the project site or premises, not caused by act of the Indemnified Parties or other contractors of City; (iii) arising out of the violation of federal, state, county, or municipal laws, ordinances, or regulations by Contractor or its subcontractor; or (iv) arising from liens or claims for services rendered for labor or materials furnished in or for the performance of the Work. The extent of the Contractor's indemnification shall be limited to one and one-half(1 1/2) times the Contract Price or One Million Dollars ($1,000,000) per occurrence, whichever is greater. This paragraph shall not be construed to require the Contractor to indemnify the Indemnified Parties for such Indemnified Parties' own negligence or intentional acts. Nothing in this paragraph shall be construed as a contractual waiver by the City of the protections and limits of sovereign immunity under Section 768.28, Fla. Stat., nor a waiver of any defense the City may have and shall not be construed as consent to be sued by third parties based on any claims arising under this Agreement. Contractor and City agree that any liability of the City under this Agreement shall be limited to the amounts set forth in Section 728.68, Fla. Stat. This paragraph shall survive the expiration or termination of this Agreement. Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 10 Article 13. REIMBURSEMENT OF CONSULTANT EXPENSES. Should the completion of this Agreement be delayed beyond the specified or adjusted time limit, separate and apart from the Liquidated Damages stated in Section 3.5, the Contractor shall also reimburse the City for all expenses of consulting and inspection incurred by the City during the period between said specified or adjusted time and the actual date of final completion. All such expenses for consulting and inspection incurred by the City will be charged to the Contractor and deducted from payments due to the Contractor as provided by this Agreement. Said expenses shall be further defined as Consultant charges associated with the construction contract administration, including resident project representative costs. City may, but is not obligated to, deduct such costs from the monies due the Contractor for performance of Work under this Agreement using unilateral credit Change Orders issued by City as costs are incurred by the Consultant and agreed to by City. Article 14. FLORIDA'S PUBLIC RECORDS LAW. The City is a public agency subject to Chapter 119, Fla. Stat. The Contractor shall comply with Florida's Public Records Law. Specifically, the Contractor shall: a. Keep and maintain public records required by the City to perform the service; b. Upon request from the City's custodian of public records, provide the City with a copy of the requested records or allow the records to be inspected or copied within a reasonable time at a cost that does not exceed the cost provided in Chapter 119, Fla. Stat., or as otherwise provided by law; c. Ensure that public records that are exempt or that are confidential and exempt from public record disclosure requirements are not disclosed except as authorized by law for the duration of the contract term and, following completion of the Contract, Contractor shall destroy all copies of such confidential and exempt records remaining in its possession once the Contractor transfers the records in its possession to the City; and, d. Upon completion of the Contract, the Contractor shall transfer to the City all public records in the Contractor's possession at no cost to the City. All records stored electronically by the Contractor must be provided to the City, upon request from the City's custodian of public records, in a format compatible with the City's information technology systems. e. IF THE CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF CHAPTER 119, FLORIDA STATUTES, TO THE CONTRACTOR'S DUTY TO PROVIDE PUBLIC RECORDS RELATING TO THIS AGREEMENT, CONTACT THE CUSTODIAN OF PUBLIC RECORDS: CITY CLERK'S OFFICE 100 E. OCEAN AVENUE BOYNTON BEACH, FLORIDA 33435 561-742-606 CityClerk a.bbfl.US Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 11 Article 15. E-VERIFY. The Contractor shall comply with Section 448.095, Fla. Stat., "Employment Eligibility," including registering and using the E-Verify system to verify the work authorization status of employees. Failure to comply with Section 448.095, Fla. Stat., shall result in termination of this Agreement. Any challenge to termination under this provision must be filed in the Circuit Court no later than 20 calendar days after the termination date. If this Agreement is terminated for the Contractor's violation of the statute, the Contractor may not be awarded a public contract for one (1) year after the termination date. Article 16. REPRESENTATIONS OF CONTRACTOR. 16.1 Authority. The Contractor represents and warrants that this Agreement constitutes the legal, valid, binding, and enforceable obligation of the Contractor and that neither the execution nor performance of this Agreement constitutes a breach of any agreement that the Contractor has with any third party or violates applicable law. The Contractor further represents and warrants that execution of this Agreement is within the Contractor's legal powers, and each individual executing this Agreement on behalf of the Contractor is duly authorized by all necessary and appropriate action to do so on behalf of the Contractor and does so with full legal authority. The Contractor, by execution of this Agreement, binds itself, its partners, successors, assigns, and legal representatives to all covenants, agreements, and obligations contained in this Agreement. 16.2 Duly Licensed. The Contractor represents that it is duly licensed to perform the services under this Agreement and will continue to maintain all licenses and approvals required to conduct its business. 16.3 Compliance with Laws. The Contractor shall comply with all applicable City, State, and Federal laws relating to the scope of work under this Agreement, now or hereafter in effect. It shall not be grounds for a change order that the Contractor failed to investigate the codes and regulations of all applicable government agencies with jurisdiction over the Work. 16.4 Lobbying Certification. The Contractor certifies to the best of its knowledge and belief that no funds or other resources received from the state in connection with this Agreement will be used directly or indirectly to influence legislation or any other official action by the Florida Legislature or any state agency. 16.5 Non-Collusion. In accordance with Section 838.22, Fla. Stat., the Contractor certifies that it has not entered into any agreement to commit a fraudulent, deceitful, unlawful, or wrongful act or any act which may result in an unfair advantage over other bidders or contractors. 16.6 Non-Discrimination. In performing under this Agreement, the Contractor shall not discriminate against any person because of race, color, religion, sex, gender identity or expression, genetic information, national origin, age, disability, familial status, marital status, or sexual orientation. Contractor or its subcontractor shall not unlawfully discriminate (as proscribed by federal, state, county, city, and any other local law) against any employee, city employee working with Contractor or its subcontractor, or applicant for employment with such Contractor or subcontractor based on that person's race, color, Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 12 religion, sex, gender identity or expression, genetic information, national origin, age, disability, familial status, marital status, or sexual orientation, or association with members of such protected classes. The Contractor and its subcontractor(s) shall take action to ensure that applicants are not discriminated against and that employees are treated equally during employment. 16.7 Entities of Foreign Concern. The provisions of this section apply only if the Contractor or any subcontractor will have access to an individual's personal identifying information under this Agreement. The Contractor represents and certifies: (i) the Contractor is not owned by the government of a foreign country of concern; (ii) the government of a foreign country of concern does not have a controlling interest in the Contractor; and (iii) the Contractor is not organized under the laws of and does not have its principal place of business in, a foreign country of concern. On or before the Effective Date, the Contractor and any subcontractor that will have access to personal identifying information shall submit to the City executed affidavit(s) under penalty of perjury, in a form approved by the City attesting that the entity does not meet any of the criteria in Section 287.138(2), Fla. Stat. Compliance with the requirements of this section is included in the requirements of a proper invoice for purposes of payment. Terms used in this section that are not otherwise defined in this Agreement shall have the meanings ascribed to such terms in Section 287.138, Fla. Stat. 16.8 Anti-Human Trafficking. On or before the Effective Date, the Contractor shall provide the City with an affidavit attesting that the Contractor does not use coercion for labor or services, in accordance with Section 787.06(13), Fla. Stat. 16.9 Public Entity Crime Act. The Contractor represents that it is familiar with the requirements and prohibitions under the Public Entity Crime Act, Section 287.133, Fla. Stat., and represents that its entry into this Agreement will not violate that Act. The Contractor further represents that there has been no determination that it committed a "public entity crime" as defined by Section 287.133, Fla. Stat., and that it has not been formally charged with committing an act defined as a "public entity crime" regardless of the amount of money involved or whether Contractor has been placed on the convicted vendor list. 16.10 Discriminatory Vendor and Scrutinized Companies Lists; Countries of Concern. Contractor represents that it has not been placed on the "discriminatory vendor list" as provided in Section 287.134, Fla. Stat., and that it is not a "scrutinized company" pursuant to Sections 215.473 or 215.4725, Fla. Stat. Contractor represents and certifies that it is not, and for the duration of this Agreement will not be, ineligible to contract with City on any of the grounds stated in Section 287.135, Fla. Stat. Contractor represents that it is, and for the duration of this Agreement will remain, in compliance with Section 286.101, Fla. Stat. 16.11 Federal Labor / Employment Laws. In accordance with Section 255.20, Fla. Stat., the Contractor represents that it has not been found guilty by a court of any violation of federal labor or employment tax laws regarding subjects such as safety,tax withholding, workers' compensation, reemployment assistance or unemployment tax, social security and Medicare tax, wage or hour, or prevailing rate laws within the past 5 years. 16.12 Unauthorized Aliens. The knowing employment by the Contractor or its sub- contractors of any alien not authorized to work by the immigration laws or the Attorney Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 13 General of the United States is prohibited and shall be a default of this Agreement, which results in unilateral termination. The Contractor further represents that it is not in violation of any laws relating to terrorism or money laundering, including Executive Order No. 13224 on Terrorist Financing. 16.13 Safety and Environmental Laws. In performing the Work, the Contractor shall comply with all Occupational Safety and Health Administration (OSHA), State and County Safety and Occupational Health Standards, applicable environmental laws, and any other applicable rules, regulations, and permits. The Contractor bears full responsibility for training, safety, and providing necessary equipment for all Contractor personnel throughout the term of this Agreement. Upon request, the Contractor will demonstrate to the City's satisfaction any programs, procedures, and other activities used to ensure compliance. 16.14 Contingency Fee. The Contractor represents and warrants that it has not employed or retained any person or entity, other than a bona fide employee working solely for the Contractor, to solicit or secure this Agreement and that it has not paid or agreed to pay any person or entity, other than a bona fide employee working solely for the Contractor, any fee, commission, percentage, gift, or other consideration contingent upon or resulting from the award or making of this Agreement. If this Agreement is subject to Section 287.055, Fla. Stat., the Parties agree and stipulate that the statutory language stated in Section 287.055(6)(a), Fla. Stat., is deemed included and fully incorporated herein. 16.15 Truth-In-Negotiation Representation. The Contractor's compensation under this Agreement is based upon its representations to the City. The Contractor certifies that the wage rates, factual unit costs, and other information supplied to substantiate the Contractor's compensation, including, without limitation, in the negotiation of this Agreement, are accurate, complete, and current as of the date the Contractor executes this Agreement. In its sole discretion, the Contractor's compensation may be reduced by the City to correct any inaccurate, incomplete, or noncurrent information provided to the City as the basis for the Contractor's compensation in this Agreement. Article 17. LIENS. The Contractor acknowledges that no liens may attach to the subject improvements and property as a public project. Nevertheless,the Contractor agrees to keep the project, the buildings thereon, and the property free of liens for or on account of any work done or materials furnished under this Agreement. In the event any such lien is filed, Contractor shall, within five (5) days after written notice by City, discharge the lien(s) or cause a satisfaction of such lien(s) to be recorded in the Public Records of Palm Beach County, Florida, or post a bond sufficient to release the lien(s) and cause the Clerk of the Circuit Court of Palm Beach County to discharge such lien, as may be appropriate. In the event Contractor fails to discharge or bond the lien(s), City shall have the right, but not the obligation, to discharge or bond the lien(s) and shall have the right to retain out of any payment then due or thereafter to become due to the Contractor, monies sufficient to discharge the amount of such lien(s) and City's costs and reasonable attorneys' fees incurred. Article 18. IRON AND STEEL PRODUCTS. If this Agreement is for a "public works project" as defined in Section 255.0993, Fla. Stat., then any iron or steel product permanently incorporated in the project must be produced in the United Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 14 States, unless specifically exempted in writing by the City in accordance with Section 255.0993, Ha. Stat. Article 19. INSURANCE. During the performance of the Work under this Agreement, the Contractor shall maintain the insurance policies required by the Insurance Advisory in the Contract Documents and the General Conditions and provide originals or certified copies of all policies to the City's Risk Manager. All policies shall be written by an insurance company authorized to do business in Florida. The Contractor shall be required to obtain all applicable insurance coverage before commencing any Work under this Agreement. Article 20. DEFAULT OF CONTRACT & REMEDIES. 20.1 Correction of Work. If in the judgment of the City, Work provided by the Contractor does not conform to the requirements of this Agreement, or if the Work exhibits poor workmanship, the City reserves the right to require that the Contractor correct all deficiencies in the Work to bring the Work into conformance without additional cost to City, and/or replace any personnel who fail to perform per the requirements of this Agreement. City shall be the sole judge of non-conformance and the quality of workmanship. 20.2 Default of Contract. The occurrence of any one or more of the following events shall constitute a default and breach of this Agreement by the Contractor: 20.2.1 The abandonment of the project by the Contractor for more than seven (7) calendar days. 20.2.2 The abandonment, unnecessary delay, refusal of, or failure to comply with any of the terms of this Agreement, or neglect or refusal to comply with the instructions of the City's designee. 20.2.3 The failure by Contractor to observe or perform any of the terms, covenants, or conditions of this Agreement to be observed or performed by Contractor, where such failure shall continue for seven (7) calendar days after written notice thereof by City to Contractor; provided, however, that if the nature of Contractor's default is such that more than seven (7) calendar days are reasonably required for its cure, then Contractor shall not be deemed to be in default if Contractor commences such cure within said seven (7) calendar day period and thereafter diligently prosecutes such cure to completion. 20.2.4 The assignment and/or transfer of this Agreement or execution or attachment thereon by Contractor or any other party in a manner not expressly permitted hereunder. 20.2.5 The making by the Contractor of any general assignment or general arrangement for the benefit of creditors, or the filing by or against Contractor of a petition to have Contractor adjudged a bankruptcy, or a petition for reorganization or arrangement under any law relating to bankruptcy (unless, in the case of a petition filed against Contractor, the same is dismissed within sixty (60) days); or the appointment of a trustee Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 15 or a receiver to take possession of substantially all of Contractor's assets, or for Contractor's interest in this Agreement, where possession is not restored to Contractor within thirty (30) days; for attachment, execution or other judicial seizure of substantially all of Contractor's assets, or for Contractor's interest in this Agreement, where such seizure is not discharged within thirty (30) days. 20.3 Remedies in Default. In case of default by the Contractor, the City shall notify the Contractor, in writing, of such abandonment, delay, refusal, failure, neglect, or default and direct the Contractor to comply with all provisions of the Agreement. A copy of such written notice shall be mailed to the Surety on the Performance Bond. If the abandonment, delay, refusal, failure, neglect, or default is not cured within thirty (30) days of when the City sent notice, the City may declare a default of the Agreement and notify the Contractor of such declaration of default and terminate the Agreement for cause in accordance with Section 3.3 of the Agreement. The Surety on the Performance Bond shall, within ten (10) days of such declaration of default, rectify or cause to be rectified any mismanagement or breach of service in the Agreement and assume the work of the Contractor and proceed to perform services under the Agreement, at its own cost and expense. City shall have all other rights available at law, in equity, or as otherwise described in the General Conditions. Article 21. SOVEREIGN IMMUNITY. Nothing contained herein is intended to serve as a waiver of sovereign immunity by the City or as a waiver of limits of liability or rights the City may have under the doctrine of sovereign immunity or Section 768.28, Fla. Stat. Article 22. FORCE MAJEURE. If the performance of this Agreement, or any obligation hereunder, is prevented by reason of hurricane, earthquake, or other casualty caused by nature, epidemic, pandemic, or other public health emergency, or by labor strike, war, or by a law, order, proclamation, regulation, ordinance of any governmental agency (collectively, "Force Majeure Event"), the Party so affected, upon giving prompt notice to the other Party, shall be excused from such performance to the extent of such prevention, provided that the affected Party shall first have taken reasonable steps to avoid and remove such cause of non-performance and shall continue to take reasonable steps to prevent and remove such cause, and shall promptly notify the other Party in writing and resume performance hereunder whenever such causes are removed; provided, however, that if such inability to perform due to the Force Majeure Event exceeds sixty (60) consecutive days, the Party that was not prevented from performance by the Force Majeure Event has the right to terminate this Agreement upon written notice to the other Party. This section shall not supersede or preclude the exercise of any right either Party may otherwise have to terminate this Agreement. Article 23. MATERIALITY AND WAIVER OF BREACH. Each requirement, duty, and obligation outlined in this Agreement was bargained for at arm's length and is agreed to by the Parties. Each requirement, duty, and obligation outlined in this Agreement is substantial and essential to the formation of this Agreement, and each is, therefore, a material term. City's failure to enforce any provision of this Agreement shall not be deemed a waiver of such provision or modification of this Agreement. A waiver of any breach shall not be deemed a waiver of any subsequent breach and shall not be construed as a modification of this Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 16 Agreement. To be effective, any waiver must be in writing and signed by an authorized signatory of the Party granting the waiver. Article 24. INDEPENDENT CONTRACTOR. The Contractor and the City agree that the Contractor is an independent contractor concerning the Work provided under this Agreement. Nothing in this Agreement shall be considered to create the relationship of employer and employee between the Parties hereto. Neither Contractor nor any employee of Contractor shall be entitled to any benefits accorded City employees by virtue of the services provided under this Agreement. The City shall not be responsible for withholding or otherwise deducting federal income tax or Social Security, or for contributing to the state industrial insurance program, or otherwise assuming the duties of an employer with respect to the Contractor or any employee of the Contractor. The Contractor shall not have the right to bind the City to any obligation not expressly undertaken by the City under this Agreement. Article 25. OWNERSHIP AND USE OF DOCUMENTS. Any and all Construction Drawings produced for the City become the property of the City without additional payment by the City. The Contract Documents, in whole or in part, are to be used by the Contractor only for the Project and the Work and shall not be used by the Contractor for any other purpose without written authorization by the City. This prohibition shall survive the completion or termination of this Agreement. The Contractor may retain copies of Contract Documents for record purposes. For security reasons, building plans, construction drawings, security features, technical details, and specifications of City-owned facilities are not public documents. The Contractor may share these documents with employees and subcontractors as needed to perform the Work; however, the Contractor and its subcontractors shall not release such plans, drawings, and specifications to any other third party without the City's prior written approval. Upon expiration or termination of this Agreement, any and all Construction Drawings and documents shall become the property of the City and shall be delivered by the Contractor to the City within seven (7) days after expiration or termination. Any compensation due to the Contractor may be withheld until all documents are received as provided in this Agreement. Article 26. ATTORNEY'S FEES. If either Party brings suit to enforce the Agreement, each Party shall bear its own attorney's fees, expenses, and court costs through trial and appeal. Article 27. WAIVER OF CHAPTER 558, FLORIDA STATUTES. Pursuant to Section 558.005(1), Fla. Stat., the Contractor and City agree to opt out of the requirements of Chapter 558, Fla. Stat. Article 28. SURVIVAL. The Contract Documents and the Contractor's obligation to perform corrective Work survive the final completion of the Work and final payment. Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 17 Article 29. TERMINATION FOR NON-APPROPRIATION. This Agreement is expressly conditioned upon the availability of funds lawfully appropriated and available for the purposes set out herein, as determined in the sole discretion of the City. If funding for this Agreement is in multiple fiscal years, funds must be appropriated each year before costs are incurred. Nothing in this paragraph shall prevent the making of contracts with a term of more than one year, but any contract so made shall be executory only for the value of the work or services to be rendered or paid for in succeeding fiscal years. If funds to finance this Agreement become unavailable, the City may terminate this Agreement without penalty on the last day of the fiscal period for which funds were legally available. The City shall be the sole and final authority regarding the availability of funds. Article 30. THIRD-PARTY BENEFICIARIES. Neither Contractor nor City intends to primarily or directly benefit a third party by this Agreement. Therefore, the Parties acknowledge that there are no third-party beneficiaries to this Agreement and that no third party shall be entitled to assert a right or claim against either of them based upon this Agreement. Article 31. GOVERNING LAW; JURISDICTION; VENUE; LITIGATION. 31.1 The Contract Documents shall be construed and interpreted, and the rights of the Parties hereto determined, in accordance with Florida law without regard to conflicts of law provisions. 31.2 The Contractor and City submit to the jurisdiction of Florida courts and federal courts located in Florida. The Parties agree that the proper venue for any suit concerning this Agreement shall lie exclusively in Palm Beach County, Florida, or the Federal Southern District of Florida. The Contractor agrees to waive all defenses to any suit filed in Florida based upon improper venue or forum non conveniens. 31.3 WAIVER OF JURY TRIAL. THE CITY AND CONTRACTOR HEREBY MUTUALLY KNOWINGLY, WILLINGLY, AND VOLUNTARILY WAIVE THE RIGHT TO TRIAL BY JURY. NO PARTY NOR ANY ASSIGNEE, SUCCESSOR, OR LEGAL REPRESENTATIVE OF THE PARTIES (ALL OF WHOM ARE HEREINAFTER REFERRED TO AS THE "PARTIES") SHALL SEEK A JURY TRIAL IN ANY LAWSUIT, PROCEEDING, COUNTERCLAIM, OR ANY OTHER LITIGATION PROCEEDING BASED UPON OR ARISING OUT OF THE CONTRACT DOCUMENTS, OR ANY COURSE OF ACTION, COURSE OF DEALING, STATEMENTS (WHETHER VERBAL OR WRITTEN) OR ACTIONS RELATING TO THIS AGREEMENT. THE PARTIES ALSO WAIVE ANY RIGHT TO CONSOLIDATE ANY ACTION IN WHICH A JURY TRIAL HAS BEEN WAIVED WITH ANY OTHER ACTION IN WHICH A JURY TRIAL HAS NOT BEEN WAIVED. THE PROVISIONS OF THIS PARAGRAPH HAVE BEEN FULLY NEGOTIATED BY THE PARTIES. THE WAIVER CONTAINED HEREIN IS IRREVOCABLE, CONSTITUTES A KNOWING AND VOLUNTARY WAIVER, AND SHALL BE SUBJECT TO NO EXCEPTION. NEITHER THE CITY NOR THE CONTRACTOR HAS IN ANY WAY AGREED WITH OR REPRESENTED TO THE OTHER OR ANY OTHER PARTY THAT THE PROVISIONS OF THIS PARAGRAPH WILL NOT BE FULLY ENFORCED IN ALL INSTANCES. THIS PARAGRAPH'S PROVISIONS SHALL SURVIVE THE EXPIRATION OR TERMINATION OF THIS AGREEMENT. Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 18 Article 32. CONTROLLING PROVISIONS. Except as otherwise explicitly provided herein, in the event of any conflict between the specific provisions of this Agreement and the requirements or provisions of the ITB and/or Bid, the provisions shall be given precedence in the following order: (1) this Agreement, (2) the ITB: and (3) the Bid. Wherever possible, the provisions of the documents shall be construed in such a manner as to avoid conflicts between the provisions of the various documents. Article 33. REGULATORY CAPACITY. Notwithstanding the fact that the City is a municipal corporation with certain regulatory authority. the City's performance under this Agreement is as a Party to this Agreement and not in its regulatory capacity. If the City exercises its regulatory authority, the exercise of such authority and the enforcement of applicable law shall have occurred under the City's regulatory authority as a governmental body separate and apart from this Agreement and shall not be attributable in any manner to the City as a Party to this Agreement. Article 34. PRIOR AGREEMENTS, AMENDMENTS, ENTIRE AGREEMENT. This Agreement, including the ITB, the Bid, and the Exhibits incorporated into it in their entirety, embodies the entire agreement and understanding of the Parties concerning the subject matter of this Agreement and supersedes all prior and contemporaneous agreements and understandings, oral or written, relating to said subject matter. This Agreement may only be modified by a written amendment duly executed by the authorized representatives of the City and Contractor. Article 35. SEVERABILITY. If any provision of this Agreement or application thereof to any person or situation shall, to any extent, be held invalid or unenforceable, the remainder of this Agreement and the application of such provisions to persons or situations other than those as to which it shall have been held invalid or unenforceable, shall not be affected thereby and shall continue in full force and effect, and be enforced to the fullest extent permitted by law. Article 36. ASSIGNMENT. The Contractor shall not assign this Agreement in whole or in part without the written consent of the City, which may be withheld, conditioned, or delayed at the City's sole discretion. The Contractor shall not assign any monies due or to become due to it hereunder without the previous written consent of the City and Contractor's Surety, with the Contractor acknowledging that until the final payment request is approved, the amount of monies due or to become due to Contractor or that may be due from Contractor to City has not been fixed or finally determined. Assigning this Agreement shall not relieve the Contractor or its Surety from any contract obligations. Article 37. NO WAIVER. The City's failure to enforce any provision of this Agreement shall not be deemed a waiver of its right or power to enforce such provision or a modification of this Agreement. The failure to assert a breach of a provision of this Agreement shall not be deemed a waiver of such breach or any subsequent breach, nor shall it be construed to be a modification of the terms of this Agreement. Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 19 Article 38. COUNTERPARTS AND MULTIPLE ORIGINALS. This Agreement may be executed in multiple originals and may be executed in counterparts, whether signed physically or electronically, each of which shall be deemed to be an original, but all of which, taken together, shall constitute one and the same agreement. Article 39. EFFECTIVE DATE. This Agreement shall become effective on the date it is executed by the last Party to sign the Agreement(the"Effective Date"). The Effective Date shall be the date of the last signature below." (SIGNATURES ON FOLLOWING PAGE) Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 20 IN WITNESS WHEREOF, the Parties have hereunto set their hands and seals on the day and year set forth below their respective signatures. CITY O OYNTON BEACH, FLORIDA CONTRACTOR NAME ___/eit1Rebecc Iton, Mayor (Signature), C pany 01 a(), �c Timottny COnrci cl Date Print Name ofAuthorized Official Qu(A,t eiQ s( COn cf0-00Y Title Approved as to Form: C9 ((s,tv\`a ` C „Aze,(/A 1am6 Date Shawna G. Lamb, City Attorney (Corporate Seal) Attest/Authenticated: Att: te. Authenticate . (Signature), Witness ithi 11 Maylee De sus, City Clerk Print Name � 1 pN BFq ‘�� i0J. RATE•• • C� 1 1 iiY:• Cjo�Qor1� : i '1,'O •.•�' ..\, Q' / 111 • '�L�° ••F\.o - Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 21 CORPORATE ACKNOWLEDGEMENT STATE OFn VI ,t�� , ��) COUNTY OF pro eA vatni The foregoing instrument w.s acknowledged before me by means ofsical pre ence o r ip line notarization, this a day of .4 , 20 bys l�� �- �( of .' �r _ , 1. IV , , o ehalf of the company. They are personally known to me or have produced p L- as identification. Notary Public State of Florida t , A (leen Gonzalez I N TARY PUB!' My Commission HH 446445 I 4 tlrl Expires 9/20/2027 ( \-f-W al (Name of Notary Typed, yped, Printed, or Stamped) " 14CD ki-6 Commission No. Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 22 EXHIBIT A PROJECT SCHEDULE Oyer Park Fire Boat Lifts Installation Project AKA Boynton Beach Boating Safety Program Phase II 23 EXHIBIT A PROJECT TIMELINE Project substantial completion shall be within Ninety (90) calendar days from Contractor's receipt of City's Notice to Proceed. Final Completion shall be THIRTY (30) calendar days from date of substantial completion totaling One Hundred Twenty (120) calendar days. EXHIBIT B CONTRACT PRICE BID FORM Oyer Park Fire Boat Lifts Installation Project 24 AKA Boynton Beach Boating Safety Program Phase II 25-026B OYER PARK FIRE BOAT LIFT INSTALLATION PROJECT SEASIDE MARINE CONTRACTORS Line Unit of Item Description QTY. Measure Unit Price Total 1 Indemnification 1 Lump Sum $ 26.00 $ 26.00 Mobilization/Demobilization Bonds,Insurance and General Requirements,and As-Built Record Drawings.Contractor shall be limited to a max of six percent(6%)of 7,904.60 2 the total bid price. 1 Lump Sum $ 7,904.60 $ Total General Conditions $ 7,929.50 SELECTIVE DEMOLITION 1 I Selective Demolition,timber piles,aluminum railing,fish cleaning station,etc. 1 Lump Sum $ 4,700.00 $ 4,700.00 Total Selective Demolition $ 4,700.00 CONCRETE 1 I Concrete support piles-14"X45', I strand FDOT(4)piles per lift, see plans. 1 Lump Sum $ 36,000.00 $ 36,000.00 Total Concrete $ 36,000.00 METALS 24k Aluminum cradle lifts supply 4 pile,2-motor,standard kits, includes electrical contoles, 1 aluminum bunks and hardware 1 Lump Sum $ 48,688.00 $ 48,688.00 Aluminum catwalks-(1)12"&1 2 16"each lift(4)total 1 Lump Sum $ 7,500.00 $ 7,600.00 Aluminum hinged access 3 platforms(1)each lift. 1 Lump Sum $ 4,800.00 $ 4,800.00 Aluminum stair ststem(4)steps 4 with handrail(1)each lift. 1 Lump Sum $ 7,600.00 $ 7,600.00 Total METALS $ 68,388.00 SPECIALTIES 1 1Fire extinguisher and cabinet (marine grade) 1 1 Lump Sum $ 17,000.00 $ 17,000.00 TOTAL SPECIALTIES $ 17,000.00 ELECTRICAL Electrical Design complete design by contractor for procurement&installation 1) Elec.Wiring,tie into new shore power pedestal;2)Power& lighting(2)shore power pedestals shore power pedestal to exising water service. 30,000.00 1 1 Lump Sum $ 30,000.00 $ Total ELECTRICAL $ 30,000.00 SUBTOTAL OF ITEMS I $ 163,017.50 ALLOWANCES 1 (Permit Fee reimbursement I 1 , Lump Sum $ 16,000.00 $ 16,000.00 TOTAL ALLOWANCES $ 16,000.00 TOTAL INCLUDING INDEMNIFICATION AND ALLOWANCE $ 178,017.50