March 17, 1988
TO: PETER L. CHENEY, CITY MANAGER
FROM: CARMEN S. ANNUNZIATO, PLANNING DIRECTOR
RE: CITRUS GLEN-MASTER PLAN MODIFICATION (RESUBMISSION)
Delfin F. Menendez, agent for Allen Miller and Felix Granados,
Sr., contract purchasers, has requested a modification to the
previously approved master plan for the Citrus Glen PUD. This
request represents a resubmission of a request which was
withdrawn prior to consideration by the City Commission in
February, 1988, as outlined in the attached correspondence.
The procedure for approving master plan modifications in planned
unit developments is twofold. First, the City Commission must
make a determination as to whether or not the changes requested
are substantial in nature. A determination of substantial change
on the part of the City Commission, which has sole discretion in
this matter, would require a new application for PUD. On the
other hand, a determination of no substantial change allows the
forwarding of the request to the Planning and zoning Board. The
Planning and Zoning Board then may approve the request. This
procedure appears in Appendix B, Section 12 of the Code of
Ordinances.
With respect to the change requested by Mr. Menendez, the
Technical Review Board (TRB) met on Thursday, March 17, 1988, to
review the plans submitted, and they offer for your
consideration, a recommendation that the City Commission make a
finding of no substantial change for the requested modification,
and that the Planning and Zoning Board approve this request
subject to the attached comments from the Utilities Department
and the Forester/Horticulturist.
Co.-- 0"1 ~
CARMEN S. ANNUNZIAT~
CSA:ro
Attachments
('\ '\""1
.J . I
\..... ,
....- .---
STAFF COMMENTS
CITRUS GLEN-MASTER PLAN MODIFICATION (RESUBMISSION)
, ,
,
1
.
Utiliites Department
See attached memo
Forester/Horticulturist
See attached memo
. .
~
MEMORANDUM
To:
Carmen Annunziato, Planning
From:
John A. Guidry, Director of
Directo~~
Ut1l1t1ey
Date:
January 26, 1988
Subject: Citrus Glen - Master Plan Revision
We can approve the above-referenced Master Plan. subject to the
following conditions:
1. The 6" water main connection to Lawrence Road must be
in a 20' common area.
2. All utilities must be in dedicated easements that are wide
enough to allow servicing. Water mains may be no closer
than 10' to any structure.
3. The sanitary service to the proposed water storage facility
is to be centered in a minimum 15' wide easement.
dmt
Forester/Horticulturist
Subject to approval of a
detailed tree management
plan which addresses
littoral zones, uplands,
tree management, master
landscaping, etc.