CORRESPONDENCE
I
tl [%!JfJiJDD@Wo!JO@[l[JD Ij
Kimley-Horn and Associates, Inc_ 5800 Corporate Way, West Palm Beach. Fla 33407. (305)683-5500
RaleIgh. West Palm Beach Tampa. Orlando. NashvIlle. Dallas
December 20, 1984
Mr Wade Riley
RITE CO Development Corporation
1300 West lantana Road - Suite 20 I
lantana, Florida 33462
RE: Construction Plans and Right-of-Way Maps
For Expansion of Congress Avenue/Boynton Beach Boulevard Intersection
Dear Mr Riley:
Kimley-Horn and Associates, Inc. is pleased to submit this proposal to provide
engineering services to prepare plans and specifications for roadway improvements
at the referenced location We have reviewed the details of the required
improvements; we have discussed the project with staff members of Palm Beach
County's Department of Engineermg and Public Works; and we have visited the site
to determine particulars related to the work.
With regard to our discussion with Palm Beach County, we have been informed that
they will undertake signing and marking and signalization requirements for the
project. This condition is as we assumed when we initially (some time ago) made
you aware of the work effort and fee requirements.
For the purpose of defining the scope of work, we offer the following:
A. The intersection improvement will expand both roadways (Congress Avenue
and Boynton Beach Boulevard) to provide three through lanes, dual left turns
and a right turn lane for each approach to the intersection.
B. The length of reconstruction for each approach to the intersection will be
approximately 500 linear feet.
C. The scope of work will involve performing field surveys; making preliminary
investigations and recommendations; preparation of right-of-way maps and
legal descriptions for acquisition of additional rights-of-way; and preparation
of roadway and bridge plans with documents and specifications suitable for
biddmg and construction as a Palm Beach County project.
D. The design will be conducted and the plans will be prepared in accordance
with the latest standards adopted by the American Association of State
Highway Officials, Florida State Department of Transportation and
requirements of Palm Beach County
RITEco/127-1
( r ===;')
II! / --;- , ,r ~"'-'7 I Lr..,--....~r::;'I
l ~~LL LUU'.5")JO:IL'l2-u UJ
Within the above understandmg, the scope of serVices we will provide follows:
TASK 1- FIELD SURVEYS
A. Right-of-Way Surveys
We will review existing right-of-way maps and verify breakdowns of adjacent
parcels. In addition, parcel property lines that will be affected by the
additional right-of-way taking will be established, as required, and tied to the
baseline of survey
B. Design Surveys
We will conduct field surveys to furnish data required for design and
preparation of plans; including, but not limited to the following:
I Set aerial targets that will be used to produce the aerial plan
sheets.
2 Re-establish base lines within the project limits.
3. Tie base lines to section and quarter section lines.
4 Reference base lines control points in order that base lines can be
re-established if disturbed or destroyed during construction of the
roadway improvements.
5 Establish 100' stations along the survey base lines.
6 Establish temporary benchmarks, as required, based upon NGVD-
1929 Datum.
7 Obtain topography, as required, to supplement the aerial
photography Since most topographic data will be produced by
photogrammetry; that which is obscured by overhead cover, or
shadow, or that is otherwise unclear will be obtained by field
surveys.
8. Take roadway cross sections at 100' stations (or as required) to
furnish necessary data for design.
9 Conduct a survey of the existing bridge on Congress Avenue
(north of the intersection) to furnish necessary data for design.
10 Conduct drainage surveys, as required, to furnish necessary data
for design.
J
RITE CO/ 127-2
i.
II LC;r?PT,' ,- ~y-Jftn''''m i!
I ........L..... L~:"'" C--j ~JO L./1JI..!:!..JU 11 U II
,---- )
[/-------- ..
11 Field verify aboveground utilities determined by photogrammetry
Underground utilities will be determined, as required, for design.
TASK 11- PRELIMINARY INVESTIGATIONS AND RECOMMENDATIONS
A. We will perform preliminary studies and make required analyses to determine
the feasibility of including certain design concepts in the project prior to
proceeding with preparation of final plans. The preliminary analyses will
include a functional layout of the project. The layout will show the typical
section for the various roadway elements, the approximate location of new
pavements, connections to existing pavements, and other necessary features
to be incorporated in the final design and plans.
B. The results of the investigation, designs and layouts described in Section A.
above will be prepared in preliminary format on prints and other appropriate
media and reviewed with the affected agencies. These results will be used as
the basis for development of the final plans.
TASK 111- DOCUMENTS FOR ACQUISITION OF ADDITIONAL RIGHT-OF-WAY
A. Right-af-Way Maps
We will prepare right-of-way maps showing survey base line, existing right-
of-way, right-of-way to be acquired, and parcel ownership data.
B. legal Descriptions
We will prepare legal descriptions for each parcel to be acquired, which will
define the taking by a metes and bounds description and include the area of
taking.
TASK IV - DOCUMENTS FOR CONSTRUCTION
A. Design
We will perform design services necessary to establish controls for the
horizontal and vertical construction of the improvements; and design
drainage facilities (including modifications to existing systems) to properly
conduct surface water runoff to existing outfalls within proximity of the
project.
_.~_._- ----- ------------~------~- ---------------
RITECO/127-3
I : 'I
I I~r ________r ..,,, (1f',-
l. i ., ""1'/') '0.''''''''''' II
\_~ ._. < ~,_"l~:~~lj
B. Roadway and Drainage Plans
Prepare a complete set of plans in accordance with the
County and the Florida Department of Transportation.
layouts will be prepared on 1" = 20' scale aerial sheets.
contain, but not be limited to, the following information:
practices of the
The horizontal
The plans shall
1 A cover sheet containing title information, vicinity map, sheets'
index, and other appropriate information.
2 Proposed typical sections and required miscellaneous construction
details.
3. Proposed horizontal and vertical alignments, and geometrics
required for layout and construction.
4. locations of proposed pavements and other items of construction.
5 General notes defining basis of design and construction
requirements.
Required drainage systems, structures, and details
preparation of a drainage map will not be required. )
7 Cross sections and earthwork for proposed grading.
8. Slope ~l~'tenlimits and existing right-of-way
The
6.
9 Miscellaneous construction details.
10 Summary of quantities and schedules with appropriate notes.
C. Bridge Widening Plans
We will prepare a complete set of plans for widening the existing bridge on
Congress Avenue north of the intersection in accordance with the practices
of the County and the latest standards adopted by the American Association
of State Highway Officials. The plans shall contain, and not be limited to,
the following information
1 A plan and elevation sheet.
2. A summary of quantities and design/construction notes.
3. Details showing required modifications to the existing bridge.
---"
RITECO/127-4
( ,
I' .,. '. ~.~ III
L' J[ LL JlYOJV0L0 UV
1..:--- _ _________/
4 Bent and bulkhead details.
5 Superstructure details.
6. Prestressed deck slab details.
7. Barr ier and hand rail details.
8. Sidewalk details.
9 Reinforcing bar listing and standard bar bending details.
10 Approach slab details.
D. Utility Adjustments
Prepare utility adjustment plans identifying which existing utilities will
remain in place, which will be relocated, and which will be abandoned. The
utility plans will be sepia reproductions of the roadway plans. The design and
relocation of the utilities will be prepared by the individual utility owners and
these shall be shown in ink on the sepias. The utility relocation plans will be
incorporated and be made a part of the project plans. Should utility
relocation be minimal, upon approval of the County, the utility relocation
will be shown on the roadway layout sheets.
E. Traffic Control
We will prepare construction phasing plans which will detail sequences of
construction and traffic control. The plans will include necessary lane
closures, detours, temporary pavement construction and other necessary
features to be instituted in order to maximize safety, minimize traffic
congestion and maintain continued access to adjacent properties during
construction. Separate plan sheets may be prepared or the information may
be shown on reproducibles of the roadway plans according to what shall be
required to properly detail the construction phasing information The
construction phasing plans shall be incorporated in and be made a part of the
project plans.
F. Quantities
Compute the quantities of all materials required for construction and prepare
a pay item schedule listing the various construction materials.
---~
RITECO/127-5
II I "'-';~~,~\''''''''n u. --";i''?;"'''':;'
I: L ,--LL L LL05!/w ,I1.:(Q)u u U
L_ I
G. Cost Estimates
We will furnish up to two preliminary cost estimates during the preparation
of the plans and furnish an "Engineer's EstimateJl after plans preparation and
specifications work have been completed
H. Specifications
We will prepare specifications for the project construction. The context of
the specifications will conform to the construction materials and methods
required by the County
I. Permitting
We will contact the vanous permitting agencies and review the plans with the
agencies at appropriate stages of development in order to satisfy the
agencies' require-nents. In addition, we will prepare necessary permit
applications and drawings required for obtaining approval of the project
construction. Permit applications and drawings will be submitted to the
County for transmission to the appropriate agencies.
J. Plans Reviews, Site Visits, Coordination, and Administration
We will send prmts of the plans to the County for review and document at the
50 and 100 percent stages of project completion. Additional prints of the
plans may be submitted, as deemed necessary, at other stages of
development of the plans.
We will make visits to the site, as required, during plans preparation to
confirm onsite features and verify compatibility of the proposed
construction.
We will coordinate our work with the County, utility companies, Florida
Department of Transportation, and other entities, as required, during
preparation of the plans and specifications.
We will conduct project administration, as required, during the preparation of
the plans and specifications.
T ASK V - ADDITIONAL WORK
Should additional work be required which is not covered in the scope of
services, we will undertake said work upon your .vritten authorization.
----"
RITE CO/ 127-6
r- I
I ,L ~ ,- ',' Ice u-tJl"~":;- \;
i l____ ~_=___!J
I
I
FEE AND BILLING
We propose to provide the above described engmeerIng services as outlined in Tasks
I - IV for a lump sum fee of $36,600 00 An ite-nization of the distribution of the
lump sum fee for various tasks follows:
Task I - Field Surveys
$ 5,800
Task II - Preliminary Investigations and Recommendations
1,800
Task II - Documents for Acquisition
Of Additional Right-of-Way
6,400
Task IV - Documents for Construction
22,600
TOTAL lUMP SUM FEE
$36,600
We will accomplish the work outlined in Task V on the basis of our hourly billing
rates in effect at the time the work is done plus 1 15 times direct expenses.
Fees are payable monthly based upon a percent complete of the lump sum elements
or for work actually accomplished for hourly rate elements. Billing will .Je due and
payable within 25 days.
Please be advised that the above lump sum fee does not include obtaining title
search mformation for the parcels affected for acquisition of additional right-of-
way Title search information will be furnished by a local title company We will
coordinate the work with the title company, but the title search cost will be an
expense that will be billed to RITECO Development Corporation with payment
made to the title company by RITECO Development Corporation.
~
"
~
t
tr
\
Ie
\-.
/!
Additionally, soils investigations are not included in our lump sum fee We do not
feel soils data will be required; but should it be required, the work will be
conducted by a local firm, with the same cost payment conditions as for the title
search information.
SCHEDULE
We will work as expeditiously as possible to complete the work within four months.
We are prepared to begm work immediately upon receipt of the executed contract.
__________J
RITECO/127 -7
,n/"r ~ n n I
I I r-"""-""-" ,,,--,.......... J "'--""r->"1""'-"
~__ ~<_:___~_~c~ ~_~:. "L~J J
CLOSURE
If you concur in the foregomg and wish to direct us to proceed with the
aforementioned work, please execute the enclosed copy of this letter agreement in
the space provided and return the same to the undersigned. Fees and times stated
in this agreement are valid for sixty (60) days after the date of agreement by the
engineer.
We appreciate the opportunity to submit our proposal for this important
assignment, and look forward to its approval and an early execution of this
agreement so we can proceed with the work. We look forward to working with you
on this project.
Very truly yours,
KIMLE Y -HORN AND ASSOCIATES, INC.
\
- ,\ \ H ~! -7 c-~ l ~
l ~, "-
James-~ Zook, P.E ' ''""'')'
Vice Pre ident
JRZ:bt
A ttachment: Standard Provisions
/~
Agreed to this
day of
, 1984
RITECO DEVELOPMENT CORPORATION
A corporation
By:
Title Its President/Vice President
Attest:
Its Secretary/Assistant Secretary
(Affix Corporate Seal)
Fla.81
KIMLEY HORN AND ASSOCIATES, INC
STANDARD PROVISIONS
(1) Invoices. Invoices will be submitted by Kimley-Horn and Associates, Inc. (the 'Engineer") to the Client
monthly for services performed and expenses incurred pursuant to this Agreement during the prior month Payment
of each such invoice will be due within twenty five (25) days of the receipt thereof A service charge will be added to
delinquent accounts at the maximum rate allowed by law for each month of delinquency
(2) Failure to Pay If the Client fails to make any payment due the Engineer for services and expenses within
sixty (601 days after the Engineer s transmittal of its invoice therefor the Engineer may after giving seven (7) days
written notice to the Client, suspend services under this Agreement until it has been paid in full all amounts due for
services and expenses.
(3) Legal Action. In the event any invoice or any portion thereof remains unpaid for more than sixty (60)
days followlllg the IIlvoicc date the Engllleer may initiate legal proceeulrlgs to collect the same and recover in add,.
tion to all amounts due and payable including accrued interest, its reasonable attorneys' fees and other expenses reo
lated to the proceeding. Such expenses shall include but shall not be limited to the cost, determined at the Engi-
neer s normal hourly billing rates, of the time devoted to such proceeding by its employees.
(4) Non-Contingency The Client acknowledges and agrees that the payment for services rendered and ex
penses incurred by the Engineer pursuant to this Agreement is not subject to any contingency unless the same is ex
pressly set forth in this Agreement.
(5) Opinions of Cost.
(a) Since the Engineer has no control over the cost of labor materials, equipment or services furnished by
others, or over methods of determining prices, or over competitive bidding or market conditions, any and all opine
ions as to costs rendered hereunder including but not limited to opinions as to the costs of construction and mater
ials, shall be made on the basis of its experience and qualifications and represent its best judgment as an experienced
and qualified professional engineer familiar with the construction industry but the Engineer cannot and does not
guarantee that proposals, bids or actual costs will not vary from opinions of probable cost prepared by it. If at any
time the Client wishes greater assurance as to the amount of any cost, he shall employ an independent cost estimator
to make such determination. Engineering services required to bring costs within any limitation established by the
Client will be paid for as additional services hereunder by the Client.
(b) If a limit with respect to construction or other costs is established by written agreement between the
Client and the Engineer the following will apply
(i) The acceptance by the Client at any time during the performance of services hereunder of a re-
vised opinion of probable cost in excess of the then established cost limit will constitute a corresponding revision in
the previously agreed cost limit to the extent indicated m such revised opinion.
Oi) Any cost limit so established will include a contingency of ten percent unless another amount is
agreed upon in writing.
(iii) The Engineer will be permitted to determine what materials, equipment, component systems and
types of construction are to be included in the drawings and specifications prepared by it pursuant hereto and to
make reasonable adjustments in the extent of the project to bring it within the cost limit.
(iv) If the bidding or negotiating phase of the project has not commenced within six months after
completion of the Engineer's design hereunder the established cost limit will not be binding on the Engineer and
the Client shall consent to an adjustment in such cost limit commensurate with any applicable change in the general
level of prices in the construction industry between the date of completion of the Engineer's design hereunder and
the date on which proposals or bids are sought.
(v) If the lowest bona fide proposal or bid exceeds the established cost limit, the Client shall (1) give
written approval to increase such cost limit, (2) authorize negotiating or rebidding the project within a reasonable
time or (3) cooperate in revising the project's extent or quality In the case of (3) the Engineer shall without addi-
tional charge, modify the plans and specifications prepared by it hereunder as necessary to bring the subject cost
within the cost limit. The providing of such service will be the limit of the Engineer's responsibility in this regard
and, having done so the Engineer shall be entitled to payment for his services in accordance with this Agreement.
(6) Termination The obligation to provide further services under this Agreement may be terminated by either
party upon seven (71 days' written notice in the event of substantial failure by the other party to perform in accord-
ance with the terms hereof through no fault of the terminating party In the event of any termination, the Engineer
will be paid for all services rendered to the date of termination all expenses subject to reimbursement hereunder
and other reasonable expenses incurred by the Engineer as a result of such termination In the event the Engineer's
compensation under this Agreement is a fixed fee upon such termination the amount payable to the Engineer for
services rendered will be determined using a proportional amount of the total fee based on a ratio of the amount of
the work done as reasonably determmed by the Engineer to the total amount of work which was to have been per
formed, less prior partial payments, if any which have been made
I r;:;tOiJiJ~ofXk9xl[jf) I
.
Fla-81
(7) Reuse of Documents. All documents, including but not limited to drawings and specifications, prepared
by the Engineer pursuant to this Agreement are related exclusively to the services described herein They are not in-
tended or represented to be suitable for reuse by the Client or others on extensions of this project or on any other
project. Any reuse without written verification or adaptation by the Engineer for specific purposes intended will be
at the Chent's sole risk and without liability or legal exposure to the Engineer and the Client shall indemnify and
hold the Engineer harmless from all claims, damages, losses and expenses, including but not limited to attorneys'
fees, arising out of or resulting therefrom. Any such verification or adaptation will entitle the Engineer to further
compensation at rates to be agreed upon by the Client and the Engineer
(8) Liability The Engineer is protected by Workmen s Compensation Insurance (and/or employer's liability
insurance) professional liability insurance and by public liability insurance for bodily injury and property damage
and will furnish certificates of insurance upon request. The Engineer agrees to hold the Client harmless from loss,
damage injury or liability arising directly from the negligent acts or omissions of the Engineer its employees, agents,
subcontractors and their employees and agents but only to the extent that the same is actually covered and paid
under the foregoing policies of insurance. If the Client requires increased insurance coverage the Engineer will if
specifically directed by the Client, take out additional insurance if obtainable at the Client's expense.
(9) Limitation of Liability In performing its professional services hereunder the Engineer will use that de-
gree of care and skill ordinarily exercised under similar circumstances, by reputable members of its profession prac
tieing in the same or similar locality No other warranty express or implied, is made or intended by the Engineer's
undertaking herein or its performance of services hereunder It is agreed that, in accordance with and subject to the
provisions of the foregoing paragraph (8) the Client will limit any and all liability claim for damages, cost of de.
fense or expenses to be levied against the Engineer on account of any and all design defects, errors, omissions, and
professional negligence to the amount actually paid in compensation for or with respect to, such liability claim,
cost, or expense under any policy or policies of professional liability insurance maintained by the Engineer Further
the Client agrees to notify any contractor or subcontractor who may perform work in connection with any design,
report or study prepared by the Engineer of such limitation for design defects, errors, omissions, or professional
negligence, and require as a condition precedent to his (or its) performance of such work an identical limitation of
liability on his (or its) part as against the Engineer In the event the ClIent fails to obtain an identical limitation of
liability provision as to design defects, the Client shall indemnify and hold the Engineer harmless for any liability
related to errors, omissions, or act of professional negligence in such a manner and to such extent that the aggregate
liability of the Engineer including awards and costs assessed by any mediator-arbitrator for such design defect to
all parties, including the Client, shall not exceed the aforementioned amount. Under no circumstances shall the
Engineer be liable for extra costs or other consequences due to changed conditions or for costs related to the failure
of the contractor or materialmen to install work in accordance with the plans and specifications.
(10) Expenses of litigation In the event litigation in any way related to the services performed hereunder is
initiated against the Engineer by the Client, its contractors, or subcontractors, and such litigation concludes with the
entry of a final judgment favorable to the Engineer the Client shall reimburse the Engineer for all of its reasonable
attorneys' fees and other expenses related to said litigation Such expenses shall include but shall not be limited to
the cost, determined at the Engineer's normal hourly billing rates, of the time devoted to the defense of such litiga-
tion by the Engineer's employees.
(11) Controlling law This agreement is to be governed by the law of the State of Florida
(12) Binding Effect. This Agreement shall bind and the benefits thereof shall inure to the respective parties
hereto their legal representatives, executors, administrators, successors and assigns.
(13) Merger, Amendment. This Agreement constitutes the entire agreement between the Engineer and the
Client, and all negotiations and oral understandings between the parties are merged herein This Agreement can be
supplemented and/or amended only by a written document executed by both the Engineer and the Client.
(14) Photographs. Photographs of any completed project embodying the services of the Engineer provided here-
under may be made by the Engineer and shall be considered as its property and may be used by it for publication.
(15) Compensation for Additional Services. The undertaking of the Engineer to perform professional services
under this Agreement extends only to those services specifically described herein. If upon the request of the Client,
the Engineer agrees to perform additional services ( Additional Services ') hereunder the Client shall pay the Engi-
neer for the performance of such Additional Services an amount (in addition to all other amounts payable under this
Agreement) equivalent to iii the payroll costs ( 'Payroll Costs ') incurred by the Engineer in providing such Addi-
tional Services multiplied by a factor of 2 75 plus (ii) the reimbursable expenses ( Reimbursable Expenses ') so in.
curred by the Engineer in providing such services multiplied by a factor of 1 15.
....
\
,)
DRAFT
FOR REViEVV ONLY
.L
SUPPLEMENTAL AGREEMENT
BETWEEN
RITECO DEVELOPMENT CORPORATION
AND
KIMlEY-HORN AND ASSOCIATES, INC.
FOR PROFESSIONAL ENGINEERING SERVICES
FOR AN ENGINEERING STUDY AND JUSTIFICATION REPORT
OF A PROPOSED INTERCHANGE AT 1-95 AND NW 22ND A VENUE
IN BOYNTON BEACH, FLORIDA
THIS SUPPLE~1ENT AL AGREEMENT made and entered into this day of
, 1984, by and between RITECO DEVELOPMENT CORPORATION,
hereinafter called the Client, and KIMLEY -HORN AND ASSOCIATES, INC., heremafter
called the Engineer, a Florida corporatiOn, of 5800 Corporate Way, West Palm Beach,
F lor ida.
WITNESSETH
WHEREAS, the Client and Engineer heretofore on
into an agreement whereby the Engineer was retained
services to the Client;
, entered
to furnish certain professional
WHEREAS, the Client now desires to expand the scope of the proposed services (see
attached scope of work - EXHIBIT "A"); and
WHEREAS, it has been determined that a lump sum fee of Sixty-three Thousand Six
Hundred and Forty Dollars ($63,640 OO) is reasonable and just compensation for the
addi tional services.
NOW THEREFORE, THIS INDENTURE WITNESSETH: That for and in consideration
of the mutual benefits to flow from each to the other, the parties hereto agree as follows:
1 The Engineer agrees to produce the required interchange justification
report and provide such other services as described in EXHIBIT "A" of
this Supplemental Agreement
2 The Client agrees to pay the Engineer a lump sum fee of .$63,640 00 for
these addl tiOnai serVices.
4479 01/P84-22
Page 1 of 2
Except as hereby amended, changed or modified, all other terms and conditiOns at
the original Agreement dated and supplements thereto shall
remain in full force and effect
IN WITNESS WHEREOF, the parties hereto have made and executed this Agreement
as of the day and year first above written
OWNER:
ENGINEER:
RITECO DEVELOPMENT CORPORA nON KIMLEY -HORN ANDASSOCIA TES, INC.
By
By:
Title
Ti tIe:
Date
Da te:
ATTEST:
Da te:
Da te:
4479 0 l/P84-22
Page 2 of 2
EXHIBIT "A"
SCOPE OF SERVICES
FOR
INTERCHANGE JUSTIFICATION REPORT
PROPOSED INTERCHANGE AT 1-95 AND NW 22ND AVENUE
BOYNTON BEACH, FLORIDA
t.
Prepared by:
KIMLEY -HORN AND ASSOCIATES, INC.
Prepared for
RITECO DEVELOPMENT CORPORATION
COPR JUNE 1984
INTRODUCTION
This proposal has been prepared at the request of the RITECO Development
Corporation to determine the feasibility of a new interchange on 1-95 at NW 22nd
A venue in Boynton Beach, Florida.
Before a new interchange can be built on 1-95, the FHWA requires that an economic
analysis be undertaken to determine whether or not the interchange can be justified
from the standpoint of cost-effectiveness In other words, a determination as to
whether the public will receive benefits, over the life of the project, to offset the
costs, must be made A cursory review of environmental, social and other economic
issues surrounding the project must also be made to determine the overall
"environmental attainability" of the project Analysis of environmental attainability
does not pre-empt nor presume any final environmental determinations. An in-depth
environmental analysis will be conducted in the near future.
In this case, it is also appropriate to perform a preliminary analysis of alternatives.
The purpose of this analysis should be to refine and define an interchange concept
and configuration that best represents a solution to the engineering problems. This
exercise should also be utilized to establish the geometric and operational feasibility
of the proposed plans. Since this study precedes the environmental assessment
process, no final decisions or quantified geometric analysis can be prepared. All
analyses in this proposal are preliminary and all geometric studies will be graphic in
nature
OVERVIEW
This proposal is designed to answer a number of key issues that are
critical to the FHW A, FOOT, and the County These include:
o Is it cost-effective to construct an interchange on 1-95
providing direct access to the NW 22nd A venue?
o On a preliminary basis, what is the best configuration for such
an interchange?
o Is there a proposed interchange concept that will operate
effectively under forecast peak period traffic conditions? Can
it be constructed under heavy 1-95 traffic condi tions
o Is there an interchange configuration that is geometrically
feasible and acceptable from the standpoint of Federal-Aid
Interstate design standards
o Will connecting facilities be able to adequately feed and
discharge projected interchange volumes?
i-
o Is there a feasible interchange concept that is environmentally
attainable?
o Will the project's impacts on the local economy,
neighborhoods, and social fabric jeopardize the feasibility of
the project?
o Is the proposed proj ect consistent wi th other local plans,
programs and priorities?
o Does the project have local support and has it been
coordinated, on a preliminary basis, with key officials that
might have an interest in it?
This proposal identifies the methodologies and framework for attacking
and resolving these issues. It provides for the publication of the
appropriate documentation to secure appropriate and necessary
approvals of the FHW A, FOOT and local government
-2-
TECHNICAL APPROACH
The following pages contain a task-by-task description of the important
elements essential to the success of the interchange justification
project This technical approach contains sufficient technical analysis
effort to secure the necessary economic justification approvals
required This approach simultaneously suggests sufficient analysis to
assure that a workable interchange configuration can be developed,
wi thin reasonable and tolerable social/ economic/ environmental
constraints
The tasks in this approach have been organized into nine (9) major
categories or "Task Groups," as follows:
o Task Group I - Transportation Systems Analysis
o Task Group 2 - Traffic Engineering Analysis
o Task Group 3 - Engineering Analysis
o Task Group 4 - Preliminary Social, Economic and
Environmental Studies
o Task Group 5 - Relationships to Other Plans and
Programs
o Task Group 6 - Economic Analysis
o Task Group 7 '- Alternatives Analysis
o Task Group 8 - Meetings and Conferences
o Task Group 9 - Documentation
Each of these Task Groups is described in greater detail in the pages
that follow
-3-
TASK GROUP 1
TRANSPORTATION SYSTEMS ANALYSIS
This task will involve the overall collection and verification of the
transportation systems data required for an interchange justification
report The purpose of this effort is to collect and organize all of the
relevant and necessary data that will be used in subsequent tasks
TASK 1.1
COLLECT AND ANALYZE DATA
This task is organized into seven (7) subtasks as follows:
Subtask 1.1.1 - Obtain existing network
Existing and available urban area transportation data
relative to the existing transportation networks will be
collected, evaluated and verified for reasonableness
Subtask 1.1.2 - Obtain forecast network(s)
A vail able urban area transportation data for the future
transportation system in the project area will be
collected, classified and organized
Subtask 1.1.3 - Acquire trip tables
A vailable trip making characteristics of the urban area
will be collected for both existing and forecast condi tions
Subtask 1.1.4 - Inventory number of lanes/capacity
characteristics
The accuracy of the data in the urban area transportation
study statistics will be field-verified.
Subtask 1.1.5 - Collect soci~economic data and travel
models
The socio-economic forecasts and trip generation models
will be acquired and reviewed
Subtask 1.1.6 - Inventory current land-use/development
plans/ proposals
Current land-use plans and major development proposals
will be inventoried to update the trip-making models, as
needed.
Subtask 1.1.7 - Summarize Data
All preceding data will be summarized into usable
formats
-4-
TASK 1.2
DEVELOP BASE MICRONETWORKS
This task will involve the identification of the portion of
the existing and future roadway systems that will be
relevant to the analysis. It will also involve the
preparation of microscale graphics, network formatting
and coding for subsequent computer analysis
Subtask 1.2.1 - Base Micronetworks
Detailed micronetworks for both existing and future
condi tions will be identified, mapped and coded for
subsequent computer analysis. One-way coding of the
interchange system will be undertaken to insure the
adequacy and level of detail necessary to perform
weaving analyses, and movement-by-movement capaCl ty
analysis
It is proposed that a third micronetwork containing future
HOV lanes on 1-95 also be developed and analyzed to
insure ali FHW A concerns and policies are addressed.
This plan will also include exclusive HOV connector ramps
to the airport
This coding activity will include the preparation,
compilation and recording of capacity characteristics,
operating speeds, link length, number of lanes, turn
prohibi tions, and similar operating data, for each link and
node in each of the micronetworks
One network will be coded with no interchange to serve as
the base case for comparison purposes
Subtask 1.2.2 - Check and Verify Base Micronetworks
Both the future and forecasts micronetworks will be
checked for mapping and coding errors prior to computer
analysis. This doublecheck will minimize expensive
computer time spent finding and debugging network
coding errors at a later time
-5-
TASK 1.3
TASK 1.4
DEVELOP MICRO-TRIP TABLE FOR STUDY AREA
This task will involve the acquisition of base year and
horizon year trip tables and socio-economic data. These
trip tables will be modified into the desired format
Zones external to the study area will be compressed into
"macro-zones" since they are not relevant to the micro-
analysis At the same time traffic zones in the study area
will be subdivided, as appropriate, to insure an adequate
level of detail for the micronetwork analyses
This task will also involve the redistribution of trips
within the new zonal framework for the existing and
forecasts trip tables Trip generation rates for the
airport and high-growth zones will also be checked and
adjusted, if needed
Subtask 1.3.1 - Collect and Review Data
Existing and available trip tables for existing and forecast
conditions will be collected In addition, socio-economic
data, and trip productions and attractions will be analyzed
to determine their reasonableness in view of current land
use developments and development proposals in the study
area. Meetings with local planning officials will be
arranged to collect and review recent development
proposals, and modifications to land use plans
Comprehensive plans and other relevant data will also be
collected and discussed with local officials.
Subtask 1.3.2 - Modify Trip Tables
Trip generation rates will be modified as needed and the
trip table modified accordingly Growth factors will be
applied to update the forecast trip table to the desired
horizon year (20 years from date of opening)
TRAFFIC ASSIGNMENT
After all trip tables have been prepared, and
transit/carpool splits established, auto, transit and
carpool trips will be assigned to the micronetwork for
existing and planning horizon years
-6-
TASK 1.5
TASK 1.6
Subtask 1.5.1 - Load Auto Trips
Auto trips will be loaded to the micronetwork using
automated traffic assignment models
Subtask 1.5.2 - Load Carpool and Transit Trips
Transit and carpool vehicular trips will also be loaded to
the network
SUMMARIZE TRAFFIC ASSIGNMENT DATA
Traffic assignment statistics will be summarized in
tabular form sui table for incorporation into the final
report These statistics will also become the primary
source of road user data for input into the road user
benefit analysis. These statistics will include vehicle
miles of travel (VMT), vehicle hours of travel (VHT) and
person-hours of travel (PHT)
SUMMARY MEMO
A summary memorandum covering all of the information
generated within this Task Group will be prepared
-7-
TASK GROUP 2
TRAFFIC ENGINEERING ANALYSIS
The traffic engineering task group is designed to assure the operational
integrity and feasibility of the plans under study Results of this effort
will also play an important role in the project's final justification by
pinpointing the operational benefits of the project
TASK 2.1
UPDATE TRAFFIC DATA
Existing and available traffic counts in the area will be
updated and supplemented with new available data
generated since earlier studies Where necessary, and
where needed traffic count information is absent,
addi tional traffic counts will be taken, as required
TASK 2.2
DEVELOP MICRO-ASSIGNMENT OF PEAK HOURl Y
VOlU MES
The results of the preceding analysis will be assigned and
displayed in a graphic single-line format to illustrate the
critical peak volume loadings for individual links in the
various interchange configurations
TASK 2.3
ANALYZE CAPACITY OF INTERCHANGE CONCEPTS
Once the controlling peak hour volumes are graphically
displayed on each of the interchange configurations under
study, an in-depth analysis of the capacity of each
configuration can be undertaken The purpose of this
analysis is twofold: first, it is to determine those
components of each interchange configuration that may
be deficient from a capacity and level-of-service (LOS)
standpoint; second, it is to identify those remedies that
can be implemented to reduce or eliminate the capacity
problems so identified.
Subtask 2.3.1 - Preliminary Screening
To undertake this analysis effort, it is important to
discard unneeded analyses. For example, certain sections
and components of the various interchange concepts will
be obviously sufficient from a capacity analysis
viewpoint These sectlOns w1l1 not be subjected for
unneeded in-depth quantitative analysis.
-8-
TASK 2.4
Subtask 2.3.2 - Execute Capacity Studies
Capacity studies will be conducted for the following types
of freeway segments:
o Basic freeway mainline segments
o Basic freeway ramp segments
o Isolated on-ramp
o Isolated off-ramp
In addition to the studies listed above, critical lane
analyses for critical signalized intersections will also be
performed.
Subtask 2.3.3 - Determine Levels of Service
Based upon the preceding effort expended in Subtask
2.3 2, the level-of-service of each roadway segment and
intersection will be classified in accordance with its
corresponding level-of-service, using the following
categories:
o Level of Service "C", or better
o Level of Service "0"
o Level of Service "F"
Subtask 2.3.4 - Plot and Display Level of Service Results
Based upon the results of Subtask 2.3 3, these results will
be graphically displayed on single-line representations of
the interchange configurations
ANALYZE CAPACITY OF SURROUNDING FACILITIES
TO FEED AND DISCHARGE I~TERCHANGE VOLUMES
In recent years, the FHW A, and the traffic engineering
communi ty, in general, have become acutely concerned
with upstream/downstream capacity problems. In many
cases in the past, massive investments have been made
-9-
TASK 2.5
into major freeway or highway expansion projecvts, only
to find that these improvements were underutilized, due
to the inability of connecting facilities to feed and
discharge the volumes associated with the improvement
Subtask 2.4.1 - Upstream/Downstream Capacity Studies
To avoid this problem, it is important to analyze the
capaci ty of the facilities connected to the planned
improvement In this case, the capacity of several
connecting facilities will be analyzed against the capacity
of the proposed interchange:
o 1-95 - and connecting facilities, south of the proposed
interchange
o 1-95 - and connecting facilities, north of the proposed
interchange
o NW 22nd Avaenue, east and west of the proposed
interchange
SAFETY ANALYSIS
One of the key factors in any economic analysis is the
costs associated with accidents. Normally, improved
facilities can significantly enhance the safety
characteristics of a transportation system This task will
be composed of several key subtasks:
Subtask 2.5.1 - Collect Accident Records
Accident records for 1-95 and connecting facilities in the
area will be collected and analyzed
-10-
TASK 2.6
Subtask 2.5.2 - Analyze Accident Data
Accident statistics will be categorized as fatal, property-
damage only (PDO) or injurious
Subtask 2.5.3 - Develop Unit Costs
Uol t costs for the various types of accidents will be
researched and developed
Subtask 2.5.4 - Develop Accident Forecasts
Forecasts of accident rates under the various
improvement scenarios will be prepared These
alternatives will include the "Do-Nothing" alternative
Subtask 2.5.5 - Develop Accident Cost Profiles
Accident cost profiles for the various alternatives will be
prepared by accident category
CONCEPTUAL MAINTENANCE OF TRAFFIC ANALYSIS
Maintaining interstate traffic during massive interchange
construction and 1-95 reconstruction is a complex and
oftentimes expensive undertaking The design concepts
must be sensi tive to this factor, and will be evaluated for
their ability to be constructed under heavy traffic
condi tions
The objective of this task will be to conceptually analyze
maintenance of traffic schemes that maintain the existing
number of lanes of traffic wherever possible At the
same time, design concepts will be reviewed and modified
to accommodate sensible, cost-effective maintenance of
traffic schemes
-11-
TASK 2.7
PREP ARE TRAFFIC ENGINEERING TECHNICAL MEMO
A technical memo summarizing the results of the Traffic
Engineering Task Group will be prepared.
-12-
TASK GROUP 3
ENGINEERING ANALYSIS
This task is essential to the development of a reasonable and practical
concept that will be subjected to the various analyses. The concepts
must be workable, geometrically, and the purpose of this analysis is to
assure that this is the case
To accomplish this, "desirable" federal-aid interstate design criteria
should be followed to the maximum extent feasible If these criteria
cannot be met, strong reasons for nonconformity must be clearly
established
In this case, detailed typical section studies are required in the vicinity
of potential right-of-way problems in order to understand the order-of-
magnitude of the project's impacts
Likewise bridge span arrangement studies must be undertaken to grasp
the technical feaSibility of several concepts, and to get a handle on
cos ts
This task group will also include the important task of cost estimating
which is essential to the process of securing federal justification
TASK 3.1
GEO~ETRIC FEASIBILITY ANALYSIS
A number of geometric tests must be performed to assure
that the concepts under consideration are geometrically
feasible This will involve several subtasks:
TASK 3.2
ADJUST GEOMETRIC PLANS
Based upon the analysis completed in Task 3.1, the
alternative concepts will be modified and re-drafted to
better accommodate desirable design criteria. These
adjustments may include longer weaving areas, improved
gore arrangements, improved span arrangements,
enhanced geometric conditions, and improved merging
condi tlOns
TASK 3.5
PREP ARE COST ESTIMATE
This task will involve several subtasks; as follows:
-13-
TASK 3.6
Subtask 3.5.1 - Acquire Unit Cost Data
Current FOOT unit cost information will be obtained
Subtask 3.5.2
Quantities
Develop Preliminary Construction
Preliminary quantities for major cost items such as lane-
miles of pavement, square-footage of bridge (by
category), cubic yards of embankment, and linear feet of
retaining wall will be developed A gross parametric
percentage unit estimate for incidental engineering and
contingencies will be used
Subtask 3.5.3 - Estimate Right-of- Way Costs
Local unit land costs for industrial/residential acreage
and structures will be obtained for the area by contacting
local realtors. A rough estimate of total acreage and
I-
square feet of strlictures will be made for each al ternate
PREPARE TECHNICAL MEMO
A technical memo summarizing the findings of the
engineering analysis will be prepared.
-14-
TASK GROUP 4
PRELIMINARY SOCIAL, ECONOMIC AND ENVIRONMENTAL
STUDIES
This task group involves a preliminary examination of the
environmental attainability of the various alternatives. This is not a
final environmental assessment and will not result in any final
environmental determinations. However, this analysis will answer the
question: "is the project environmentally attainable?" This analysis
will also identify significant social, economic and environmental issues
and their order-of-magni tude The relative impact of the various
alternatives will be analyzed in a preliminary way, and unfeasible
concepts will be modified or discarded
TASK 4.1
INSPECT PROJECT SITE FOR SENSITIVE AREAS
An inspection of the project site will be performed to
inventory classify, and assess the sensi tivi ty of potential
impacts. i.
TASK 4.2
ANALYZE SOCIAL IMP ACTS
The impact of the various alternatives on local
neighborhoods, parks, recreation facilities, police/fire
facilities, churches, minority groups, schools, historic
sites, archaeological sites, hospitals, nursing homes,
medical services, and the like, will be assessed in a
preliminary way
ECONOMIC IMPACT STUDY
TASK 4.3
The economic impact of the project on the local economy
will be assessed in a general way The impact of the
project on local businesses and employment, in the short,
and long term will be identified This analysis will include
conclusions regarding project impacts on the following
categories:
o highway construction employment
o general employment
o local businesses displaced
o overall economic condi tion of metro area
o indirect benefits
-15-
TASK 4.4
TASK 4.5
TASK 4.6
TASK 4.7
ANALYZE ENERGY IMPACTS
The effect of the project on overall energy consumption
will be analyzed and addressed, in a qualitative manner
Motor fuel consumption will be addressed quantitatively
ANALYZE ENVIRONMENTAL IMPACTS
A cursory assessment of environmental impacts will be
made by visual inspection of the project area and by
conferences with local environmental officials.
Environmentally-sensi ti ve receptors and habitats for
endangered species will be identified, if any, and the
impact of the project on local waters and wetlands will be
addressed In addition, the general effect of the project
on air quality, noise and local hydrology will be addressed.
IDENTIFY MITIGATIVE COUNTERMEASURES
If noise or other impacts are identified as being
significant, the appropriate mitigative countermeasures
will be suggested, and identified The effectiveness of
the countermeasure will be addressed.
TECHNICAL MEMO
A technical memo summariz~ng the findings of the
preliminary social, economiC and environmental
assessment will be prepared.
-16-
TASK GROUP 5
RELATIONSHIP TO OTHER PLANS AND PROGRAMS
To receive federal approval for a new interchange on 1-95, it must be
demonstrated that the proposed improvement is consistent with other
local plans and programs. The purpose of this task group is to provide
that documentation.
TASK 5.1
INVENTOR Y PLANS AND PROGRAMS
Other local plans, programs and goals will be collected
and examined. These plans will include local land use
plans/comprehensive plans, transportation plans,
transportation improvement programs, transi t
development programs, capital improvement programs
and so f<;xth.
EVALUATE COMPATIBILITY
~
TASK 5.2
The compatibility of the proposed project with other plans
and programs will be analyzed
TASK 5.3
TECHNICAL MEMO
A technical memo summarizing the findings of this task
group will be prepared.
-17-
TASK GROUP 6
ECONO \HC ANALYSIS
The central part of this study is the economic analysis. This analysis
must be conducted in accordance with the 1977 AASHTO Manual on
User Benefit Analysis Any deviations from the procedures in this
manual must be documented and justified. If such modifications are
found to be appropriate, more efficient, and justifiable, they will be
documented. Otherwise, this analysis process will be executed in
accordance with the AASHTO manual ThiS analysis will be conducted
for two scenarios:
o "Do-nothing" alternative
o One interchange concept
TASK 6.1
DA T A SELECTION AND DEVELOPMENT STUDIES
A host of unit cost factors most be researched, developed
and formatted tor input into the economic analysis
program This wiIl involve several subtasks
Subtask 6.1.1 - Update Cost Factors
Cost factors must be updated to current year costs using
the Consumer Price Index or other indices of inflation.
Some of the factors, that must be researched and
updated, in accordance with AASHTO requirements, will
include:
o Gasoline costs
o Idling cost factors
o Unit value of motorists' time
o Oil costs
o Tire costs
o New car depreciation factors
o Repair and maintenance costs
o Interest rates
o Section cost factors
Subtask 6.1.2 - Identify and Classify Roadway Sections
The AASHTO procedures provide for the stratification of
user costs and benefits in accordance
classification of each roadway segment.
segments can be subclassified by a
wi th the
Roadway
variety of
-18-
TASK 6.2
characteristics, including design, speed, grades, curvature
and so forth. This classification procedure will be
undertaken in compliance with AASHTO guidelines
Subtask 6.1.3 - Develop User Cost Factors and Related
Data
Once uni t cost factors are updated to the current year,
and roadway sections have been classified, user cost
factors will be developed and sorted for application to
each category of roadway This procedure will include
the development of the following data for input into the
analysis process:
o Roadway variables affecting running costs
o Vehicle miles of travel
o Passenger hours of travel
o Vehicle class mix
o Passenger car running cost consumption factors:
- fuel - maintenance/repair
- oil - depreciation
- tire wear
o Truck running costs
o Truck class mix
o Accident costs
o Other data, as required
Subtask 6.1.4 - Format Input Data
The above data will be assembled and compiled into a
usable format for computer analysis purposes
EXECUTE BENEFIT - COST ANALYSIS
A comprehensive benefit cost analysis will be executed in
accordance with AASHTO guidelines It is anticipated
that this analysis will be executed using a computer
program available from the DOT that is based upon
AASHTO procedures and that has the approval of the
FOOT and FHW A
-19-
TASK 6.3
The purpose of this task is to determine the relative
economic merit of the project, as a whole This analysis
will also produce some preliminary comparisons among
the alternatives subjected to the analysis
The proposed procedure will be a present worth analysis.
The current value of the user benefit stream will be
computed and divided by the present worth of the capital
and operating/maintenance costs of the proposed
imporovment packages The user benefit stream will be
computed by subtracting the user costs of the proposed
improvements, from the "do-nothing" alternative, over a
twenty year planning period If the net present value
(NPV) resulting from this computation is greater than
zero, then the project is justified
SUMMARIZE FINDINGS
The findings of this economic analysis task group will be
summarized in a technical memo This memo will include
singleline graphic representations of the al ternati ves
analyzed and a listing of all of the assumptions used in the
analysis.
-20-
TASK GROUP 7
AL TERN A TIVES ANALYSIS
The task group will involve a preliminary evaluation of each alternative
using all of the criteria and analytic data assembled in previous tasks
Both quantitative and qualitative data will be used to establish the
general relationship of each alternative to each other in a
comprehensive format A matrix analysis procedure is proposed.
DEVELOP EVALUATION CRITERIA
TASK 7.1
Broad project goals and objectives will be subdivided into
specific criteris for evaluation purposes These criteria
will include subdivisions of such items as level fo
transportation service, safety, economic impacts,
environmental impacts, social/neighborhood impacts, and
costs
TASK 7.2
ANALYZE AL TERNA TIVES AGAINST CRITERIA
Each alternative will be arrayed in matrix format against
the evaluation criteria. Subjective and objective data will
be displayed in the matrix. These data will then be used
to judge the relative value of one alternative versus
another
TASK 7.3
SUMMARIZE FINDINGS
A graphic display of the matrix analysis will be prepared.
A technical memo summarizing the principal findings of
the analysis will also be prepared
-21-
T ASK GROUP 8
MEETINGS AND CONFERENCES
This task group includes all of the meetings and conference required for
the study effort.
TASK 8.1
CONDUCT MEETINGS WITH GOVERNMENT OFFICIALS
Multiple meetings with a number of government agencies
will be required at various stages of the analysis process
Some meetings will be held during the data collection
phase and others will be held during key technical analysis
activities Very important meetings will also be held with
the lead agencies (i.e., the FOOT and Palm Beach County)
prior to publication of findings, for review purposes
Agencies that will be contacted will include:
o FDOT - District 4
o FOOT - Tallahassee
o Palm Beach County Department of Engineering
o Palm Beach County Planning
o MPO staff
o FHW A
o City of Boynton Beach
o Florida Department of Environmental Regulation
TASK 8.2
CONDUCT MEETINGS
ENVIRONMENTALISTS
WITH
LOCAL
Meetings with local people intimately familiar with
environmental issues will also be arranged These people
will include local archaeologists, historic site personnel,
wildlife experts, marine biologists and general
environmentalists Leaders of local organized
environmental groups such as the Audobon Society will be
sought and contacted.
-22-
TASK 8.3
TASK 8.4
CONDUCT MEETINGS WITH lOCAL BUSINESS lEADERS
Several meetings will be held with local chambers of
commerce and/or local business leaders Individual
neighborhood leaders and businessmen directly affected
by the project will also be contacted, as appropriatae
PREPARE MINUTES OF MEETINGS
Summary minutes of all meetings will be prepared, filed
and maintained.
t
-23-
TASK GROUP 9
DOCUMENT A nON
This task group will include the compilation and preparation of all study
documentation.
TASK .9.1
PREPARE DRAFT REPORT
A draft of the final report will be prepared for circulation
to the County, FOOT and FHW A for review and comment.
TASK 9.2
REVIEW DRAFT REPORT
A meeting will be held to coordinate and discuss review
comments Conflicting comments will be resolved
TASK 9.3
PREPARE FINAL REPORT
The draft report will be rewritten as needed based upon
the results of Task 9 2. Appendices will be included as
needed
-24-
PROJECT SCHEDULE
We propose to execute this assignment within eighteen (18) weeks of
your notice to proceed.
t.
P84-2~
-25-