CORRESPONDENCE M E M 0 RAN DUM April 3, 1985 TO: Mr. Carmen Annunziato, City Planner FROM: Tom Clark, City Engineer Re: Chalet IV at Boynton Comments: 1. The site plan although supported with engineering plans for other improvements does not include work- ing drawings for street lights. Complete working drawings are required for the street lights, i.e., luminairs, foot candles, supporting structure (posts, etc.), requirements for conductors, etc. etc., just as for the other improvements. A note concerning street light design by FP&L for dedicated rights of way should be shown for the loop road. 2. The "Site Plan" should show the division line between Plat No. 1 and Plat No.2. 3. The construction for the future Community Recreation Facility with access road and utilities should be completed prior to completion of the units in the first plat. The performance bond should include the cost for recreation facilities and appurtenances (and the design of same if not designed and approved prior to submission of the final plat No. 1 for approval) . 4. Miner road from Congress Avenue to the loop road should be included in the construction for Plat No.1. 5. The loop road in my opinion should be planned as a public right of way based on its function as a col- lector roadway. 6. Subgrade for roadways must be stabilized to a F.B.V. of 50 p.s.i. Ytp d~ Tom Clark TAC:mb _.... /, . C~TY of BOYNTON BEACH , ~fJ (J 1/"/. \JljJ ~ ~ ~ 120 N.E. 2nd AVENUE P.O. BOX 310 BOYNTON BEACH, FLORIDA 33435-0310 (305) 734-.8111 Apri l 18th, 1985 OFFICE OF THE CITY ENGINEER Ms. Nancy Metzger Wantman & Associates 2328 South Congress Avenue West Palm Beach, Flori MET IV OF BOYNTO Preliminary Plat 1 ~ Dear Ms. er' Reference is made to our recent conversation concerning additional materials to be submitted and changes required for the subject plats. Some of the items and comments are listed herein below: 1. A letter in regard to a separate excavation and fill permit is requested with appropriate plans for accomplishing the work, and with a breakdown of costs related to restoration to protect the public after the work is completed and/or abandoned. Said letter is requested since it is my understanding that an excavation and fi U permit is desired prior to platting. 2. A cost estimate for all of the required improvements is required. Line items should be listed with quantities, unit costs, and total amounts. The cost estimate should include the costs for Miner Road extended on the property fron- tage. Costs for the private recreational facilities should be included also. Street lights in the public right-of-way are required to be included in the cost estimate. 3. Drainage calculation should be submitted. 4. Definitive drawings for Miner Road extended should be submitted. If construction is not planned to start with the other improvements, a schedule is requested. 5. The plans for the private recreational facilities should show the size, location, and other information necessary for review by the Technical Review Board and the Planning and Zoning Board. The access road required to serve the recreational facilities should be included with the plans, along with the utilities and drainage facilities. \ ;/y) ...., )"1 J. v L ~ I ~i \'~ i ,"-- J ~ / - .. ~ .. April 18th, 1985 Page II 6. Information to identify the value of the property is required so that the Planning and Zoning Board can determine the recreation fee required. A recent sales contract or an appraisal may be acceptable. 7. If Plats I and II are to be recorded as two plats, an additional filing fee of $50.00 is required. 8. Sub-grades for roadWays and shoulders are to be stabilized to 50 p.s.i. F.B. V. 9. Dimensions should be shown for the cul-de-sac. 10. Notes concerning street light construction on private streets should be added or details included with the plans. 11. A concrete bicycle path eight feet wide is required on the collector street. 12. Utility easements for municipal sewers, water lines and ingress/egress should be more clearly documented on the plat. 13. Notes on the plat referencing Palm Beach County should be changed to Boynton Beach. 14. The Mayor's name is Nick Cassandra. 15. The surveyor's certificate should delete any reference to Palm Beach County, Board of County Commissioners. 16. All utility easements and drainage easements required should be shown. 17. Lake Worth Drainage District L-20 should be indicated on the plat, and the identity of the property to the north. 18. The collector or loop road and Miner Road extended, should be dedicated to the public, along with drainage facilities within the right-of-way. 19. Applications for water and sewer plan approval should be sent to the Department of Environmental Regulations (requiring approval by the Utility Director). 20. Applications with all required materials should be sent to the Water Management Dis trict. The above materials should be submitted as soon as possible so they can be reviewed by the Technical Review Board on May 7th, 1985, and placed on the Planning & Zoning Board Agenda for May 14th, 1985. ~....., . . sour. r'orida Water Management District Post OHice Box V 3301 Gun Club Road C . D West Palm Beach, Florida 33402 ~ 1>..;,"~-:';~"/ q Telephone (305) 686.8800 ~r........,c~ ~ " Florida WATS Line 1-800-432-2045 ;:Cll"~ ,;"':;1); 'hi: "'~.. \' ,,>',..J,~d IN REPLY REFER TO: JOhn R Wodraska. Executive Director Apri 1 19, f{; tN \"'-' I' I C~lf.// 1985 Q-;:-Y, \i 'J'Jl ~ fl ~ jJ~ I/~# /'~fJ, ~~ API=! '., .'1 lC,./'lv."e;::, ," " PLANi~ii'.G DtJ'l. Mrs. Nancy Metzger Wantman and Associates, Inc. 2328 South Congress West Palm Beach, FL 33406 RE: Application #03205-B, Melear PUD (Chalet Corporation). Boynton Beach, Palm Beach County, S18/T45S/R43E Dear Mrs. Metzger: The staff has completed a preliminary review of the above. According to Rule 40E-4 Florida Administrative Code (FAC), the circled items on the attached checklist must be provided before our review can continue. Also, please see attached comments. f In accordance with 40E-l.603(5) FAC, if the fnformation is not received within 90 days of this date, the application may be processed for denial, if not withdrawn by the applicant. Please submit FOUR copies of the information. Should you have any questions, please call. Sincerely, EJM:m ~chment cc: Boynton Reach City Engineer DER Mr.N.Reed Mr.J. Flanigan Lake Worth Drainage District .(~~ p. 4~~ Edward J. Maciejko Water Management Engineer Resource Control Department .; Stanley W. Hole Chairman - Naples William E_ Sadov.,II:1 Viea Chairman Miami J Ned Gallagher St. Cloud Nalhanl~1 P Reed Hobo'! S0;,;....'d Kathleen She,] AbramS Miami Shor.~s JOhn F Flanigan NorH'. P8.lm Be,1ch Timer E. Powers Indian town Kenl Price Okeechobee . , APPENDIX 1 CHECKLIST FOR SURFACE WATER MANAGEMENT PERMIT APPLICATIOl12 I. Site Infonnation including: A. G) C9 @ C9 o Detailed location sketch. Topographic map of the site and ad acent h drolo icall related areas, which shall inc1u~ location and description of bench marks mininurI of one per ...jor water control structure). Overall map of the area showing where runoff presently goes and size, location, topography, and land use of off-site areas which drain through,on t~,and from the project. Identification of seasonal water table elevations. If the project is in the kn",n flood.way of a natural stream, It should be identified and approximate flooding depths determined. The 100 year flood plain elevations and limits should be identified if applicable. E. Description of vegetative cover. Wetland areas should be identified. F. A recent aerial photograph of the project area with project boundaries delineated. Paving, grad~g and drainage plans, ~ith special attention to peri~ter site grading. H. Percolation tests must systems are proposed. deSign conditions. be submitted if percolation or exfiltration Percolation tests shall be representative of Complete description of measures to be implornented during the construction perfod to mitigate adverse Quantity and quality impacts off-site. II. Master Drainage Plan Showing: A. Location of all water bodies with details of size, side slopes, elevations and depths. ~ location and details of all major water control structures. Control elevations of the control structures must be included along with any seasonal water level regulation schedules. (9 G) Drainage basin boundaries showing direction of flow, tatino into account off-site runoff being routed throuoh or around the project. Locations of roods and buildings alon9 with their ~r6~6se6 elevations. .. IIE:\ Right-af-way dnd easement locJtions for the drainAge system including L/ d 11 areas to ~ reserved for water managewnt purvoses. F. Location and size of internal minor wat.- monagement facilities. ~ Nearby existing offsite water management facilities such as wells, lakes, etc. which might be affected by the proposed construction or development. The names and addresses of the owners of such facilities should also be submitted. Ill. Drainage Calculations including: (!) Design storms used including depth, duration and distribution. ~ Off-site inflows. o Stage-storage computations for the project alll stage-discharge computations for the outfall structure(s). (i) Acreages and percentage of prooerty proposed as: 1. ImperviOUS surfaces (excluding water bodies) 2. Pervious surfaces (green areas) 3. Lakes. canals, retention areas etc. 0) 4. Total acreage of project Run6ff routing calculations showing discharges. elevations. and vo1u""s retained and/or detained during applicable sto,," events. Included should be the necessary mathematical computations to demonstrate that the ~ro~osed development will not remove net storage from the asin for events up to the 100 year frequency. Calculations required for dete,,"ination of minimum building floor and road elevations. F. IV. Legal and Institutional Information including: Identify entity responsible for operation and maintenance of the surface water management system. (9 (0 If the operation and maintenance entity is to be a public body such as a city or drainage district, a letter of potential acceptance fcrom the pUblic body must be submitted prior to staff report approval. [f the entity is a homeowners association, then documents verifying the existence of such an or,Jnization ond its ability to accept o eration and m4intenance res onslbility must be submitted prlor to ~ COltlTl!ncement of construction assumlng P!1nn S lssue (() Indicate how water and wastewater service will be supplied. Letters ~' of commitment from off-site suppliers must be included. CD ~ Identify, ~gencies. organizations, etc. contact~d. [Dclude meeting sUlllMries d/ 'esponses. Give status of l( < 'Ovals indicating if site plan anu/or subdivision approval has b~~n g.anted, final plats recorded and building or construct In permits issued. Present and proposed zoning: Evidence of compatible density and classi- fication under the Local Government Zoning Or Comprehensive Plan must be submitted; include tlie status under the DR! process, if applicable. The number of proposed dwelling unlts and/or square feet of coomercial area must be supplied. If the project is a DR!. then a copy of the final approved development order must be supplied. .. .... CD Submit a copy of a boundary survey and a copy of the recorded warranty deed, if the Applicant is a contractual buyer then a copy of the executed contract. must be provided. @ Documentation of legal and physical availability of receiving water system to receive project discharge if such is not evident. NOTES: 1. Include four copies of all information. and one completed copy of Application Form RC-l. 2. For a Conceptual Approval. Items !.G. I.!.. II.E. and II.F.will not be necessary. COM MEN T S 1. Please clarify if either surface or ground water withdrawals are proposed for irrigation or other on-site water use. Prior to any withdrawals the project will require a Water Use Permit (enclosures), which will be included as a special conditi on of the Surface Water Management Permi t. 2. Best Management Practices ~ould be to place all 'catch basins in grassed swales. 3. Please differentiate the amount of stormwater runoff that is detained in the lake from the amount of runoff detained in the swale system. .i ,r ~ "i \ \ J MEMORANDUM 7 May 1985 TO: Tom Clark, City Engineer FROM: Carmen S. Annunziato, Planning Director RE: Chalet IV Plat I and Chalet IV Plat II preliminary Plats Approval of these two preliminary plats is recommended subject to the following: 1. All of Miner Road is to be bonded and dedicated in connection with the approval of Plat I. 2. For those portions of Miner Road outside of the limits of Plats I and II, the right-of-way should be dedicated by separate instrument within 120 days of preliminary plat approval. 3. That part of the 80' collector road lying west of the part which appears on Plat I should be dedicated to the public by instrument through the limits of the recreation are a prior to filing a final plat. 4. The recreation area shown on the master plan for the Melear PUD lying north of the collector road should be dedicated by easement to the homeowners prior to filing for final plat approval. 5. The location of off-site utilities will require the dedication of easements by instrument which should be recorded prior to filing the final plat for 0 Plat I. 6. Miner Road must be constructed through the limits of the public land located at Congress Avenue and Miner Road in a timely manner. The reason for this is that the recently approved bond issues provide for the construction of a multi-purpose public building to be located on-site, thus, Miner Road must be in place to serve this improvement at the time of occupancy. 7. The collector road should be dedicated to the public in order to provide for enhanced municipal circulation consistent with current City policy. 8. It is recommended that the Planning and Zoning Board set $31,815/acre as the land value for Recreation and Parks dedication purposes based on the contract for purchase submitted by the applicant. /bks lJtP1<- S. armen S. Annu ,:A~~ iato t1 ~~ ...-.' WANT-AN. AS.OCIATES, I"C. CONSULTING ENGINEERS Nay 7, 1985 City of Boynton Beach 120 North 2nd. Ave. Boynton Beach, Florida 33435 Att: Carmen Anunziado Dear Ms. Anunziado: Please find enclosed meom regarding Boynton Beach meeting on Friday, May 3rd. Thank you. Sincerely, Helody Putman enc c.c. file 2328 South Congren Avenue. West Palm Beach, Florida 33406. (305) 967-1100 1025 Martin Downs Boulevard. Palm City, Flqrlda 33490. (305) 286-6338 5151 Adanlon Str..t . Orlando. Florida 32804 (305) 844-2229 WANTMAN at ASSOCIATES, INC. CONSULTING ENGINEERS MEMO TO: FROM: DATE: CHALET IV OF BOYNTON FILE JOEL WANTMAN MAY 6,1985 RE: Boynton Beach Meeting of Friday, May 3rd with Tom Clark, Carmen Anunziado, Nancy Metzger & Joel Wantman 1. Cost estimate to be divided by Plats for the first two Plats. 2. Cost estimate for Miner Road to be extended west to the Loop Road and filed with Piat 1 - Construction to be completed within 21 months. However, City may want the East 650 +/- feet to be completed within approximately 12 months. 3. Cost estimate for Miner Road from the west Loop Road to the west property line should also be completed and filed with Plat 1 - Construction to be completed within 21 months. 4. We need a legal description of the Rec area. This is to be dedicated to the Homeowners Association and should be recorded prior to platting. That portion of Loop Road not included in Plat 1 up to the recreation area should also be dedicated by instrument to the Homeowners Association and recorded prior to platting. 5. Recreation fees calculated as follows: Project Cost Cost/At. Plat I Pl a t I I = 333 units x $6,OOO/Ac. = $ 1,998,000 = $1,998,000/62.8 Ac. = $31,815/Ac. = 80 Units x 0.015/2 x $31,815 = $19,089 = 64 Units x 0.015/2 x $31,815 = $15,2711 6. Meeting Schedule - TRB May 7th 9:00a.m., P & Z May 14th, 7:30 p.m., Council prel iminary Plat approval May 21st 7:30 p.m. 7. After preliminary Plat we need to go back to council after final sign offs from the TRB, sign offs will be obtained by Tom Clark. 8. Fees for Platting: 1 l Administration fee 1% of the construction cost. 2l Recreation. 3l All bonds (from AM Bond Company or Bank l 2328 South Congress Avenue. West Palm Beach, Florida 33406. (305) 967-1100 1025 Martin Downs Boulevard. Palm City, Florida 33490. (305) 286-6338 5151 Adanson Street. Orlando, Florida 32804 (305) 644-2229 . , , . \ MEMO TO: MAY 6, 1985 PAGE TWO CHALET IV OF 80YNTON FILE 9. Prepare a letter for the excavation permit saying that all sand will be kept wet and sand fences are to be constructed along Congress Avenue. 10. Preliminary Plat approval only good for 6 months. After that you must get extension or resubmit for Plat approval again. This will affect Plat Number 2. 11. Loop Road - City wants road public - client wants road private - needs to go to Council for final decision. 12. Water System - minimum 10' from all buildings including patios - Complete Loop North of Plat 1 with Plat 1. 13. Need all off site easements including water main. M E M 0 ~ AND U M May 8, 1985 TO: Mr. Carmen S. Annunziato, Director of Planning FROM: Tom Clark, City Engineer Re: Plat I and Plat II, Preliminary Plat, Chalet IV Forwarded herewith are two sets of development plans and six copies of the plats for the subject project including the set with the T.R.B. review stamp. Also forwarded is a copy of the cost estimate for the recreation facilities. Comments are as follows: 1. Cost estimates should be submitted for the following: (a) Plat I and Plat II water, sewer and street improve- ments including the "loop" road and street lights on the "loop" road. (b) A breakdown of the costs for Miner Road split as per planned ownership for posting of bonds. 2. The dedication should be changed to provide for the loop to be a public right of way. 3. The loop road will have to be extended to the recreation area with the first plat improvements. 4. The recreation area will have to be granted by deed to the Homeowner's Association for approval of the first plat. 5. Roadway construction to have stabilized subgrade equal to 50 p.s.i., Florida Bearing Value. 6. Other comments as per Carmen Annunziato's memo of May 7, 1985. v~~L Tom Clark . TAC:mb Attach. (i 120 N.E. 2nd AVENUE P.O. BOX 310 BOYNTON 6EACH. FLORIDA 33435-0310 (305)7~111 CITY of BOYNTON BEACH OFFICE O~ THE PLANNING DIRECTOR 5 June 1985 Mr. Joel Wantman Wantman & Associates 2328 South Congress Avenue West Palm Beach, FL 33406 RE: Chalet IV preliminary Plats 1 and 2 Dear Mr. Wantman: Please be advised that the referenced plats were approved by the City Council on Tuesday, May 21, 1985, subject to compliance with the comments from the Planning Department and City Engineer. Copies of these comments are attached. If you have any questions concerning this matter, please do not hesitate to contact me. Yours very truly, CITY OF BOYNTON BEACH ;/I@v7~d(:2~ ~::'men S. Annunziato (/ Planning Director /bks Attachments cc: City Manager Technical Review Board Central File SOli th Florida Water Management Post Office Box V 3301 Gun Club Road West Palm Beach, Florida 33402 T eJephone 1305) 686.8800 Florida WATS Une 1.800.432.2045 June 17, 1985 o i s t r i c t" R WQ:~"~:v'~"Ili," O"eC(N /1// . ~ YJ./( ..' // ,.,\V C I \\ C/ ...~~~,'~ (Y Vfii I,OJ IN REPLY REFER TO: Mr. Laurent VanCott Wantman & Associates, Inc. 2328 South Congress Avenue, West Palm Beach, FL 33406 RE: Application #03205-B, Melear PUD (Chalet Corpora J Boynton Beach, Palm Beach County, SI8/T45S/R43E Dear Mr. VanCott: We have received information from your firm on May 1, 1985. The information received was incomplete and did not adequately address the following items. Review of this project cannot be completed without this information. 1. Off-site discharge is limited to 52.5 CSM, which equates to 15.1 cfs for this I54.6-acre project. Please revise the control structures accordingly. Allowable discharge has been alloted for the 154.5-acre basin as per the submitted survey. As such, drainage shall be provided for the I54.6-acre basin. Should the 3.0-acre parcel, in the northeast corner (or others), of this project not be included in this drainage plan, then the allowable discharge and site calculations must be revised. 2. Construction of the surface water management system in this phase must include a positive stormwater outfall. Indicate the location of the discharge structure on the drainage plans. Discharge,structures shall include a "baffle" system. . 3. Submit a copy of the recorded warranty deed for the project. 4. Documentation of legal and physical availability of receiving water system to receive project discharge must be submitted. 5. Please show sufficient elevations on the plans 'to justify site storage beginning at an elevation of 11.0' NGVD. Construction plans submitted indicate an elevation of 10.88' NGVD in a few of the inlets of the roadside swales. This does not appear to be typical for the project site. Storage calculations for the roadside swales should be calculated in addition to the typical site storage calculations. 5. The project site must have the storage capacity for the 25-year, 3-day design storm on site, with discharges made only through the structural discharge facilities. Perimeter site grades will be pertinent to the boundary of this drainage basin. Stanley WHole Chairman - Nil pies William E SadowSKI /1( e- en,llrrne/I" MiamI J Neil Gallagher 51 CloL..d Nfllnarllel P Re"d Hobt'l S0und l(athlC'l;'r' '{"'<l :'bul'T1s M'l"" Sr, J'lf1n ~ F-I'U11',J.J" l\J(Jrtl"' r' lIt', ded'" rimer E, Pcv.ers !"d,;)n/own Kent Price Okce:h0bee Nancy H Roen Piant3\;0n . , RE: Application #03205-8, Melear PUD (Chalet Corporation), Phase 1 Boynton 8each, Palm Beach County, SI8/T45S/R43E 7. A storm event of I-day duration. 5-year return frequency, and rainfall amount of 8.2" shall be used in computing road and parking lot elevations. A storm event of I-day duration, 100-year return frequency, and rainfall amount of 17.6" modified by 135.9% to obtain the 72-hour depth shall be used in computing finish floor elevations. Revise calculations as necessary. 8. Please revise the submitted property owners association documents as per comments for the conceptual permit application (#03115-B). 9. Where will the drainage for Miner Road (proposed) go? If the drainage for adjacent Miner Road will go through this system, the offsite'inflows must be accounted for in the calculations. 10. Drainage basin boundaries must take into account off-site runoff routed through or around the project. Provisions shall be made so that the project will not block or cut-off another project's historic discharge path. 11. Provide right-of-way and easement locations for the drainage system including all areas reserved for water management purposes. The preliminary plat submitted is for 8.99 acres while the permit application is for construction of 30.93 acres. Please indicate clearly the water management area (lake) to be constructed in this phase. 12. What is the status of the water storage tank shown on the master drainage plan? Is this proposed to be constructed, and for what purpose? Please submit FOUR copies of the requested information. Should you have any questions, please call this office. Sincerely, &~'OL~ J!. .4(~ Edward J. Maciejko Water Management Engineer Resource Control Department EJM/ejm cc: DER Mr. J. Flanigan Boynton Beach City Engineer Lake Worth Drainage District Mrs. Nancy Metzger Wantman and Associates, Inc. 2328 South Congress, Suite 2-C West Palm Beach, FL 33406 SOL -'h~lorida Water Management Ois rict Post Office Box V 3301 Gun Club Road a..L (J ,r West Palm Beach, Florida 33402 , I I'" r Telephone (305) 686-8800 t,\ V/ '1," ~ / Florida WA TS Line 1-800-432-2045 /' y _&f jJ 91 (\)/ ;flJrw, \U, ~~ .1/ (J^~ / \< /, John R Wad raska, Executive Director Tilford C. Creel, Deputy Executive ire tor i) IN REPLY REFER TO: August 9, 1985 RE: Application #03115-B, Melear P.U.D. (Chalet Corporation) Palm Beach County, SI8/T45S/R43E Dear Mrs. Metzger: The staff has completed a preliminary review of the above referenced application. The project appears potentially permittable. Should you have any questions, please call Edward Maciejko of this office. Sincerely, ~?~ Charles W. Pemble, P.E.,Director Water Management Division Resource Control Department CWP/ejm cc: DER Mr. J. Flanigan Mr. N. Reed Boynton Beach City Engineer Lake Worth Drainage District Stanley WHole Chairman - Naples William E Sadowski Vice Chairmdrl . Mldmi J. Neil Gallagher 51. Cloud Nathaniel P Reed Hobe Sr-' ,. Kathleen Shp , , , 11"1' F Flanigan .'JI:l' ":l!rn Beach Timer r Infi '5 Nancy H. Roen Plantation Mial1~; ';., '.'s .,.. l' .." City of Boynton Beach Page 2 August 28, 1985 3. Loop Road Plan - Sheet 4 of 8 A. 07-25-85 - Revised Loop Road to show 16-foot median strip in accordance with site plan as approved by the City of Boynton Beach. B. 08-08-85 - Revised Loop Road curb transition note and flared end section. C. 08-23-85 - Revised entrance location off Loop Road for Phase II (west of the lake). Made necessary drainage changes to conform with new entrance as per Burg and Divosta. 4. pavinq and Drainaqe Details - Sheet 6 of 8 A. 08-08-B5 - Revised section A-A (parking lot detail) to include parking bumpers. Revised cul-de-sac detail as per Burg and Divosta. 5. Pavinq and Drainaqe Details - Sheet 7 of 8 A. 07-23-85 - Revised Loop Road section to show 16-foot median strip in accordance with site plan as approved by the City of Boynton Beach. B. 08-09-85 - Revised perimeter site grading detail, section G-G, as per Burg and Divosta. C. 08-15-85 - Revised outfall pipe size for control structure and added Canal No. 20 ultimate design section in accordance with Lake Worth Drainage District. D. 08-28-85 - Revised typical lake section as per Burg and Divosta. 6. Area Drainaqe Map - Sheet 8 of 8 A. 06-26-85 - Revised maintained water elevation in accordance with South Florida Water Management District. Please review all the aforementioned revisions and distribute the plans to any involved TRB members for their review and comment. We will be submitting a package for final plat approval of Plat one very shortly and would like to insure a smooth final review and approval. ~ c." .......... City of Boynton Beach Page 3 August 28, 1985 If you have any questions or concerns, please contact me at 967-1100. Sincerely, Na:~~g::e~ Project Engineer cc: J. Armanik Chuck Hathaway Files c RECEIVED HEMORANDUM SEP 3 1985 PLANNIJ~G DEPT. - ~ TO: TECHNICAL REVIEW BOARD Perry Cessna, Utilities Director Rick Walke, Public Works Director Charles Frederick, Recreation & Park Director James Rhoden, Fire Chief Bud Howell, Building Official Carmen Annunziato, Planning Director Dale Hammack, Police Department Kevin Hallahan, Forester/Horticulturist Craig Grabeel, Energy Coordinator FROM: Tom Clark, City Engineer Re: Plats 1 & II, Chalet IV, Preliminary Plat Changes A copy of a letter from Nancy Metzger is forwarded herewith, and is self-explanatory. Please note that most of the changes concern construction details and changes required by the Water Management District. A 16 foot median strip is now provided to agree with the site plan approved by the city. A set of construction plans which include the changes as per said letter are available for pick-up and/or review in my office. v~ aJ Tom Clark ~ TAC:ck Attach. WANTMAN & ASSOCIATES, INC. CONSULTING ENGINEERS ,./ 'i--.Vf? ~,r/,. I ~"j. , II' ,/1: J 1.1 ~7J.V Ii JJ )' !J:~11 tx;;y n Vt y !1;J'7 ( August 28, 1985 Mr. Tom Clark, City Engineer City of Boynton Beach 120 North 2nd Avenue Boynton Beach, FL 33435 :- Re: Chalet IV of Boynton/Melear P.J!..JX '(a;k:a.SandaTwood of Bo'ynton) Dear Mr. Clark: As per onr conversation of August 27th, I am sending you (1) one set of the most current paving and drainage plans for Chalet IV of Boynton. 'Plats one and two. Specifically, the plan revisions that have been made after the preliminary plat approval date of May 21, 1985 are as follows: 1. Horizontal Alignment Plan - Sheet 2 of 8 A. 06-26-85 - Revised to include outfall location for Plats one & two in accordance with South Florida Water Management District. B. 08-08-85 - Revised cul-de-sac configuration per Burg and Divosta. C. 08-15-85 - Revised 24-inch diameter outfall pipes to 30- inch diameter and added sand-cement endwall detail in accordance with Lake Worth Drainage District. 2. Pavinq and Drainage Plan - Sheet 3 of 8 A. 06-20-85 and 06-26-85 - Revised controlled water elevation to 9.00 feet N.G.V.D. and added outfall note in accordance with South Florida Water Management District. B. 07-23-85 - Revised Loop Road to show 16-foot median strip in accordance with site plan as approved by the City of Boynton Beach. C. 08-08-85 - Revised site grading by deleting parking lot grading and providing a typical parking lot grading detail. Revised cul-de-sac grading and drainage as per Burg and Divosta. 2328 South Congress Avenue. West Palm Beach, Florida 33406. (305) 967.1100 1025 Marlin Downs Boulevard. Palm City, Florida 33490. (305) 286-6338 5151 Adanson Street. Orlando, Florida 32804 (305) 644-2229 ! f ( , ,I' ~ ---r:; !u , / WANTMAN & ASSOCIATES, INC. CONSULTING ENGINEERS I-,Ii"i' ll.-j, ( , " r J/rJ -(<j' / '~')(- V' , /i (J~,r '> C (7% , September 3, 1985 Mr. Tom Clark, City Engineer City of Boynton Beach 120 North 2nd Avenue Boynton Beach, Florida 33435 RE: Chalet IV of Boynton/Melear, P.U.D. (a.k.a. Sandalwood of Boynton), final plat submittal package Dear Mr. Cl ark: Please accept this letter with the attached plans and exhibits as a formal request for final plat approval of Plat One of Chalet IV of Boynton. The administrative fee and recreation fee will be sent under separate cover. The required performance bonds (Plat One, and Miner Road) will be posted with the City shortly; and the offsite easements shall be executed and filed for recordation prior to fi nal approval. If you require anythin9 further, please let me know as soon as possible. Sincerely, mmcr Mei?fJff Nancy Metzger Project Engineer NM/ma cc: Jack Armanik Chuck Hathaway Fil e s 2328 South Congress Avenue. West Palm Beach, Florida 33406 . (305) 967-1100 1025 Martin Downs Boulevard. Palm City, Florida 33490. (305) 286~6338 5151 Adanson Street. Orlando. Florida 32804 (305) 644-2229 MEMORANDUM September 11, 1985 REr""""'''''''''''''D ~' .., '", ~'-,~", ~\ ~ 1,:.'- ._..i '"," .'. ,.~- ~ ,.....- TO: Mr. Peter Cheney City Manager JSUS FROM: Tom Clark City Engineer RE: Recommendation for final plat approval,l:halet IV, Plat No. 1 PLI'" ",,' .:J Ud" r Forwarded herewith is a print of the subject final plat with T.R.B. review stamp. The filing fee, the administration fee of $6,304.00, and the recreation fee of $18,972.00 have been received and forwarded to the Finance Department for deposit in the appropriate accounts. Also forwarded are copies of the performance bonds as listed below (the original bonds are forwarded with this memo to the Finance Department). -Aetna Performance Bond for Water, Sewer & Paving----- $290,820.15 -Aetna Performance Bond for Loop Road Paving & Drainage-----$193,335.40 -Aetna Performance Bond for Miner Road Paving & Drainage (East Part)-----$ 89,773.30 -Aetna Performance Bond for Miner Road Paving & Drainage (West Part)-----$ 54,125.35 Documents required but not received as of this date are the following. -Bond for the private recreational facilities in the amount of $136,000.00. -A signed agreement for the use of the off-site recrea- , tion area by Plat I occupants. -A signed easement for access and utilities to serve the recreation area. -A signed right-of-way deed for Miner Road to Palm Beach County. TO: City Manager September 11, 1985 RE: Chalet IV, Final Plat Approval Page 2 Approval of the subject final plat is recommended subject to receipt of the above listed documents not yet received. The original Mylar plat is in the custody of the City Clerk. A proposed resolution for approving the final plat is in- closed herewith. ~ / VtL- Tom Clark ...... ~! TAC:ck Attach. cc: Grady Swann w/original bonds James Vance w/copy of bonds Carmen Annunziato Perry Cessna Bud Howell ,,"- '",', "lJ T . /} ,f. , [\~\ 'ylre. ..... ~ ;...J/ WANTMAN . A.SOCIATES, INC. CONSULTING ENGINEERS '-- 4 October 23. 1985 '- Mr. Jack Armarn1k Chalet IV Corporatfon Post Offfce Box 5381 Lake Worth. Florfda 33466 RE: Chalet IV. Plat No.2. Boynton Beach Dear Mr. Armarnfk: In effort to accomodate the proposed constructfon schedule we strongly recommend that the final plat submittal for Plat No.2 be made as soon as possfble. The followfng ftems 101111 be requfred for submfttal to the City of Boynton Beach: 1) A bond for Plat No.2 in the amount of $54,125.35. 2) A ffl1ng fee in the amount of $150.00. 3) An adminfstrative fee in the amount of $,~'2.54. * (It of the bond amount) 4) A recreation fee in the amount of $15,171.60. * Based on 64 unfts at a $31,620 per acre cost (64 unfts X 0.015/2 X $31,620 a $15,111.60) Please submit the above ftems to this offfce and we will provide the plat documents, engfneering plans, and cost estimates which are also required for submittal. If you should have any questions, please contact me. Sincerely. Nam.el) J7')a~r Nancy ~t~g~;Jt1 Project Engineer NH/ma cc: files 2328 South cong..... Ave....e . We'l Palm eeach, Florida 33.406. (305) ee7~1100 1025 Martin Down. a_eward . Palm City, Florida 33490. (305) 286-6338 5~_5~. A~n.~--!!~~eet . Orlando, Florida 3~804 (305) 64-i~2228 ( -' , WANTMAN & ASSOCIATES, INC. CONSULTING ENGINEERS September 9, 1985 City of Boynton Beach Engineering 120 North 2nd Avenue Boynton Beach, Florida 33435 Attention: Mr. Tom Clarle RE: Chalet IV of Boynton/Melear P.U.D. (a.le.a. Sandalwood of Boynton) Dear Mr. Clarle: As per our September 9th telephone conversation, please accept the following letter with attached cost estimates for the clarification of the required administrative fee and recreation center fee. The recreation fee of $18,972 was calculated as follows: Project cost = 333 units x $6000/ac = $1,998,000 Cost/acre = $1.998,000/63.186 acres = $ Plat I = 80 units x 0.015/2 x 31,620 = $ 31,620/acre 18,972 The discrepancy noticed by Carmen Annunziato from the earlier amount of $19,089 was due to a difference in the acreage used for the cost per acre figure. The required administrative fee was calculated as follows: Plat I - $484,200 $ 89,800 Miner Road - (Chalet IV) Miner Road - (Melear) $ 56 , 400 $630,400 $630,400 x 0.01 = $6,304 2328 South Congre.. Avenue. We.t Palm Such, Florida 33406. (305) 9&7~1100 1025 Martin Down. Bouleverd. Palm Clly, Florida 33490 . (305) 286-6338 5151 Aden,on 51,..... Orlando. Florida 32804 (305) 644-2229 I STANLEY/WANTMAN & AS:,OCIATES. INC. L_~_J 7Of? T12? })J(';; '.':J ~ \ .-- r I ,I Lf/~/lf"'~ 't:'}~ ,1....-..r /- /, f, 1/ 0 ., _ ~ :! - cJ,~G-.j .& bcJ "-: 6;J2,u J 1~v1 \J~? "I') 0. $T I pJ:",:+-- L . ~"'i" r:~.... ~ ,,{UnPlH,. pJ,~ ~~~ ij ~ 0''- Jvv.... Ov,,"^I d' b j e (> J.;<h^~ i::t;) ~ /\{.0~-~~~ {r;vr( Rf(;\,~~1Il' /j} /) y~ff~ ~.,"..,~-..,-"~ n rr~'c-, , .trL~'~:\ ' I~OV 1QOf;; 1..~OI.. r-;Lf~j'-j; .: ._" i. November 6, 1986 Boynton Beach Engineering 120 North East 2nd Avenue Boynton Beach, Florida 33435 Attention: Tom Clark RE: ~a1et IV of Boynton Plat I, Performance Bond Reduction Loop Road and Congress Avenue Dear Mr. Clark: The required improvements for Plat I and Congress Avenue have been completed. Because of the amount of construction traffic entering the project, the developer has only had the first lift of asphalt installed on Loop Road. Enclosed is a Certified Engineer's Opinion of Cost of the work remaining to complete the required improvements. Please note that the required street lights have not been installed at this time. They are not included in the work remaining total because the developer has reimbursed the City of Boynton Beach for the installation of this lighting system. At this time the developer respectfully requests to reduce the remaining surety bond of $55,702.90 to $29,000.00. If you have any questions or require any additional information, please do not hesitate to call. Very truly yours, Thomas D. Alexander, P.E. Project Manager c.c. Jack Armarnik Bill Blazak ~ 1~1 1~ ~1,'l\ LOMBARD CENTER'. 2000 LOMBARD STREET . WEST PALM BEACH. FLORIDA 33407 . (305) 642-7444 ~ . MEMBER OF THE STANLEY CONSULTANTS GROUP INTERNATION,(L CONSULTANTS IN ENGINEERING, ARCHJTECTURE, PLANNING. AND MANAGEMENT Chalet IV Corporation Burg & DiVosta ...........,.._.-,--" FTir"""- ' ~ '!- '- ~ - """ ,.-- RE: PERFORMANCE BCNDS 'I!Cr, Ch" a let, ]lf7 I'll".."; -""" 'J14 /7 /<)' (~/ ...:_ .'.L . .. /...t'.-t--H...4'- / I '-' . COR P 0 RAT I I fr ;-I~K.:b, y}/o;;rJ?l'?, ,_ ,,1, F/l..fl')1 ~ - '"/.;1-/-'"'. ~::/' J-- /r-, bEl ','" - /' .('..., - d-r.:/ ,..~,..;~",........ ~.~'..., ,'0,",-" 'b 7l! ' ,;;" _ " . ... " '-'.T r'/,1. } "VI,? ye ,</~:)~''Y' L, -ft..(..,J:- [, rf. v r ( ,,- - ,)," - .;t ,.<f J~.~O-'.. ,,' < v-h ~j/6 "f.JJ ~ p.. ~ n ....... -fk. 1"n-y1'Y"...&o,....y ~r' ..(.u,'/d ''''i.--A-fP / \..1 N~ G II '8'/. . r ~<kYX ~u. J?'t~)~ ,q~,fjj? ~ /,/} {; V.... -t-f'#~ , ,.;' ! Decerrber 3, 1986 Mr. Tan Clark, City Engineer Boynton Beach Engineering 120 North East 2nd Avenue Boynton Beach, Florida 33435 Dear Nr. Clark: Ycu have received fran Stanley!Wanbran & Associates, Inc., the following certifi- cation of =rent construction status of Bonded Inq:>rovements: Reduction of Bonds Novenber Decenber Existing Bond 11 & 12 1 & 2 Reduced Bonds l. plat 1 $- 2,165.40 €l 2. plat 2 4,500.00 G 3. plat 3 341,200.00 $158,100.00 $ 72,000.00 (3)$ 72,000.00 4. plat 4 61,800.00 G 5. Restoration Bond 30,000.00 G 6. Recreation Area 136,000.00 60,050.00 26,750.00 (6) 26,750.00 7. Loop Road 53,537.50 29,000.00 - I (7) 29,000.00 8. Miner Road 1 89,773.30 (8) 89,773.30 9. Miner Road 2 54,125.35 (9) 54,125.35 We ~ld appreciate Items 1, 2, and 4 being cancelled, and Items 3, 6, and 7 reduced ac=rding1y. ~t'f~ ,,~( ~ /1.-L-.q/Jel>t ~ ~i1ln' We ~ ..h~t ,Ie have a~ii8" that the }:Iiii' 1 ., _ J shoold be reduced to $10,000 as a guarantee for a Hauling Penn:it. Very truly yours, Chalet IV Corporation. 7100 Biscayne Boulevard. Miami, Florida 33138 . (305) 759,2441 WANTMAN &: ASSOCIATES. INC. CONSULTING ENGINEERS '"'7"""l" '....- ,,'-' -.... April 23, 1986 Boynton Beach Engineering 120 North East 2nd Avenue Boynton Beach, Florida 33435 -.--'....-.----"- Attention: Tan Clark RE: Chalet IV of Boynton Plat I, Loop Road and Congress Avenue Performance Bond Reduction Dear Mr. Clark: The majority of the Required Improvements for the subject Plat have been canpleted to date. Our Client, The Chalet DI Corporation, has posted a Performance Bond for Chalet DI of Boynton Plat I, Loop Road and Congress Avenue in the arrount of $484,200.00 (Aetna Casualty and Surety Crnpany). At this tine the Developer respectfully requests to establish a Reduced Bond J\rrnunt of $55,800.00. The arrount represents the Cost of Work Remaining to caIl>lete the Required Improvements in the Plat. Enclosed is a Certified Engineer's Opinion of the Work Remaining. We would appreciate your expeditious review and approval of this request to Reduce the Referenced Performance Bond to $55,800.00. 2328 South Congress Avenue. West Palm Beach, I 1025 Martin Oo~ns Boulevard. Palm City, Flor 5151 Adenaon Street. Orlando. Florida: _~~lt.. 'I O!-~ ti,~f-/.g-" FPo~;-' l.r-aJ R:- ~~{ ?-e;111 PRh~~~ PA~~ :; ~~\e.x-4-~ h~~ V~cP.J- Very truly yours, 11h1'2C4 /llE1JlI' Nancy ~tzger Junior Project Manager c.c.Jack Arnarnik N'I/as 0- '. J ! I' I' I! Ii " II II r " 11 I, " 'I I " 'I I " i WANTMAN & ASSOCIATES, INC. CONSULTING ENGINEERS .~- --. . 1)' i""'~' ."...."r.t"""t~,-"'r "T~-:'-'{ 1..'~ i.~, tl...; :~,.,,' ,(,' ~:'. ~'--"~' April 23, 1986 ,',', ,"", :.-:('\~,. X~:-'.' rn r!,',::~-:r~ """.,.\", '\-.' ':!BilG.. "del. Boynton Beach Engineering 120 North East 2nd Avenue Boynton Beach, Florida 33435 , Attention: Tan Clark RE: Chalet IV of Boynton Plat II Performance Bond Reduction Dear Mr. Clark: The najority of the Required Irrprovements for the subject Plat have been canpleted to date. Our Client, The Chalet IV Corporation has posted a Performance Bond for Chalet IV of Boynton Plat II, in the arrount of $54,125.35 (J\etna Casualty & Surety COOlJaI1Y). At this tine the Developer respectfully requests to establish a Reduced Bond !\m::Junt of $4,500.00. The amJunt represents the Cost of Work Rem3.ining to canplete the Required Irrprovements in the Plat. Enclosed is a Certified Engineer's Opinion of the \iork Rem3.ining. We would appreciate your expeditious review and approval of this request to reduce the Referenced Performance Bond to $4,500.00. Very truly yours, AIe 1,',-y ILlef!J/l' Nancy Metzger Junior Project Manager c.c. Jack Arrrarnik ~V~~i+E. ~oject ~ +/u<J.-/'?,6 7d'1 - V61~ C{ F:))~o Yc::-..- d~ f6. ~ e{}J!>>; lr, ePd-lI . ?~~ O-~~ I r::~7"f::t. 2tf, I '] "';- _ fj./ 2328 South Congress Avenue. West Palm Beach, Florida 33 y b-. 1)1",- 1025 Martin Downs Boulevard. Palm City, Florida 33490 5151 Adanson Street. Orlando, Florida 32804 (30! l'I-I/as CITY of BOYNTON BEACH ~ @ 120 N.E. 2nd AVENUE P.O. BOX 310 BOYNTON BEACH, FLORIDA 33435-0310 (305) 734-8111 Office of the City Engineer March 14, 1986 .1"" ,,"n" i~1-_:\.,-, '~ MAR 1 I, ';(Wr Ms. Nancy Metzger Wantman and Associates, Inc. 2328 South Congress Avenue West Palm Beach, Fl 33406 PLANliiNG Di:CPT. . Re: Chalet IV, Plats 1 & 2, Revised Paving & Drainage grawings Dear Ms. Metzger: Reference is made to your letters of February 5th and February 10th concerning proposed revisions to the drainage and the addition of berms adjacent to Congress Avenue. Please be advised that the revisions to the drainage, ie, de- leting structures, and calling for circular inlet structures, is acceptable. With respect to the berm construction, the configuration will have to conform with the Utility Departments requirement for cover over .the regional force main and water main and valve boxes may have to be extended, etc. The berm construction must be graded to a lower elevation than the sidewalk where adjacent thereto to prevent sheet flow of storm water across the sidewalk. A revised berm cross-section should be submitted for approval after required changes are made. Please advise if you have questions concerning the above. very truly yours, - - CITY O~~YNTON BEACH y'ff~ Thomas A. Clark City Engineer TAC:ck cc: Carmen Annunziato Perry Cessna John Vogt H.H. Harvey ;/ c {}- WANTMAN & ASSOCIATES, INC. CONSULTING ENGINEERS February 19, 1986 City of Boynton Beach ~20 North 2nd Avenue Boynton Beach, Florida 33435 Attention: Mr. Tom Clark RE: CHALET IV OF BOYNTON (a.k.a. SANDALWOOD OF BOYNTON) Dear Mr. Clark: This letter is drafted to address your concern regarding the drainage outfall for the 3.0 acre City out parcel within the Melear P.U.D. (Chalet IV of Boynton). As we discussed, 2 outfall routes are avail~ble for the out parcel. The first of these would be through Plat 2 of Chalet IV (by connecting to catch basin No. C-12 - see Wantman & Associates, Inc. Engineering Plans, job nu~ber 84056-0, dated March, 1985, sheet 3 of 8). An easement would be required for this outfall. If the City plans to outfall to this structure the maximum pipe diameter for connection would be 18 inches, and the contribution of drainage from the City parcel could not be such that it would impair the functioning of the Plat 2 system. If the City chooses this outfall the owner of Chalet IV should be notified directly fo.r the easement request. The second alternative would be to outfall to the proposed Miner Road drainage system. The construction plans for Miner Road are pres~ntly being designed by this office with consideration for accommodating drainage from the 3.0 acre parcel. This outfall route would be preferable since an easement would not be required and greater capacity would be available for stormwater discharge. The proposed drainage system for Miner Road outfalls directly to the lake, then lake discharge passes through a control structure and separate culvert system to the Lake Worth Orainage District L-20 Canal. Final construction plans for Miner Road will be submitted for your review. - continued - . 2328 Soulh Cong..... A..nu. . W.ol P.lm B.ech, Florida 33406 . (305) 967-1100 1025 M.rlln Downo Boul.....d . P.lm City, Flortd. 33490 . (305) 286-8338 5151 Ad.noon Slreet. Ort.ndo. Flortd. 32804 (305) 644-2228 Mr. Tom Clark February 19. 1986 Page Two The South Florida Water Management District has issued conceptual approval for the Melear P.U.D. which includes the City parcel and Miner Road. When construction drawings are available for the City parcel these should be submitted to South Flordia Water Management District for construction and operation approval. I hope that this covers all of your concer~s. If you have any further questions. please do not hesitate to contact me. Respectfully yours. N~Z~ Jr. Project Manager NM/ma cc: Jack Armarnik f11 es c' . MEMORANDUM 10 February 1986 TO: Tom A. Clark, City Engineer FROM: Carmen S. Annunziato, Planning Director RE: Chalet IV - Plats land 2 It appears that by the placement of a berm which separates the plats from the City's property, positive drainage which was originally provided for the City's site may have been eliminated. This should be determined, and if it is so, it should be corrected. ~~ CARMEN S. ANNUNZIATO /bks Attachment MEMORANDUM 10 February 1986 TO: Tom A. Clark, City Engineer FROM: Carmen S. Annunziato, Planning Director RE: Chalet IV - Plats 1 and 2 It appears that by the placement of a berm which separates the plats from the City's property, positive drainage which was originally provided for the City's site may have been eliminated. This should be determined, and if it is so, it should be corrected. /bks Attachment ~~~ 6?~ '7#j-~ tJ3 ~~~~k ~~Y;; (L;J~~~~ Jll'~ S~~% ~ ~ 6R) r~~ = ~A-efJ~ ~~~ C ~~~;.o/ CARMEN S. ANNUNZIATO - r y~ February 5. 1986 ~ G l1- vllJ; WANTMAN . ASSOCIATES, INC. v:. ,: CONSULTING ENGINEERS ())'. _ ~ ~~~,ti~ , ~~' R.ECEIVED Mr. Tom Clark. City Engineer City of Boynton Beach 120 North 2nd Avenue Boynton Beach. Florida 33445 FEB ; I' " . , I\)q.(' ~ I, PLAt,i. ~ '" '--',,_1-) f. --- ____ i CHALET IV - PLATS 1 AND 2. JOB NUMBER 84056-0.D~TED 1985. REVISED FEBRUARY 5. 1986 MARCH RE: Dea r Mr. Cla rk : Please find attached 6 copies of the 3 revised sheets (sheets 3. 7 and 8 of 8. job number 84056-0. dated March 1985. revised February 5. 1986) for Chalet IV. Plats 1 and 2. Also attached are revised drainage calculations. As we discussed earlier. the plans have been modified to (1) include a berm along Congress Avenue. and (2) to delete drainage structure C-l. and C-7 with the attached runoff drainage pipe. It was necessary to delete these structures since the proposed location would have fallen within~the berm. When the drainage calculations were investigated it was noted that these structures could safely be removed and that structures C-2 and C-8 could adequately handle the increased drainage area. Please refer to the attached drainage calculations. All grading will be accomplished in such a manner that runoff will now be directed to structures C-2 and C-8. Your prompt review of the revised plans would be sincerely appreciated. Please contact me at 967-1100 if you have any questions or require additional copies of the revised sheets for your inspectors. Respectfully yours. JliIJ26f' !Z:ewr Nancy 'etzger Jr. Project Manager NM/ma cc: J. Armarnik B. Blazak Observation Department Meridian Surveying 2328 South Congre.. Avenue. Weat Palm Baach, Florida 33406. (305) 987-1100 1025 Mertin Down. Boulevard. Palm CIty. fIorkIII 33490 . (305) 286-6338 5151 Adanaon Street. Orlando, FlorIda 32804 (305) 644-228 , , ~ ", ;~,..:;_~. \L,.~_,,~i @- .~.. 120 N.E. 2nd AVENUE P.O. BOX 310 BOYNTON BEACH. FLORIDA 33435-0310 (305) 734~111 ~ ~. ~;;:;m,"", " " "'--"'h.~..r-~Pl.i-"~=I I ~~ll ~~~j~;~I~ .! -.~ ~ CITY of BOYNTON BEACH OFFICE OF THE CITY ENGINEER -r-,......, .....-.7'"'7-F T~D iCe, ' "/ t:;" March 2, 1987 , ~,; '.) ;-; 1881 P' ~...J-~! ~.i " i~j -'i-,~:')f. Mr. Michael L. Kirk Project Engineer Stanley/Wantman & Associates, Inc. 2000 Lombard Street West Palm Beach, Fl 33407 Re: Miner Road Plans Dear Mr. Kirk: Reference is made to your letter of February 20, 1987. I have reviewed the revised plans and comments are as follows:- 1. Plans are still incomplete and do not extend to the limits as shown on the Master Plan. All of Miner Road as shown on the Master Plan was bonded and a required improvement for the approval of Plat No. 1 of Chalet IV. The Subdivision regulations require that this construc- tion be completed within 21 months. A land development permit was issued for Plats I and II of Chalet IV on January 9, 1986. 2. The top of grass shall be shown at or below the level of the base material at the edge of the roadway. 3. The base material should extend at least 6 inches beyond the surface course of asphaltic concrete. 4. The proposed typical section should show location of swale bottom and depth with respect to the sidewalks. 5. A note should be added that the street lighting will be done by Florida-Power & Light Company after plans are approved by the City and the Florida Power & Light Co. estimated cost is paid to the City by the Developer. Plans should be submitted as soon as possible to Florida Power & Light so plans can be started. con't...... . . To: Mr. Michael Kirk March 2, 1987 Re: Miner Road Plans Page 2 6. A right turn lane is requested at Miner Road and Congress. This will be desirable for normal traffic expected and will be especially important for fire apparatus leaving the site when the new fire station is constructed. As mentioned in item No.1, above, construction shall be complete within 21 months after the January 9, 1986 land development permit. An early completion is important for serving the future fire station, extending water lines to the new proposed ground storage tank and for serving property to be developed to the west. A response to the above comments is requested as soon as possible. Please advise if you have question concerning the above. Very truly yours, C~TON N --V Thomas A. Clark, P.E. City Engineer TAC/ck cc: Joel Wantman, P.E. Jack Armarnik, Chalet IV Corp. Charles Walker, P.E., County Traffic Engineer Carmen Annunziato, City of B.B. Planning Director rt.EI>10RANDUM 13 11arch 1987 TO: Tom Clark, City Engineer FROM: Carmen S. Annunziato, Planning Director RE: l_Mi~er Road Plans/Wantman Letter of March 5, 1987 With respect to Mr. Wantman's letter of March 5th, I offer for your consideration, corr~ents as follows: 1. I do not know who filed with the City, the bond for the western half of Miner Road through the Melear PUD, however, it was filed at the same time as the first plat for the Chalet development. In any case, the 21 months was from the date of the approval of the first final plat. 2. Street lights are required on all public rights-of-way constructed in Boynton Beach, consistent with our subdivision regulations. It does not matter that Miner Road is a County arterial. 3. The language cited in item number 6 of Mr. Wantman's letter is correct, however, two issues remain. One, the right-turn lane is necessary regardless of who pays for it, and two, the Miner Road plans require the reduction in the northbound left-turn lane on Congress, with the developer reducing capacity without compensation. This may mitigate the funding issue. c,,____ , CC~_2 CARMEN S. ANNUNZIATO /bks cc: City Manager Utilities Director RE: -<"> fL..-1..:::! J v ~j Chalet IV CORPORATION(y /' \ q, ry JIS rI'''' ~\ \~; ;;:1', ? ~~~~~~~ESTED 'J'" y)/''''''-' -,",,-,~ :&t7 ( \1' i.'\O c-r r\~:J- r f?,y:r) 7[1 I,D 1 mm --.J v ,/ U's ~ \Cp' (i,.',,"'/ ~ \, ,(1ffl; 1f. 1::8 TIt J "')t ~^,J,!~ ;.r-; 8 \ pU\"i..Mi",;,.:o om. P" j" (; '~ "\ yf" . 'j ~ CHALET IV/MINER ROAD PART 1 l REQUEST FOR PERFORMANCE BOND CANCELLATION OR REDUCTION STANLEY/WANTMAN JOB NUMBER 85109-0 August 12, 1987 Mr. Tom Clark Boynton Beach Engineering 120 North East 2nd Avenue Boynton Beach, Florida 33435 Dear Mr. Clark: Enclosed please find certification from Stanley/Wantman, Inc. of works executed on Miner Road and requesting reduction of bond from $89,773.30 to $60,000.00. We would like to remind you that the following bonds have not yet been reduced, notwithstanding the certifications of Stanley/Wantman during July 1 and July 7, 1987: plat 4 Recreation Area Restoration Bond Plat 1 Plat 3 $20,000 $ 3,000 $15,000 $29,000 $16,800 Cancellation of Bond Cancellation of Bond Cancellation of Bond Reduction to $2,900 Reduction to $1,000 We would appreciate it if the above bonds are cancelled and/or reduced as soon as possible. Sincerely yours, CHALET ,{\ :~~P{~Al::~~ J. Arma~tQk, Execu ~ve Vice r\1 "Is Above President JA/bgm Encl.: Chalet IV Corporation. 7100 Biscayne Boulevard. Miami, Florida 33138. (305) 759-2441 , - ! i STANLEY /WANTMAN, INC. , ~i";t{';r r,-. "", >, -'. "~' .1, '" August 10, 1987 -RC'1nr"lt1'tT-"'''''''~'' , .~ M'" .1'1;' '~j:.; ~. " .loo.~-......J..;;LJJ1. V ..h..!n.....t.... t Boynton Beach Er.gineering 120 North East 2nd Avenue Boynton Beach, Florida 33435 AIlG '1'71001 RU\NNil'~> '0;,;~f~. Attention: Tom Clark RE: Chalet IV/Miner Road Part 1 Request for Performance Bond Reduction Stanley/Wantman Job Number 85109-0 Dear Mr. Clark: The majority of the Required Drainage Improvements for the subject plat have been completed to date. The top section of 4 (four) drainage structures are the only drainage items which have not been installed. The current bond amount for the Drainage Improvements is $32,920.00. As of this date, no required Paving Improvements have been completed. The current bonded amount for the paving items is $56,853.30. At this time the developer respectfully requests to reduce the current total bonded amount of $89, 773.30 to $60,000.00. Included in the $60,000.00 is $56,853.30 which is the full bonded amount of the Paving Improvements. The remaining portion is an opinion of cost of the work remaining to complete the tops of the 4 (four) drainage structures previously mentioned. We would appreciate your expeditious review and approval of this request to reduce the referenced Performance Bond to $60,000.00. ~lY y~u/} /J ~ ~U4pa Thomas D. Alexana~T, P.E. Project Manager c.c. Jak Armarnik - Chalet IV Corporation Bill Blazak - Burg & DiVosta Mary Arnold - Stanley/Wantman Inc. TDA/as LOMBARD CENTER . 2000 LOMBARD STREET . WEST PALM BEACH. FLORIDA 33407 . (305) 842-7444 MEMBER OF THE STANLEY CONSULTANTS GROUP INTERNATIONAL CONSULTANTS IN ENGINEERING. ARCHITECTURE, PLANNING, AND MANAGEMENT Chalet IV CORPORATION October 22, 1987 CERTIFIED MAIL RETURN RECEIPT REQUESTED Mr. Tom Clark Boynton Beach Engineering 120 North East 2nd Avenue Boynton Beach, Florida 33435 RE: REQUEST FOR PERFORMANCE BOND CANCELLATION Dear Mr. Clark: The Miner Road (Part 1) has been accepted by the Palm Beach County representative on Friday, October 16, 1987. You have received from Stanley/Wantman a Certification of Completion of bonded work for Items (a), (b), (c), (d), and (e) in July, and Item (f) in October. (a) plat 1 Cancellation of Bond $ 29,000 (b) Plat 3 Cancellation of Bond 16,800 (c) Plat 4 Cancellation of Bond 20,000 (d) Recreation Cancellation of Bond 3,000 (e) Restoration Bond Cancellation of Bond 15,000 (f) Miner Road (Part 1 ) Cancellation of Bond 89,773 Total Amount $173,573.30 We expect the above Bonds to be cancelled without any further delay. Sincerely yours, CORPORATION Executive Vice president t! JA/bgm Chalet IV Corporation. 7100 Biscayne B('ulevard. Miami, Flor"da 13138. (305) 759-2441 Chalet IV CORPORATION CERTIFIED MAIL - RETURN RECEIPT REQUESTED December 9, 1987 Mr. Tom Clark Boynton Beach Engineering Dept. 120 Northeast 2nd Avenue Boynton Beach, Florida, 33435 RE: Request for performance bond cancellation Dear Mr. Clark: , '" 'AU . ,'.}/ / rJ' .', /J '2y(,1 ,/ '~'A ~ CtY[l/ C)f l' ~fJ0 l We acknowledge your letter of December 4, 1987 with the attached four resolutions dated December 1, 1987. Your resolution #87-EEEE has not reduced the bond of Miner Road but reduced only $8,000 from Plat 1. Further to our letter of October 22, 1987, we request you to cancel the remaining outstanding bonds for which work has been completed and certified by Stanley/ Wantman. These bonds are: (a) Plat 1 - Cancellation of Bond (b) Plat 3 - Cancellation of Bond (c) East Part of Mi~er Road - Cancellation of Bond Total Amount We expect the above bonds to be cancelled without any further delay. ~ ~r}k~ - r ~ ~~ ~/ v-.l0 h~P.Jj UJ~-/~ ~ ~-"J-;)' J.w- , CJ--Ol/X rr'j.7)C5~0~ ~-i\~,q ~UT , Fv~p =rf~ "C",l . . , 1""- '1( I REQUESTED Sincerely yours, CHALET IV CORPORATION (, \llllCt~I()-~ J. Ar ar . , Executive Vice President I cc: I Hen ciklin RECEIVED oel Wantman JA/eg DEe 16 1987 PL/V"'" CERTIFIED MAIL - RETURN RECEIPT Chalet IV Corporation. 7100 Biscayne Boulevard. Miami, Florida 33138. (305) 759-2441 STANLEV/WANTMAN,INC. [ ::Sc=:::l [sL~;~~h 1 December 10, 1987 lfft City of Boynton Beach 120 N. 2nd Avenue Boynton Beach, Fl 33435 Re: Miner Road. Stanley/Wantman Project No. 85109. Attention: Mr. Tom Clark Gentlemen: On December 8, 1987 I had a telephone conversation with Mr. Jim Peters of Palm Beach County Engineering. Mr. Peters informed me that the letter we had received from Mr. Alan Kurtis in October saying that Miner Road had been inspected and accepted is, in fact, Palm Beach County's acceptance of Miner Road and commitment to continuing maintenance. Should you have any questions, please do not hesitate to contact me. ~lY yoursy//, / ~uQ?a2'~~ Thomas D. Alexander, P.E. Project Manager TDA/mjb cc: File .-, LOMBARD CENTER. 2000 LOMBARD STREET. WEST PALM BEACH. FLORIDA 33407 . (305) 842-7444 MEMBER OF THE STANLEY CONSULTANTS GROUP INTERNATIONAL CONSULTANTS IN ENGINEERING. ARCHITECTURE, PLANNING, AND MANAGEMENT CITY of BOYNTON BEACH ~ -;. ~ 'V3; 120 N.E. 2nd AVENUe P.O. BOX 310 BOYNl"ON BEACH, FlORIDA J3.435-0310 (3051134-8111 OFFICE OF THE ClTY ENGINEER December 11, 1987 Mr. Thomas D. Alexander, P.E. Project Manager Stanley/Wantman, Inc. 2000 Lombard Street West Palm Beach, Fl 33407 dd.4 .rr ~/-J I ~~ / Re: Miner Road Dear Mr. Alexander: Reference is made to your letter of December 10, 1987, concerning the subject project. Said letter referenced further the County's acceptance of the Miner Road construction done by the Chalet IV developer's contractor, ie., J.W. Cheatum, Inc. It is apparent to me from my investigation at the site that the eight foot shoulders were not stabilized for the 20" depth with material having a 75 p.s.i., F.B.V. as required by the plans. I presume a credit may be due to the Owner since I have no plans showing a deletion of the shoulder stabilization requirement. The change in plans would need approval from the County and the City of Boynton Beach, in addition to the approval of the developer. , Please advise concerning the above as soon as possible. I would like to take this opportunity to request a set of plans for that portion of Miner Road, west of Sandalwood Drive. As you know, this construction should also have been completed this month and another time extension should be requested. please advise of you have any questions concerning the above. Very truly yours, L\--'''': '....-- : \ 1 ~...J DEe 13 iD~1 PLr.s~ l\d j ~'_;.t ...i __. \. ~ ~ Thomas A. Clark, P.E. City Engineer TAC/ck -- -- con't.... . To: Mr. Thomas D. Alexander, P.E. December 11, 1987 RE: Miner Road Page 2 cc: Mr. Jack Armanik wjcopy of letter of December 10, 1987 Mr. Alan Kurtis, County Engineering Dept.wjcopy of letter Peter Cheney, City Manager wjcopy of letter Raymond Rea, City Attorney w/copy of letter Carmen Annunziato, City Planner wjcopy of letter Ann Toney, Assistant to the City Manager wjcopy of letter J.N. Cheatum, Inc. w/copy of letter Jim Peters, County Engineering Dept. wjcopy of letter The following items are enclosed for your review: 1) 4 sets of plans 2) Drainage calculations & 25 year/3 day flood routing. Please call me if you have any questions. Very Truly Yours, Keshavarz & Associates, Inc. ~~ Ronald Bucina, P.E. Senior Engineer Enclosures co: Joel Wantman, P.E. Thomas Clark, P.E. RB/rar ~ ~- - , - - - - - - - KESHAVARZ CONSULTING & ASSOCIATES, INC, ENGINEERS SURVEYORS January 3, 1989 Project No. 88135 South Florida Water Management District P. O. Box 24680 3301 Gun Club Road West Palm Beach, Florida 33416 ATTH: MS. ANITA CAREY RB: HINER RD. 50-01375-5, CHALET IV '/-v cMQ/, ;1\ \ ('-. \ " (" e ~(f , RECEIVED Hv' ,,',~ I,,? ]i18q PIA"I' '- ., Vii;:.J: Uc..PT" Dear Ms. Carey: We submitted the Miner Rd. plans to Larry Melear, c/o Ann Marie Rezzonico for their review of the proposed drainage ditch, in October of 1988. Joel wantman, P. E., of Stanley jWantman was in touch with the lawyers for the Melear P.U.D. Mr. Wantman indicated that the lawyers for the Melear P.U.D. were not receptive to the proposal of a drainage ditch and would not voluntarily grant an easement for the proposed ditch. The City of Boynton Beach Engineer, Thomas Clark, P.E. would like to see this section of roadway built as soon as possible. To speed up the permitting process, it was suggested by Palm Beach County Engineering to provide retention in the right-of-way and construct a temporary outfall of the L-20 Canal, and avoid the problems of trying to get an easement for the drainage ditch. We discussed the matter with the Lake Worth Drainage District and they did not voice any objection to a temporary connection in our telephone conversations with them. At the direction of our client, Stanley/Wantman, we have reviSed the Miner Rd. plans to provide 1.25" of dry retention in a roadway swale with a temporary overflow to the L-20 Canal. We are also submitting the plans to the Lake Worth Drainage District for their review. The developer responsible for the north half of Miner Rd. will have to install the drainage facilities required to get the drainage to the Chalet IV Lake system and the temporary connection will be abandoned. 4425 BEACON CIRCLE SUITE 201 .. WEST PALM BEACH. FLORIDA 33407 4078448600 ~ ,- ,~ ATTH: RAMZI ASFOUR ROADWAY PRODUCTION RECEIVED --I ~ Jer J1#' L~' UfJ- r ~ \0 J;V' lr\~ \ ~S\;' ;[ ~~ft / .~ KESHAVARZ CONSULTING & ASSOCIATES, INC. ENGINEERS SURVEYORS January 11, 1989 project No. 88135 Palm Beach County Department Engineering and Public Works 160 Australian Avenue West Palm Beach, Florida RE: MINER ROAD . :\~ r ~ ]Y8'.' . .\f,' Dear Mr. Asfour: ;:iA">'" 1"- ''.il.i".,._ u' ':.11" .,..... c.: . The plans have been revised as per the "Inl;ou-office Communication" memo from the Traffic Division dated December 14, 1988 as follows: 1) This note has been added to sheet 9 of 11. 2) The two W14-1 "Dead End" signs have been added to sheet 9 of 11 and the quanti~ies sheet. 3) The cover sheet has been revised to reflect the current County Commissioner's. 4) The typical section has been revised as per a previous meeting with Javier Lopez, P.E. and Ramzi Asfour in December. S) The connection between the Citrus Glen project and the Chalet IV section of Miner Road was discussed in a January 9th meeting which included Andy Hertel, Christopher Mora, P.E. and Ron Bucina. A sketch was left with Christopher Mora, P.E. reflecting the propoljled connection and I have revised the plans accordingly, sheet 7 of 11 and sheet 9 of 11. 6) In order to speed up the approval process of the plans, this requirement was waived by Palm Beach County Engineering as per previous discussions with ~oel Wantman, P.E. 7) Engineer's Certification statement has been added to the' cover sheet. 8) The ultimate section has been revised. 9) The revisions in red have been done. 10) The "Road Closed" sign is shown directly on the Type III Barricade. 11) The "Road Closed 500 Ft." signs have been added. ~ 4425 BEACON CIRCLE SUITE 201 WEST PALM BEACH, FLDRIDA 33407 407e~1 8600 12) R.P.M.'s have been added to the striping plan and quantities sheet. 13) The plan and profile sheets are at 20:1 scale. 'The pavement markings and specifications sheet is at 1"=50' scale. These plans were done prior to the requirement that pavement marking plans had to be at 1"=20'. In order to speed up the construction of this roadway, we are requesting that the pavement markings and specifications sheet remain at 1""50: Please call me if you have any questions. Very Truly Yours, Keshavarz & Associates, Inc. ~c2~ Ronald Bucina, P.E. Senior Engineer RB/rar Enclosures: 2 sets of revised plans 1 original marked up traffic plan 1 traffic comments letter cc: Joel Wantman, P.E. Tom Clark, P.E. ~ ~ KESHAVARZ CONSULTING ASSOCIATES, INC. . I G ENGINEERS SURVEYORS 'f ~ ' e;/V~ cf;J.{ & February 7, 1989 project No. 88135 city of Boynton Beach Engineering Department 200 N. Seacrest Blvd. P. O. Box 310 Boynton Beach, Florida 33425 ATTN: MR. THOMAS CLARK. P.E. REF: MINER ROAD Dear Mr. Clark: I am enclosing one (1) set of the latest Miner Road plans. They have been corrected with respect to the minor comments I received over the telephone from Palm Beach County Engineering Department. We expect to receive approval from Palm Beach County Engineering very shortly. Very Truly Yours, Keshavarz and Associates, Inc. ~~ Ronald Bucina, P.E. Senior Engineer RECEIVED RB/rar Enclosures FEB 9 1989 PLANi\mG D[.!'T. 4425 BEACON CIRCLE SUITE 201 WEST PALM BEACH, FLORIDA 133407 407-844-8600 CITY of BOYNTON BEACH OFFICE OF CITY ENGINEER February 8, 1989 Mr. Ronald Bucina, P.E. Keshavarz & Associates, Inc. Consulting Engineers & Surveyors 4425 Beacon Circle, Suite 201 West Palm Beach, F1 33407 Re: Miner Road Plans (West Part) Chalet IV Dear Mr. Bucina: Reference is made to your letter of February 7, 1989. The subject plans are acceptable to the City Engineering Department, predi- cated on approval by the Palm Beach County Engineering Department. Please advise when plans are approved by the County and when construction will proceed. " Very truly yours, CITY BOYNTO~~ Thomas A. Clark, P.E. City Engineer TAC/ck cc: Peter Cheney, City Manager Carmen Annunziato, City Planner " './ ....(~' :(' '. .~~ ;.';, < ." Y~;:'~",.'T ff.'O \) \~,~'~' \i) l.. ~ . b.\~'''\'' ~.- ~~~ .. \, "'I'-"~-: ..' .).... "'; to,.'"' , .,,, WANTMAN. ASSOCIATES. INC. CONSULTING ENGINEERS MELEAR P.U.D. CHALET IV OF BOYNTON BEACH EXCAVATION METHODOLOGY '\ \ CLIENT: CHALET CORPORATION 7!?O BISCAYNE BLVD. MJAMI, FLORIDA PREPAREO BY: WANTMAN & ASSOCIATES 2328 S. CONGRESS AVENUE ~EST PALM BEACH, FLORIDA 2328 South Congress Avenue. West Palm Beach, Florida 33406. (305) 967~1100 1025 Martin Downs Boulevard. Palm City, Florida 33490 . (305) 286-6338 5151 Ad'anson Slra.l. Orlando, Florida 32804 (305) 644-2229 '. . The following - report has been drafted in an effort to clearly communicate the sequence of earthwork excavation operations which shall be employed by the Chalet Corporation in the development of Chalet IV of Boynton Beach. The selected methods have been designed in order to minimize any impacts to the water resources, and/or to the surrounding areas with regard to noise pollution or airborne dust and sand. Further, the particular methods and design have been selected to insure public safety. Specifically, as general construction practice: 1. Selective area clearing will be restricted to only those areas where construction is about to commence; and the entire stripping of the site shall be avoided. 2. All open wetted down if and sand. disturbed areas shall be seeded and mulched or dry conditions exist to minimize blowing dust 3. Fencing shall be constructed along the eastern and northern project boundaries to prevent any blowing dust or sand from drifting onto Congress Avenue or Miner Road. 4. All dewatering operations will contain discharge onsite. No offsite discharge is proposed during the construction period. 5. Construction will be scheduled so that rainfall runoff from disturbed open areas will flow toward the proposed lake area. 6. Construction will be limited to daylight hours. 7. Lake banks will be graded at a maximum slope of 4:1 to a depth of 2 feet below the water level. 8. All haul roads will be constructed with rock, and a sprinkler truck will be available for dust control. 9. The developer will limit construction to only those areas necessary to perform excavation and fill functions. . . I. EARTHWORK METHODOLOGY A. SEQUENCE OF OPERATIONS 1. Begin selective demucking operations. existing muck limits. area clearing to prepare for Refer to attached soils report for 2. Commence with muck excavation. Stockpile and dry the excavated muck just south of the proposed site and west of the proposed lake. See excavation plan for location. Stockpiles will not exceed 12 feet in height. The estimated amount of muck to be removed is 29,293 C.Y. 3. After the completion of muck removal, complete lake excavation. In order to accomplish muck removal and lake excavation, hydraulic/trash dewatering pumps will be employed. Discharge will be pumped on site and will sheet flow to the low lying area just north of the site. If necessary a berm will be constructed to contain discharge. Use compactible excavated material as fill for muck areas and site. 4. Begin selective area clearing and topsoil stripping for the remainder of the site. 5. Excavate areas of proposed roadway and parking. Use the excavated material which is compactab1e as fill for building pads and for fill of excavated muck areas which do not lie within the lake limits. Borrow will be , obtained from the areas southwest of the site as needed (see excavation plan). 6. Use dried muck for open area fill and mounding. 7. Excess muck and excess site and will be used for phases of development. stockpiling is 10 months. excavation will be stored on open area fill for future The estimated duration of ~ . B. ESTIMATED EARTHWORK QUANTITIES l. Clearing and grubbing 30.9 acres 2. Topsoil stripping 13,955 cu. yd. 3. Muck excavation 29,293 cu. yd. 4. Lake and general excavati on 108,400 cu. yd. 5. On-site fill (spread and compacted) 95,479 cu. yd. ~ . , . DEVEL OPER/OWNE R: DESIGN ENGINEER: EARTHWORK CONTRACTOR: CHALET CORPORATION 7100 BISCAYNE BOULEVARD MIAMI, FLORIDA WANT MAN & ASSOCIATES, INC. 2328 S. CONGRESS AVENUE WEST PALM BEACH, FLORIDA