R06-197
II
1 RESOLUTION NO. R06- ,q 1
2
3 A RESOLUTION OF THE CITY OF BOYNTON
4 BEACH, FLORIDA, AUTHORIZING CHANGE ORDER
5 #6 WITH SESSOMS CONSTRUCTION FOR THE
6 BOYNTON BEACH LIBRARY PROJECT;
7 DECREASING THE GENERAL CONTRACTOR'S
8 CONTRACT SUM BY $396,137.52 AND INCREASING
9 THE CITY'S CONSTRUCTION COSTS BY $367,780.00
10 TO PAY FOR OWNER DIRECT PURCHASES FOR A
11 TOTAL NET SAVINGS OF $28,357.52; PROVIDING
12 FOR A $50,000.00 CONTINGENCY; AND PROVIDING
13 AN EFFECTIVE DATE.
14
15 WHEREAS, the City of Boynton Beach, through owner direct purchases, has been
16 able to take advantage of a Tax/Cost Savings Recovery Program; and
17 WHEREAS, due to these savings the General Contractor's contract will be reduced
18 by the sum of$396,137.52; and
19 WHEREAS, the City's construction costs will be increased by $367,780.00, saving
20 the City a net sum of$28,357.52; and
21 WHEREAS, Change Order #5 was to include the approval of an additional
22 $50,000.00 for contingency work; and
23 WHEREAS, the City of Boynton Beach has reviewed Change Order #6 and has
24 determined that the contract changes set forth therein are both necessary and appropriate.
25 NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF
26 THE CITY OF BOYNTON BEACH, FLORIDA, THAT:
27
Section 1.
The foregoing "Whereas" clauses are hereby ratified and confirmed as
28 being true and correct and are hereby made a specific part of this Resolution upon adoption
29 hereof.
30
Section 2.
The City Commission of the City of Boynton Beach, Florida does
T:ICAIRESOICHANGE ORDERSlLibrary Project CO 6.doc
II
1 i hereby authorize and direct the approval and execution of Change Order 006 decreasing the
2 General Contractor's contract with Sessoms Construction for the Library Expansion Project
3 by $396,137.32 and increasing the City's construction costs in the amount of $367,780.00
4 for a total savings of $28,357.52 due to owner direct purchases, a copy of which is attached
5 hereto as Exhibit "A".
6
Section 3.
The City Commission approves $50,000.00 for contingency work
7 requested in Change Order #5.
8
Section 4.
The new contract sum, including all pnor change orders, owner
9 equipment, owner direct purchases and contingency is $7,237,589.48.
10
Section 5.
This Resolution shall become effective immediately upon passage.
11
PASSED AND ADOPTED this ~ day of November, 2006.
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
CITY OF BOYNTON BEACH, FLORIDA
1;;7:?t~
Vice Mayor
c-....~.~.
.::~...
-,
--
/('-6 r
~-:J'"
1"........
j-':~~~,~...,-.~_.~~.._~.' ,',
Commissioner
~ ;;-.
-
... . ..~._-_/
~
.......". '.-
}-.-",
r-L
/~---
Commissioner
ATTEST:
t
'\<,'" .<'-::_0_.,.-,:-,".,'..-::,/
T:IC~~SO~GE ORDERSlLibrary Project CO 6.doc
.AIA Document G70r" - 2001
EXHIBIT A
KO&' - (q 7
Change Order
PROJECT (Name and nddress):
Boynton Beach Library
208 South Seacrest Blvd.
Boynton Beach, FL 33435
TO CONTRACTOR (Name and address):
Sessoms Construction
7485 Davie Rd. Ext.
Hollywood, FL 33024
CHANGE ORDER NUMBER: 006
DATE: October 31,2006
OWNER: ~
ARCHITECT: ~
CONTRACTOR: ~
FIELD: D
OTHER: D
ARCHITECT'S PROJECT NUMBER: 0320802
CONTRACT DATE: May 04, 2005
CONTRACT FOR: General Construction
THE CONTRACT IS CHANGED AS FOLLOWS:
(Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives)
A) Fire Resistive Cementious Fire Spray........................ .......................................................... ............$8,947.00
B) Rexel Cons. Electrical Supply (Sales Tax Savings Reduction) ........................ ......................................($29,798.70)
C) Electrical Supplies (Sales Tax Savings Reduction) ..... ............................... .....................................($195,960.00)
D) YKK AP (Sales Tax Savings Reduction) ......... ................................... ................... .........................($45,629.82)
E) Plan Reproduction ..................................... .... . ..................... ..................... .................. ....$305.00
F) Elevator Dimensions.................... ................................................................................. ......... ...$3,786.00
G) Stain Wood Doors ......................... ............................... ...................... ..$5,831.00
H) Spyder double tie backs ..................... ... ............... ......... .................... ........... .........($1,600.00)
I) Trane Direct purchase (Sales Tax Savings Reduction) ... ...... ....... ...................... . .................. ........ ....($100,560.00)
J) Ships Ladder .............................................. ...... ...................... .................... ....................... ....$5,709.00
K) Credit for Security Gates ....... .... ............... ................... . .................... . .................... ..........($30,492.00)
L) Towel Dispencsers ............ ...................... .................. .....................................................................................$867.00
M) Self Closing Taps................. ............. ... .............. ......... ..................... ................... ....................$923.00
N) Additional Conduit for data ...................... ................ ......... .................... .................... .......... ......$13,750.00
0) Credit Permit Fees ................................... ........... .... ..................... ........... .......... ....$(32,215.00)
The original Contract Sum was
The net change by previously authorized Change Orders
The Contract Sum prior to this Change Order was
The Contract Sum will be decreased by this Change Order in the amount of
The new Contract Sum including this Change Order will be
The Contract Time will be increased by Zero ( 0 ) days.
The date of Substantial Completion as of the date of this Change Order therefore is January 21, 2007
$
$
$
$
$
5,727,485.00
1,351,325.00
7,078,810.00
(396,137.52)
6,682.672.48
1IC'r'f~'d"""'ft_t:lm'flgeS'tJrttre-eunttlltt~-eorrtrnt:r'l'irreurtlu:mmre_aximmrr1'rtce-wtrtr:l1
how-eoo...lMlIhefi..e~4:"_ie..(;RoRg&.QiRl€,,_,,i-I_...Rd-lirHo-Ao_~.."""~..otlt<he.Qwfter__&
Qmtam..b;-ift..w..ieh-ease-a-€h1mge-<3rd~eetlted-to-3ttper~e-etnr.'l"LI u...l;on-C-itftnge-Direetive:-
AlA Document G701 TM - 2001. Copyright @ 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AIAIIII
Document Is protected by U.S. Copyright law and International Treaties. Unauthorized reproduction or distribution of this AlA- Document, or any 1
portion of it, may result In severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document
was produced by AlA software at 10:59:25 on 11/0212006 under Order No.1000228140_9 which expires on 3/21/2007, and is not for resale.
User Notes: (4068729110)
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
SchenkelShultz Architecture
ARCHITECT (Firm name)
1300 N. Congress Avenue, West Palm
Beach, FL 33409
ADDRESS
)
I!-D'J.. 0(,
Sessoms Construction
CONTRACTOR (Firm name)
7485 Davie Rd. Ext., Hollywood, FL
33024 .
ADD~~
~ (Signaru~
I.Jit t;;tJ~~Il7-S
(Typed name)
lI/oJ/Ob
DATi! I
City of Boynton Beach
OWNER (Firm name)
208 South Seacrest Blvd., Bounton
Beach, F[, 3435
ADD S
Samuel
(Typed
BY (S gnarure)
KURT BRESSNER
aANACER
(Type ON BEACH. FL
(/ ..~ -06
DATE
DATE
CITY ATTORN~
AlA Document G701 1M - 2001. Copyright @ 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AlAe
Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AlAe Document, or any 2
portion of It, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document
was produced by AlA software at 10:59:25 on 11102/2006 under Order No.1000228140_9 which expires on 3/21/2007, and is not for resale.