MInutes 08-22-89 MINUTES OF THE SPECIAL CITY COMMISSION MEETING
HELD IN COMMISSION CHAMBERS, CITY HALL, BOYNTON BEACH,
FLORIDA, ON TUESDAY, AUGUST 22, 1989
PRESENT
Gene Moore, Mayor
Robert Olenik, Jr., Vice Mayor
Ezell Hester, Jr., Commissioner
Arline Weiner, Commissioner
Lee Wische, Commissioner
George Hunt,
Interim City Manager
Betty Boroni, City Clerk
Raymond Rea,
City Attorney
Mayor Moore called the meeting to order at 5:00 P.M.
Advertisement for City Manager
Discussion took place relative to the advertisement to be
run for the City Manager's po§ition. Interim City Manager
Hunt remarked the ad had been sent out for publication in
professional journals and would be run as often as possible
for the money that had been allocated. Mr. Hunt was
instructed to furnish the Commission with copies of the
applications as soon as they are received. At the end of
thirty days they will evaluate the response.
Chapel Hill Median Repair
Mayor Moore addressed comments to Commissioner Weiner rela-
tive to repair of a road median in Chapel Hill. The Mayor
didn't approve of the way the matter was being handled.
Commissioner Weiner stated she had conveyed the ihformation
to the City Manager to investigate whose responsibility the
median is and she stated she had not guaranteed anything to
the residents of the subdivision.
Seppala and Aho Construction Project
Mr. Mortimer Offutt, Site Superintendent addressed the
Commission regarding the status of the construction. He
explained the Contract was signed in October, 1987. They
received notice to proceed on October 20, 1987. A building
permit was not received until January 11, 1988. They did
perform some construction during that time, however, it was
not possible to obtain inspections because the electrical
department and others wouldn't inspect as there was no
approved set of plans and specifications. Mr. Offutt stated
they notified the City of that fact and requested an exten-
sion of time.
Mr. Offutt indicated Seppala and Aho was hampered by the
lack of a set of plans and specifications for the existing~
buildings. As they demolished some areas they uncovere~
unanticipated circumstances that caused severe and numerous
problems. They requested extensions of time for these.
MINUTES - SPECIAL CITY COMMISSION
BOYNTON BEACH, FLORIDA
AUGUST 22, 1989
Seppala and A_ho currently had 118 outstanding field orders
received from the architect to clarify the drawings and to
direct them on how to proceed on changes. They have
responded to 115 with proposals for prices, etc. They have
been acting on field orders as a directive to proceed, as
long as they have an agreement in principle by all parties
as to price. Mr. Offutt indicated they had requested 141
change orders, 30 of which were incorporated into field
orders and would therefore be voided. The remaining 107
requests for change orders were submitted to the architect
and owner. To date the architect has approved 63 of the
113 submitted field orders. Mr. Offutt remarked the owner
had paid for 49 field orders and 14 requests for change
orders. Discussion took place on the difference between
field orders, oral change orders and formal change orders.
Mr. Offutt stated they were not supposed to perform any work
until they had received written change orders. However,
because of the delay that~it would cause they have proceeded
prior to that. He stated they had paid their subcontractors
$200,000 more than they had received from the City.
Elaboration took place on problems encountered with soil
conditions under the Police Dept. Mr. Offutt stated when
they came to a virtual standstill at the Police Dept. all
parties were advised of the problem and they needed direc-
tion to proceed. He indicated they were attempting to acce-
lerate the construction schedule in an effort to complete
the project by the end of October, hopefully.
Mr. Offutt stated Seppala and Aho was looking for a reduc-
tion in their retainage. Their Contract calls for a reduc-
tion once substantial completion has been attained. He felt
it had been agreed by everybody that substantial completion
had been attained and they were now entitled to a reduction
of the retainage, less three times the value of any work
that is not complete. Because of the performance bond, he
felt the City would be safe in paying them. Although the
contractor had requested multiple time extensions, he
remarked they have not received any time extensions. He
elaborated on being "under the gun" to complete the project
and the fact that the original completion date had passed,
due to unanticipated problems encountered. He felt the
contractor was entitled to those time extensions under the
circumstances. Basically, Mr. Offutt did feel the City had
impeded the contractor from completing the project in a
timely manner.
Discussion took place dealing with a problem encountered in
the Police Dept. when concealed ceilings were discovered.
The contractor had no choice but to remove the ceilings. He
2
MINUTES - SPECIAL CITY COMMISSION
BOYNTON BEACH, FLORIDA
AUGUST 22, 1989
felt they should have received instant authorization to
proceed from the City, but they did not. They received a
field order to proceed, but not a change order. Mr. Offutt
indicated all orders that have gone through have been either
field orders or oral change orders and this is abnormal.
Conversation took place relative to the membrane topping to
be applied to the parking garage, which was called for in
the original drawings. He stated this had been deleted from
the Contract and another material was specified for applica-
tion. Now he understood the City was desirous of going back
to the original topping. The cost was discussed. Mr.
Offutt indicated that since he has been on the project, he
had interposed objections to directions given to change the
original plans and specifications and had been overruled.
Mr. Offutt enumerated specific figures on the project and
estimated it would take at least another $300,000 to
$400,000, to complete the project, including delay damages.
He elaborated on sequencing of construction and the
inability of the contractor to work on certain rooms once
the areas became occupied.
Vice Mayor Olenik made comments about inacceptability of
work performed in the Fire Dept.'s bathrooms. Mr. Offutt
responded on complications encountered in that area.
Mr. Offutt stated to date you couldn't get a C.O. on that
place, not because the contractor hadn't completed the work
but because some of the work doesn't meet code. He didn't
feel that was the contractor's responsibility. Vice Mayor
Olenik asked why it wouldn't be the contractor's respon-
sibility? Extensive conversation took place relative to
responsibility.
Interim City Manager Hunt remarked that he had met with Mr.
Offutt on Friday afternoon, August 18, 1989. He observed
that many of the things coming up at the present time,
never came up at that meeting. Some of the things Mr.
Offutt was saying diametrically opposed things said pre-
viously.
Discussion took place as to when Mr. Offutt began working on
this construction project. Mr. Offutt stated he arrived
near the end of May, possibly June 1, 1989. He had worked
for Seppala and Aho prior to that time. He was not present
at the pre-construction and pre-bid meetings, nor was he
present for the first 18 months of the project.
5~. Hunt remarked on a crucial point omitted in today's
discussion which happened at the pre-bid and pre-
construction conference. At that time, John Seppala and Ed
A2no were fully aware that the City needed complex phasing
MINUTES - SPECIAL CITY COMMISSION
BOYNTON BEACH, FLORIDA
AUGUST 22, 1989
and working around employees. They agreed to that complex
phasing, it was included in their bid for the project and
they submitted schedules which the City agreed to. Further
discussion took place dealing with phasing and extensions.
Mr. Offutt stated that when the contractor is entitled to a
time extension and the City doesn't issue a time extension
and requires the contractor to finish under the original
completion date, the contractor is entitled to damages for
that and they intend to seek those damages.
Discussion took place dealing with the list of 20 change
orders which the Commission had approved and which total
$222,063.83. Mr. Hunt indicated the statement made by Mr.
Offutt previously that every change order made was done on
oral field orders, was not correct.
Bill DeBeck, Project Manager stated most of the contractor's
work was done before they got the written change orders. He
received written field orders before he did the work. Mr.
Offutt stated a field order specifically prohibits the
contractor from proceeding with the work if there is a
change in the cost or if there is a time extension required.
Mr. Offutt remarked that since the beginning of this job,
the City and architect have agreed that a field order is a
directive to proceed.
Mayor Moore understood if any change order was made, par-
ticularly if it involved an overrun, it was to be generated
through the contracting party or the City Commission. Mr.
~unt stated when the original budget for this program was
set up, there was a contingency factor, because they realized
there would be things that would happen in the field that
would grind the project to a halt, if they had to wait two
or four weeks to bring it back to the Commission.
Uiscussion took place. Mr. Offutt commented that if they
don't receive a change order they can't pay their sub-
contractors. He felt change orders approved by the archi-
tect, should be processed, not held up.
Mayor Moore asked if the Commission was advised of change
orders before the work was done or did they come to the
Commission after the fact? Mr. Hunt responded they pri-
marily came to the Commission afterwards. Mr. Hunt remarked
that almost none of the change orders approved to date, have
been approved at the price the contractor originally sub-
mitted. They all have been negotiated and reduced, once time
and materials were accurately described. Mr. Offutt
responded on factors involved.
4
MINUTES - SPECIAL CITY COMMISSION
BOYNTON BEACH, FLORIDA AUGUST 22, 1989
Mr. Hunt stated the City's position is that total overruns
on the project to fruition will total $367,168.24.
Conversation took place on why the architect indicates
approximately $400,000. Mr. Hunt said Mr. Of~utt was sent
here after the company fired Mr. Aho because they knew they
were in trouble and were late. Mr. Hunt felt a great deal
of the discussion taking place was a smokescreen. When the
parties sit down at a negotiating table and, if necessary,
with an arbitrator, he was sure the "smoke" would disappear.
Mr. Offutt stated it was the City that initiated his assign-
ment to the job, by sending the contractor a nefarious
letter saying they were late on the project and to this date
the City is entitled to $150,000 in liquidated damages. He
elaborated.
Mayor Moore felt the Commission should take the position
that it doesn't know where it stands. There are varying
estimates on overruns on the project. He demanded the new
Internal Auditor be allowed to look into this extensively.
Mr. Hunt commented he would welcome Mr. Rubin's assistance.
Mayor Moore apologized to Mr. Offutt publicly, because the
Mayor didn't know where the City stands.
Commissioner Weiner felt that many of these problems were
encountered because we were dealing with an old building and
new construction.
Bill DeBeck commented he too would welcome Mr. Rubin's
assistance. The records are up-to-date and complete. He
didn't feel there was any complex question here, but rather
it was all in black and white. Discussion took place on the
anticipated completion date for various areas.
Mayor Moore referred to numerous Seppala and Aho memorandums
to the architect, where they repeatedly requested authoriza-
tion to complete the project. The contractor had indicated
these were never answered. Mr. DeBeck stated they were
responded to verbally.
Mr. DeBeck remarked that a construction meeting is held
every Tuesday where items are discussed at length. The
contractor, architect, representatives of the Building Dept.
and Mr. DeBeck attend these meetings. At the meetings most
questions are ironed out in order to not produce a flurry of
paperwork. Discussion took place regarding documentaton,
and issuance of field orders and change orders.
Conversation took place regarding the practicality of bringing
change orders to the Commission for approval prior to the
work and holding work up. The Mayor felt the Commission
should be making the decisions, not someone in the field.
MINUTES - SPECIAL CITY COI~MISSION
BOYNTON BEACH, FLORIDA
AUGUST 22, 1989
He thought any more change orders that would involve an
expenditure of taxpayer money should come to the Commission
prior to completion of work.
Vice Mayor Olenik stated he would like Mr. Offutt to provide
justification of $1,000,000 worth of change orders. He
wanted the information in his mailbox by 5:00 P.M. the next
day. If the contractor can justify $1,000,000, he wanted to
see it. Mr. Offutt said the information was in front of the
Commission, in black and white. He referred to documen-
tation from the contractor and he noted specifics.
Reference was made to damages.
Vice Mayor Olenik noted the various dates that different
areas were supposed to be complete. He asked if there were
additional days the contractor is requesting approval of,
above and beyond what he was aware of? Mr. DeBeck answered
affirmatively and it was noted some of these days are under
dispute.
Mr. Jordan Miller provided the Commission with written
information describing exactly what a field order is. The
Vice Mayor read the information outloud to the Commission.
Discussion took place on the process.
Commissioner Wische wanted to know what the bottom line is.
How much is it going to cost to complete the project? He
felt the Internal Auditor's assistance was needed.
Mr. Hunt stated the original contract cost was
$8,521,714.00. If you add approximately $370,000 in change
orders, you would have the total. He suggested anything
Mr. Offutt claims in excess of that would be offset by
claims for damages that the City makes and anything that
remains in dispute is not something that Mr. Rubin would be
able to make a decision on, but an arbitrator would have to
decide.
The consensus of the Commission was that Mr. Rubin would
investigate the facts and report back to the Commission.
Mr. Hunt repeated his prior statement that Mr. Offutt's sta-
tements tonight were different from statements made in the
City Manager's office on August 18, 1989. He took his
remarks "with a big grain of salt." Mr. Offutt responded to
the remark and some disagreement took place.
The Commission agreed Mr. Rubin should isolate himself to
this project. He is to report back to the Commission as
early as possible.
6
MINUTES - SPECIAL CITY COMMISSION
BOYNTON BEACH, FLORIDA
AUGUS~ 22, 1989
Mr. DeBeck felt Mr. Rubin should take the phasing into con-
sideration when doing his investigation as well as examining
the dollars. Mayor Moore stated Mr. Rubin was not going to
render a legal opinion. He is a highly qualified Internal
Auditor and would know how to proceed.
ADJOURNMENT
The meeting properly adjourned at 6:08~.
/ / .-. Mayor
~'/ ~ O~Vic~e yor
Comm~ s ioner
'Commissioner
Commissioner
ATTEST:
Ci~ Clerk
Recording Secretary
(Two Tapes)