LEGAL APPROVAL
\
"-
7Im \
CITY of
BOYNTON BEACH
@
~.' .
.~-
100 E. Boynton Beach Blvd.
P. O. Box 310
Soynton'Seach. Florida 33435.0310
(407) 734.8111
OFFICE OF THE PLANNING DIRECTOR
November 1, 1989
~
CH2M Hill
Attn: Mr. Robert T. Clapp, P.E.
800 Fairway Drive, suite 350
Deerfield Beach, FL 33441
RE: Boynton Beach Water Treatment Plant containment structure
Administrative 'Site Plan - File No. 358
Dear Mr. Clapp:
Please be advised that on Thursday, ~October 19, 1989, the
(Technical Review Board approved-the referenced administrative
site plan subject to staff comments, copies of which are
attached.
...
"'-
These plans were approved subject to your compliance with the
attached stipulations. After you have amended your plans to
reflect these stipulations, please submit two copies of final
plan drawings with the changes incorporated to the Building
Department 'for permitting purposes.
-~.
The approval of the Technical Review Board entitles you ,to
construct only the improvements shown on the site plan. The
plan will be viewed procedurally as an as-built or record
drawing. If you have any questions concerning this matter,
please do not hesitate to contact me.
Very truly yours,
site
~?;~
TIMOTHY P. CANNON
Interim Planning Director
TJC:frb
Encs
cc: Interim City Manager
Technical Review Board
Building Official
Central File
02
L.
/
I
!
"-
-,,/
."-'
'.;....
...
....
"-
-"
:#~
BOYNTON BEACH WATER TREATMENT PLANT
(CONTAINMENT STRUCTURE)
..
BUILDING DEPARTMENT:
ADMINISTRATIVE SITE PLAN
STAFF COMMENTS
See attached comments
s
'-,
~.~.
-~.
Jf!IJn'
MEMORANDUM
October 23, 1989
TO: Carmen Annunziato
Planning 'Director
FROM: Michael E. Haag
Development Compliance Administrator
RE: ADMINISTRATIVE SITE PLAN UNDER $100,000 for
BOYNTON BEACH WATER TREATMENT PLANT CONTAINMENT
STRUCTURE AND FUEL TANK
Upon review of the above mentioned project, the following
comments must be addressed in order to conform with Boynton Beach
City Codes:
1.
Show on site plan drawing all existing easements at tank
location and identify location of containment structure and
fuel tank by showing setback dimensions from two adjacent
property lines. Show distance in feet between tank and all
adjacent buildings.
.F
2. Applicant must obtain an Environmental Review Permit.
In order to facilitate the permitting process, the following
information should be included within your documents submitted to
the Building Department for required permits:
1. Acquire all federal, state and county permits required to
install fuel tank and containment structure.
2. Provide written verification from Florida Power and Light
Co. that location of containment structure and fuel tank is
acceptable in relation to the existing power pole and/or
power lines.
MEH:ld
xc: Don Jaeger
BBWATERT.DOC
7#f~~
-RECEIVED
OCT ~2S 1989
PLANNING DEPT~
-9
_CITY of
BOYNTON BEACH
#3it
\.
100 E. Boynton Beach Blvd.
r. O. Box 310
Boynton BC:lch, Florida 33435.0310
1407) 734.8111
OFFICE OF THE PLANNING DIRECTOR
October 25, 1989
I
CH2M Hill
Attn: Robert T. Clapp, P.E.
800 Fairway Drive, Suite 350
Deerfield Beach, Fl 33441
RE: Boynton Beach Containment Structure
Dear Mr. Clapp:
.
Please be advised that this letter constitutes an Environmental
Review Permit as required in Section 8A3 of Appendix A, City of
Boynton Beach Code of Ordinances. This permit allows for the
replacement of fuel storage tanks at 124 S.E. 15th Avenue. The
condition of the issuance of this permi.t is the memorandum from
the Developmental Compliance Administrator, dated October 23,
1989.
0#
If you have any questions concerning this matter, please do not
hesitate to contact me.
Yours very truly,
CITY OF BOYNTON BEACH
C._
-
. . ./~
CARMEN S. ANNUNZIATO, AICP
Planning Director
JJG:frb
cc: Environmental:Review Committee
Central File
~
.
.s---
: , ':;. \~:.; t' ~,,;, I; \' ",,_!~\,.~ 1 :',11 1.. ~ "<. ~~. .\;~:" j. ,J" },
:1.. ~L"""'\'''''\.E.I''.-l._.It'\hJ..t:''.'1'~''"~''~'~'1It.t'''''''.,:'1rJ....:~:f..~~<(,',"'J'_""'.~,~,,,,,,,, ,.' :1~S ")"~'i,.;J " .. ~ ." -,'
.... - - . ~ - ~~ . - - . _...~_ "- ~~~',J , ',..,. t'. ~. ~, I. c :':.. __'J_ ~:" .J. 'l'.'
, .'
SITE PLAN APPROVAL APPLICATION
tI13s~
City of Boynton Beach, Florida
Planning and Zoning Board
This application must be filled out completely and accurately and
submitted in one (1) copy to the Planning Department. Incomplete
applications will not be processed.
Please print legibly or type all information.
I. GENERAL INFORMATION
1. Project Name: Boynton Beach Containment Structure
2. Date this application is accepted:
(to be filled out by Planning Dept.)
3. Applicant's name (person or business entity in whose name
this application is made):
City of Boynton Beach, Utilities
w
Address:
124 S.E. 15th Avenue
.. ,
---
..
Boynton Beach, FL 33435
Phone:
407/738-7461
4. Agent's Name (person, if any, representing applicant):
CH2M HILL -- Robert T. Clapp, P.E.
Address:
800 Fairway Drive, Suite 350
.....-
- ----
Deerfield Beach, FL 33441
Phone:
305/426-4008
5. Property OWner's (or Trustee's) Name:
John Guidry, P.E. Utilities Director, Boynton Beach
Address:
124 S.E. 15th Avenue
Boynton Beach, FL 33435
Phone:
407/738-7461
6. Correspondence address (if different than applicant or
agent)*:
N/A
* This is the address to which all agendas,
letters, and other materials will be mailed.
Planning Dept. 1/89
,
. .. .;.
~~s,
Page 2
7. What is applicant's interest in the premises affected?
(Owner, buyer, lessee, builder, developer, contract
purchaser, etc.)
Owner
8. Street address or location of site:
City of Boynton Beach Water Treatment Plant on Seacrest Boulevard
9. Legal description of site and property control #:
City of Boynton Beach Water Treatment Plant
10. Intended use(s) of site:
Storage of diesel fuel for an emergency generator
..
11.
Developer or builder: Cherokee Petroleum Services, Inc.
12.
Architect:
N/A
13. Landscape Architect: N/A
14.
Site Planner:
N/A
15. Engineer: CH2M HILL
16. Surveyor: N/A
17.
Traffic Engineer:
N/A
18. Has a site plan been previously approved by the City
Commission for this property? N/A
19. Estimated construction costs of proposed improvements shown
on this site plan: $80,000
Planning Dept. 1/89
7
~M8,
Page 9
IV. MISCELLANEOUS
(check)
The following materials must be submitted in one (1) copy:
1. A check, payable to the City of Boynton Beach, as per
the attached fee schedule.
N/A 2. For projects that generate at least three thousand
(3,000) vehicle trips per day or two hundred and fifty
(250) single directional vehicle trips in a one (1)
hour period, a traffic impact analysis must be submitted
3. Any other engineering and/or technical data, as may be
required by the Technical Review Board to determine
compliance with the provisions of the City's Code of
Ordinances.
v. CERTIFICATION
(I) (We) understand that this application and all papers and
plans submitted herewith become a part of the permanent
records of the Planning and Zoning Board. (I) (We) hereby
certify that the above statements and any statements or
showings in any papers or plans submitted herewith are true
to the best of (my) (our) knowledge and belief. This
applic ion w'll not be accepted unless signed according to
the in ru t'on~.
John u'd . Utilities Director
Signat e of Owner(s) or Trustee,
or Aut rized Principal if property
is owned by a corporation or other
business entity.
!()!9f7'f7
Date
VI.
AUTHORIZA~ AGENT
~~ ~r
Rnh~rr T. ClApp. P F.
Signature of Authorized Agent
1011918'1
Date
this apPliCatiO;~ I;, !t.lj1
Signat e of Owner(s) or Trustee, Date I
or Authorized Principal if property
is owned by a corporation or other
business entity.
hereby designate the above signed person as (my) (ou
r)
SPACE BELOW THIS LINE FOR OFFICE USE ONLY
Review Schedule:
Date Received:
Technical Review Board
Planning & Zoning Board
Community Appearance Board
City Commission
Date
Date
Date
Date
Stipulations of Final Approval:
Other Government Agencies/Persons to be contacted:
Additional Remarks:
?
Planni~g Dept 1/89
MEMORANDUM
Utilities No. 90-268
;:z -- $-A~
rJ/M ./ ~ ~$1
r~ECEIVED. .
TO:
J. Scott Miller,
city Manager
John A. Guidry, ~
Director of utilit&es \J
April 24, 1990
APR 21 19JO
PLANNlNG DE.PT~\
FROM:
---
DATE:
· SUBJECT: Permit Requirements - standby Generator at East Water
j Treatment Plant
We are finalizing the specifications and preparing to request
bids for purchase and installation of a standby generator for the
east water treatment plant. The generator is needed to supply
auxiliary electric power to run the east plant at near full
capacity during power outages and mandatory power reductions such
.
as was experienced during the past winter cold snap.
It is our intention to purchase a package power system installed
in its own housing, located between the existing fuel tank and
generator. It' should be noted that the existing generator is
sized to provide only one half plant capacity. With the plant
approaching full capacity, we would be unable to provide adequate
water supply during extended power outages without the purchase
of the second generator.
We questioned Jim Golden regarding submission to the TRB and he
suggested that we check with your office first to determine if it
constitutes a substantial change, or could the permit be applied
for directly from the Building Department?
The estimated cost for this generator is $200,000. To assist
your review, we have prepared an information package containing
site plan, photos showing existing site, renderings showing the
site after the generator is installed, and specification sheets
on the generator and housing desired.
Please let us know if TRB review is required.
cmd
xc: Building Department
(Jim Golden, Sr. City Planner
9