REVIEW COMMENTS
TRB MEMORANDUM
.!~nua~y 27, 9~9
To: Tom Clark
From: Bill Flushing
Re: Zicaro's plumbing
1. A letter is required explaining why the first hour of a
three year storm (2.5 in.) is not retained on site as is
required by Boynton Beach Code. Copies of all permits and
agreements shall be included.
2. There should be no storm water flow over the sidewalk.
3. Certification shall be provided indicating that the light
poles comply with chapter 12 of the standard Building
Code (120 MPH wind loading) as per parking lot ordinance.
Bill Flushlng
M E M 0 RAN DUM
January 5, 1989
TO: CRAIG LIVINGSTON
FROM: TAMBRI J. HEYDEN, ASSISTANT CITY PLANNER
RE: ZICARO'S PLUMBING AT BOYNTON BEACH DISTRIBUTION CENTER
SITE PLAN SUBMITTAL
Please be advised of the Planning Department's comments with
respect to the above-referenced request:
1. Provide a cross section of the perimeter landscape
strip showing the deepening of this area to provide
additional on-site retention.
2. Contractors require one (1) parking space for every
500 square feet of gross floor area. Forty (40) parking
spaces would be required for this building; only twenty-
five (25) are shown.
3. Additional lighting information is needed including
minimum illumination level, photocell activation,
and a pole detail (parking lot lighting must be
mounted on poles around the perimeter of the lot).
4. Any freestanding signs must be located on all plans
and a detail provided indicating size, height, color,
materials, lettering style, and wording. If this
information cannot be provided at this time, a
future site plan approval for signage will be needed.
5. Dumpster detail is not labeled and the width is not
dimensioned. (Inside dimension must be 10 feet by
10 feet.)
6. Sidewalk should continue across driveway on site plan.
~u~.~
TAMBRI J. H DEN
TJH:ro
cc Central File
MEMORANDUM
February 6, 1989
TO: Mr. Jim Golden
Senior City Planner
FROM: Tom Clark
City Engineer
RE: Site Plans, Zicaro's Plumbing, Boynton Beach Distribution Center
COMMENTS:
1. Street lighting is required in the public Rights-of-Way. The street
lights are a bonded improvement and are shown on sheet 1 of 4 of the
subdivision development plans. A plan and cost estimate has been
requested by the City Engineer from Florida Power & Light Company, who
will use their own plans (approved by City) for street light installation.
Upon receipt of funds (as per F.P.& L. cost estimate) from the developer
or Surety Company, F.P.& L. will be authorized to install the street lights.
2. Drainage plans shall include inlet structures in dry grassed ponds or
swales. Storm sewers may be connected to inlet structures in the R.O.W.
No sheet flow across sidewalks is allowed, even though the Water Management
plan included the run-off from the platted lots. Regrading of the parking
lot may be necessary to accomodate the collection of rai.n fa.llon:site.
3. The current City standard for turnouts into the R.O.W. i.s not swaled.
Elevations indicating a swaled turnout should be revised as should the
typical section.
4. Stop signs should be 7 feet above grade.
5. Grassed swales should be 8 inches below crown grade of the street. New
sod is required where grass is dead.
6. Roof drainage could connect directly to the storm sewers.
7. Refer to bill Flushing's memo of January 27, 1989.
=p::=. cf?~
Tom Clark
TAC/ck
attachment
MEMORANDUM
TO
Carmen Annunziato
Planning Director
DATI!
February 3, 1989
I'lL I!
F"OM
Kevin J. Hallahan
Forester/Horticulturist
SUaJI:CT
Zicaro's Plumbing
Site Plan
The following comments pertain to the landscape plan for the
above project:
1. Thirty percent (30%) of all hedge materials must be
native species.
2. The irrigation system should provide water to the road
R.O.W.
y~~ ~.~~
-Kevin J. allahan .
Forester/Horticulturist
KJH:ad
MEMORANDUM
February 3, 1989
TO: CHAIRMAN AND MEMBERS
PLANNING AND ZONING BOARD
FROM: CARMEN S. ANNUNZIATO, PLANNING DIRECTOR
RE: ZICARO'S PLUMBING
SITE PLAN-STAFF COMMENTS
Please be advised of the Planning Department's comments with
respect to the above-referenced request for site plan approval.
1. The on-site retention comment from the January 5, 1989
Planning Department memorandum was not addressed. The
swale section provided does not indicate the depth of
the swale; nor does the drainage plan show spot
elevations at the bottom of the swale along the
eastern and northern property lines. Provide a cross
section of the perimeter landscape strip showing the
deepening of this area to provide additional on-site
retention.
2. Indicate proposed colors on elevations.
3. Indicate setback and provide details of freestanding
sign including colors, lettering style, wording,
materials, height, and colored elevations prior to
the Community Appearance Board deadline February 8,
1989 at 5:00 p.m. If this can not be met, a future
site plan approval will be required.
(2~~ ,/~
CARMEN S. ANNUNZIAT
CSA:ro
cc Central File
M E M 0 RAN DUM
TO: Carmen Annunziato, Planning Director
FROM: Don Jaeger, Site Development - Building DepartmE:nt
DATE: February 3, 1989
RE: SITE PLAN APPROVAL - ZICARO'S PLUMBING
As a condition of site plan approval, the following comments
should be incorporated into the related documents by the
applicant:
1. Curbing is required around landscaped areas adjacent to
parking stalls.
2. South Florida Water Management Distr~ct approval is re-
quired.
3. Details of signage must be submitted for Community
Appearance Board and City Commission approval.
4. Details on handicap accessibility to the building must be
provided.
5. The site plan shows trees, hedges and light poles proposed
in utility easements. Approval from the applicable utilities
must be secured prior 'to permitting.
The applicant's prompt compliance with the preceding comments
will insure a timely permitting process.
DJ:eaf
cc:E.E.Howell
MEMORANDUM
TO
DATil
Mr. James Golden
30 December 1988
,.11..1:
F"OM
5UB.JI:CT
Lt. Dale S. Hammack
';Z.ic aro
As per our discussion at the Technical Review Board on 29 December 1988, I
am recommending the following:
1 . l~ighting details.
2. stop bar and pavement markings.
3. Comply with city's Construction Security Ordinance.
~Q~~
DSH/cgrn
TRB MEMORANDUM
n~cflmber JO. liRR
To:
Jim Golden
From:
Bill Flushing
Re:
Zicaro's plumbing
1.
The lighting fixtures are to be pole mounted at
property line, (building mounted fixtures are
acceptable) .
the
not
2. A lighting level array in candle power shall be provided
or a statement by a registered engineer as to what the
average minimum light level is.
3. The lights shall be photo-cell controlled.
4. The handicap parking stall striping shall be blue.
5. The normal parking stall striping on concrete shall be
black.
6. A stop sign detail is required.
7. A wheel stop detail is required.
8. A stop bar and directional arrows are required.
9. A letter is required explaining why the first hour of a
three year storm (2.5 in.) is not retained on site as is
required by Boynton Beach Code.
/~/ '\
... .f ~ .
1:?11 t . -1-..__
Bill UShini
cc: 'I'om Clark
MEMORANDUM
Date:
Carmen Annunziato, Planning Director~ \
John A. Guldcy, Dlcectoc of Utllltles-1~
December 30, 1988 ~
To:
From:
Subject:
TRB Review - Zicaro's Plumbing - Site Plan
We request that a reduced pressure backflow preventer be specified
for the domestic water service to this building. instead of a double
check valve. The backflow preventer may be a Watts 909, Febco 825Y
or pre-approved equal.