AGENDA DOCUMENTS
1994 REVIEW SCHEDULE
FIRST HALF
SITE PLAN REVIEW AND
CONDITIONAL USE APPROVAL
*PROJECTS LOCATED WITHIN THE CBNTRAL BUSINESS DISTRICT
ORIGINAL AMBNDED CITY *COMM REDEV
SUBMITTAL PLANS *C.R.A.B. P&D COMMISSION AGENCY
DEADLINB DEADLINE MEETING MEETING MEETING & MEETING
Nov 19, '93 Jan 12 Feb 07 Feb 08 Feb 15
Dee 30, '93 Feb 04 Mar 07 Mar 08 Mar 15
Jan 31 Mar 14 Apr 11 Apr 12 Apr 19
Mar 01 Apr 11 May 09 May 10 May 17
Apr 04 (May 13~ Jun 13 ~ ~
Apr 29 Jun 10 Jul 11 Jul 12 Jul 19
NOTE: (1) TO FACILITATE THE PROCESSING OF THE REQUEST, IT IS RECOMMENDED
THAT THE APPLICANT SET-UP, BY APPOINTMENT, A PRE-APPLICATION MEETING
WITH THE DIRECTOR OF THE PLANNING & ZONING DEPARTMENT (407) 375-6260
PRIOR TO THE SUBMITTAL DEADLINE DATE. THE MEETING WILL ADDRESS CONCERNS
REGARDING THE TYPB OF SUBMITTAL, BOARD REVIEW SCHEDULE, SUBMITTAL
PROCEDURES, FEE, APPLICATION FORM, AND TYPE AND NUMBER OF
PLANS/DOCUMENTS THAT ARB REQUIRED TO BE SUBMITTED.
(2) IF A SUBMITTAL IS RECEIVED BY THE ORIGINAL SUBMITTAL DEADLINE
DATE AND WITHIN TWO (2) WORKING DAYS FOLLOWING THE ORIGINAL SUBMITTAL
DEADLINE, THE SUBMITTAL IS DETERMINED ACCEPTABLE FOR PROCESSING, THE
SUBMITTAL WILL FOLLOW THB APPROVAL SCHEDULE IDENTIFIED ABOVE. HOWEVER,
IT SHALL BE NOTED THAT THE AMENDED PLANS DEADLINE DATE ALLOCATES ONLY
TEN (10) WORKING DAYS FOR THE APPLICANT TO SUBMIT A COMPLETE PACKAGE
THAT INCLUDES THE PLANS THAT HAVE BEEN AMENDED TO COMPLY WITH THE TRC
COMMENTS GBNERATED FROM THE REVIEW OF THE ORIGINAL SUBMITTAL DOCUMENTS.
TO KEEP THB REVIEW PROCESS ON SCHEDULE THE AMENDED PLANS DEADLINE DATE
IS STRICTLY ENFORCED. IT SHALL ALSO BE NOTED, THAT PRIOR TO A PROJECT
BEING RECOMMENDED FOR APPROVAL BY THE PLANNING & ZONING DEPARTMENT, AND
BEING PRESENTED TO THE PLANNING & DEVELOPMENT BOARD OR THE COMMUNITY
REDEVELOPMENT ADVISORY BOARD, THE PROJECT SHALL BE RECOMMENDED FOR
APPROVAL BY THE TECHNICAL REVIEW COMMITTEE.
(3) APPLICATIONS WHICH REQUIRE SUBMITTAL OF A TRAFFIC IMPACT
ANALYSIS, PURSUANT TO THE MUNICIPAL IMPLEMENTATION ORDINANCE OF PALM
BEACH COUNTY TRAFFIC PERFORMANCE STANDARDS ORDINANCE REQUIRE ADDITIONAL
REVIEW TIME. NOTE: RBFER QUESTIONS REGARDING TRAFFIC TO THE DIRECTOR
OF THE PLANNING & ZONING DEPARTMENT.
(4) THE ABOVE DATES MAY BE SUBJECT TO CHANGE.