R06-197 II 1 RESOLUTION NO. R06- ,q 1 2 3 A RESOLUTION OF THE CITY OF BOYNTON 4 BEACH, FLORIDA, AUTHORIZING CHANGE ORDER 5 #6 WITH SESSOMS CONSTRUCTION FOR THE 6 BOYNTON BEACH LIBRARY PROJECT; 7 DECREASING THE GENERAL CONTRACTOR'S 8 CONTRACT SUM BY $396,137.52 AND INCREASING 9 THE CITY'S CONSTRUCTION COSTS BY $367,780.00 10 TO PAY FOR OWNER DIRECT PURCHASES FOR A 11 TOTAL NET SAVINGS OF $28,357.52; PROVIDING 12 FOR A $50,000.00 CONTINGENCY; AND PROVIDING 13 AN EFFECTIVE DATE. 14 15 WHEREAS, the City of Boynton Beach, through owner direct purchases, has been 16 able to take advantage of a Tax/Cost Savings Recovery Program; and 17 WHEREAS, due to these savings the General Contractor's contract will be reduced 18 by the sum of$396,137.52; and 19 WHEREAS, the City's construction costs will be increased by $367,780.00, saving 20 the City a net sum of$28,357.52; and 21 WHEREAS, Change Order #5 was to include the approval of an additional 22 $50,000.00 for contingency work; and 23 WHEREAS, the City of Boynton Beach has reviewed Change Order #6 and has 24 determined that the contract changes set forth therein are both necessary and appropriate. 25 NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF 26 THE CITY OF BOYNTON BEACH, FLORIDA, THAT: 27 Section 1. The foregoing "Whereas" clauses are hereby ratified and confirmed as 28 being true and correct and are hereby made a specific part of this Resolution upon adoption 29 hereof. 30 Section 2. The City Commission of the City of Boynton Beach, Florida does T:ICAIRESOICHANGE ORDERSlLibrary Project CO 6.doc II 1 i hereby authorize and direct the approval and execution of Change Order 006 decreasing the 2 General Contractor's contract with Sessoms Construction for the Library Expansion Project 3 by $396,137.32 and increasing the City's construction costs in the amount of $367,780.00 4 for a total savings of $28,357.52 due to owner direct purchases, a copy of which is attached 5 hereto as Exhibit "A". 6 Section 3. The City Commission approves $50,000.00 for contingency work 7 requested in Change Order #5. 8 Section 4. The new contract sum, including all pnor change orders, owner 9 equipment, owner direct purchases and contingency is $7,237,589.48. 10 Section 5. This Resolution shall become effective immediately upon passage. 11 PASSED AND ADOPTED this ~ day of November, 2006. 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 CITY OF BOYNTON BEACH, FLORIDA 1;;7:?t~ Vice Mayor c-....~.~. .::~... -, -- /('-6 r ~-:J'" 1"........ j-':~~~,~...,-.~_.~~.._~.' ,', Commissioner ~ ;;-. - ... . ..~._-_/ ~ .......". '.- }-.-", r-L /~--- Commissioner ATTEST: t '\<,'" .<'-::_0_.,.-,:-,".,'..-::,/ T:IC~~SO~GE ORDERSlLibrary Project CO 6.doc .AIA Document G70r" - 2001 EXHIBIT A KO&' - (q 7 Change Order PROJECT (Name and nddress): Boynton Beach Library 208 South Seacrest Blvd. Boynton Beach, FL 33435 TO CONTRACTOR (Name and address): Sessoms Construction 7485 Davie Rd. Ext. Hollywood, FL 33024 CHANGE ORDER NUMBER: 006 DATE: October 31,2006 OWNER: ~ ARCHITECT: ~ CONTRACTOR: ~ FIELD: D OTHER: D ARCHITECT'S PROJECT NUMBER: 0320802 CONTRACT DATE: May 04, 2005 CONTRACT FOR: General Construction THE CONTRACT IS CHANGED AS FOLLOWS: (Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives) A) Fire Resistive Cementious Fire Spray........................ .......................................................... ............$8,947.00 B) Rexel Cons. Electrical Supply (Sales Tax Savings Reduction) ........................ ......................................($29,798.70) C) Electrical Supplies (Sales Tax Savings Reduction) ..... ............................... .....................................($195,960.00) D) YKK AP (Sales Tax Savings Reduction) ......... ................................... ................... .........................($45,629.82) E) Plan Reproduction ..................................... .... . ..................... ..................... .................. ....$305.00 F) Elevator Dimensions.................... ................................................................................. ......... ...$3,786.00 G) Stain Wood Doors ......................... ............................... ...................... ..$5,831.00 H) Spyder double tie backs ..................... ... ............... ......... .................... ........... .........($1,600.00) I) Trane Direct purchase (Sales Tax Savings Reduction) ... ...... ....... ...................... . .................. ........ ....($100,560.00) J) Ships Ladder .............................................. ...... ...................... .................... ....................... ....$5,709.00 K) Credit for Security Gates ....... .... ............... ................... . .................... . .................... ..........($30,492.00) L) Towel Dispencsers ............ ...................... .................. .....................................................................................$867.00 M) Self Closing Taps................. ............. ... .............. ......... ..................... ................... ....................$923.00 N) Additional Conduit for data ...................... ................ ......... .................... .................... .......... ......$13,750.00 0) Credit Permit Fees ................................... ........... .... ..................... ........... .......... ....$(32,215.00) The original Contract Sum was The net change by previously authorized Change Orders The Contract Sum prior to this Change Order was The Contract Sum will be decreased by this Change Order in the amount of The new Contract Sum including this Change Order will be The Contract Time will be increased by Zero ( 0 ) days. The date of Substantial Completion as of the date of this Change Order therefore is January 21, 2007 $ $ $ $ $ 5,727,485.00 1,351,325.00 7,078,810.00 (396,137.52) 6,682.672.48 1IC'r'f~'d"""'ft_t:lm'flgeS'tJrttre-eunttlltt~-eorrtrnt:r'l'irreurtlu:mmre_aximmrr1'rtce-wtrtr:l1 how-eoo...lMlIhefi..e~4:"_ie..(;RoRg&.QiRl€,,_,,i-I_...Rd-lirHo-Ao_~.."""~..otlt<he.Qwfter__& Qmtam..b;-ift..w..ieh-ease-a-€h1mge-<3rd~eetlted-to-3ttper~e-etnr.'l"LI u...l;on-C-itftnge-Direetive:- AlA Document G701 TM - 2001. Copyright @ 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AIAIIII Document Is protected by U.S. Copyright law and International Treaties. Unauthorized reproduction or distribution of this AlA- Document, or any 1 portion of it, may result In severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AlA software at 10:59:25 on 11/0212006 under Order No.1000228140_9 which expires on 3/21/2007, and is not for resale. User Notes: (4068729110) NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. SchenkelShultz Architecture ARCHITECT (Firm name) 1300 N. Congress Avenue, West Palm Beach, FL 33409 ADDRESS ) I!-D'J.. 0(, Sessoms Construction CONTRACTOR (Firm name) 7485 Davie Rd. Ext., Hollywood, FL 33024 . ADD~~ ~ (Signaru~ I.Jit t;;tJ~~Il7-S (Typed name) lI/oJ/Ob DATi! I City of Boynton Beach OWNER (Firm name) 208 South Seacrest Blvd., Bounton Beach, F[, 3435 ADD S Samuel (Typed BY (S gnarure) KURT BRESSNER aANACER (Type ON BEACH. FL (/ ..~ -06 DATE DATE CITY ATTORN~ AlA Document G701 1M - 2001. Copyright @ 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AlAe Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AlAe Document, or any 2 portion of It, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AlA software at 10:59:25 on 11102/2006 under Order No.1000228140_9 which expires on 3/21/2007, and is not for resale. User Notes: (4068729110)