July 30, 1992
Mr. Christopher Cutro, Director of Planning
City of Boynton Beach
100 E. Boynton Beach Blvd.
Boynton Beach, Florida 33435
RE: Lighthouse Square Marina
Dear Mr. Cutro:
As per our last meeting with you and the developers of the Lighthouse Square
Marina, we are pleased to present the following phasing schedule for the
completion of construction for your review and consideration.
As you are aware, we are currently listed as an agenda item for the August 4th
City Commission meeting for a formal vote and consideration of this schedule.
Based on discussions with the developers and their financial institution,
we propose the project be completed as follows:
PHASE ONE:
*Lighthouse
*Marina and sea wall
*East Retain Building (10,000 suare feet)
*All site utilities, roadwork, landscape, parking
*East Restaurant
PHASE TWO: *West Retail Building (15,000 square feet)
*Two story Deli Building
*Harbor Master Building
*Parking at north side of Boynton Beach Blvd.
PHASE THREE: *Boat Storage Building
*Retail on South side of Boat Building
*West Restaurant
We anticipate Phase 1 to begin on November 1, 1992 and complete construction
within 9 months. Phase 2 will begin by March 1, 1993 with completion within
8 months. Phase 3 will begin by July, 1993 with completion by October, 1993.
In the event the leasing proceeds faster than expected, we will coordinate
earlier dates with your office. We look forward to hearing your comments
regarding the aforementioned, and appreciate your continued cooperation and
consideration.